R.W. Granger & Sons, Inc. v. Eastern Massachusetts Carpenters & Carpenters Local 275

686 F. Supp. 22, 1988 U.S. Dist. LEXIS 5762, 1988 WL 41322
CourtDistrict Court, D. Massachusetts
DecidedApril 21, 1988
DocketCiv. A. 87-2174-H
StatusPublished
Cited by8 cases

This text of 686 F. Supp. 22 (R.W. Granger & Sons, Inc. v. Eastern Massachusetts Carpenters & Carpenters Local 275) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.W. Granger & Sons, Inc. v. Eastern Massachusetts Carpenters & Carpenters Local 275, 686 F. Supp. 22, 1988 U.S. Dist. LEXIS 5762, 1988 WL 41322 (D. Mass. 1988).

Opinion

MEMORANDUM AND ORDER

HARRINGTON, District Judge.

This matter is before the Court on the parties’ cross motions for summary judgment. The underlying dispute on which this lawsuit is based is a grievance filed by the Defendant on December 8, 1986, contending that the Plaintiff violated the parties’ collective bargaining agreement. For the reasons stated below, Defendant’s motion for summary judgment is granted.

I. STATEMENT OF FACTS

The material facts pertinent to the instant motions are not in dispute. The Plaintiff R.W. Granger & Sons, Inc., (“Granger”) is a general contractor engaged in the construction industry. The Defendant Eastern Massachusetts Carpenters and Carpenters Local 275 (the “Union”) is a voluntary coalition of ten local unions all of whom are affiliated with the United Brotherhood of Carpenters and Joiners of America. From 1976 until a date to be resolved by this Order, the Association of General Contractors of Massachusetts, Inc. (“AGC”), a trade association of general construction contractors, has represented Granger in collective bargaining with the Union. The AGC is a multiemployer bargaining unit of which Granger was a member.

Sometime after September 5,1986, Granger subcontracted concrete form work at Granger’s Babson College job site from a subcontractor who did not have an agreement with the Union. The Union notified Granger that the subcontract violated a collective bargaining agreement to which Granger and the Union were bound. Granger replied that it was not bound by any collective bargaining agreement prohibiting the subcontract in question.

From 1976 to at least 1983, Granger authorized AGC to negotiate on its behalf with various unions, including the Eastern Massachusetts Carpenters. The Union and AGC executed a collective bargaining agreement effective August 1, 1983 through May 31, 1985. The parties agree that Granger was bound by the 1983-1985 agreement.

The termination clause of the 1983-1985 agreement states:

This agreement will expire May 31,1985, but if neither party gives notice in writing to the other party on or before March 31, 1985 then this agreement will continue in effect until May 31, 1986, and so on each year thereafter unless on or before March 31st of each year thereafter a notice is given by either party ...

In 1985 Granger did not give the Union written notice of a desire to negotiate new terms to the agreement. Accordingly, pursuant to the termination clause, the agreement continued for another year.

In 1984 Granger withdrew its bargaining authorization from AGC, but neither Granger nor AGC gave the Union written notice of the withdrawal. AGC, however, did not include Granger on any list it presented to any union representing contractors who had authorized AGC to bargain for them.

Early in 1986 the Union notified AGC of its intent to negotiate a successor agreement. The AGC and the Union arrived at an agreement effective June 1, 1986 through May 31, 1989. Granger’s name was not on the list of contractors which AGC presented to the Union as having authorized AGC to bargain on their behalf for the 1986-1989 agreement. On September 5, 1986, Granger provided written notice directly to the Union for the first time of its withdrawal from the AGC, and of its repudiation of any collective bargaining agreement which it had with the Union.

In March 1987 an arbitration proceeding was held before Arbitrator Edward C. Pinkus pursuant to the grievance. In its Answer to the Complaint in Arbitration and at oral argument, Granger took the position that the Arbitrator had no jurisdiction to determine whether a contract existed between the parties. Granger filed an Answer to the Union’s Complaint in Arbitra *25 tion under protest to protect itself against an ex parte determination by the Arbitrator.

On July 31, 1987, Arbitrator Edward C. Pinkus determined that Granger was bound to the 1986-1989 collective bargaining agreement, and that it had violated that agreement by subcontracting concrete form work to a subcontractor who did not have a collective bargaining agreement with the Union.

Plaintiff filed this suit in August, 1987 to seek a determination that the arbitrator exceeded his jurisdiction in entering the award for the Union, and to vacate the arbitrator’s award. Plaintiff also prays that this Court declare that it is not bound to the 1986-1989 collective bargaining agreement.

II. LAW AND ANALYSIS

A. Issues

There are four issues before this Court: (1) whether the plaintiff submitted itself to the Arbitrator’s jurisdiction for the purposes of determining whether or not a collective bargaining agreement existed between the parties; (2) whether the plaintiff general contractor continued to be bound to the labor contract which the defendant negotiated through the multi-employer unit solely because the plaintiff failed to provide the defendant Union with notice of its withdrawal from the multi-employer unit; (3) whether the National Labor Relations Board’s (the “Board”) ruling in John Deklewa & Sons, 282 N.L.R.B. No. 184, 124 L.R.R.M. 1185 (1987), aff'd sub nom. International Association of Bridge, Structural and Ornamental Iron Workers v. NLRB (Deklewa), 843 F.2d 770 (3d Cir.1988), which reversed previous case law by holding that pre-hire agreements pursuant to Section 8(f) of the National Labor Relations Act (the “Act”) are no longer voidable at will by either party, is controlling law; and (4) if Deklewa is controlling, should it be applied retroactively.

B. Arbitrability

Arbitrability is the determination of the arbitrator’s jurisdiction to resolve a grievance on the merits. The threshold issue of whether there is an obligation to arbitrate a dispute is a matter of contract and is for a court, not an arbitrator to decide. AT & T Technologies Inc. v. Communication Workers of America, 475 U.S. 643, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986). The parties may, however, submit the substantive arbitrability issue to the arbitrator. United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 583 n. 7, 80 S.Ct. 1347, 1353 n. 7, 4 L.Ed.2d 1409 (1960); Metal Products Workers Union, Local 1645 v. Torrington Co., 358 F.2d 103 (2d Cir.1966). If the Court determines that the parties did agree to have the arbitrator resolve the arbitrability issue, the judicial review of the arbitrator’s ruling on substantive arbitrability should be as circumspect as its review of the arbitrator’s resolution on the merits of the grievance. See Piggly Wiggly Operators’ Warehouse Inc. v. Independent Truck Drivers Union Local No. 1, 611 F.2d 580, 584 (5th Cir.1980); Teamsters Local 117 v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
686 F. Supp. 22, 1988 U.S. Dist. LEXIS 5762, 1988 WL 41322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rw-granger-sons-inc-v-eastern-massachusetts-carpenters-carpenters-mad-1988.