Russo v. Enterprise Realty Co.

199 N.E.2d 689, 347 Mass. 655, 1964 Mass. LEXIS 815
CourtMassachusetts Supreme Judicial Court
DecidedJune 23, 1964
StatusPublished
Cited by3 cases

This text of 199 N.E.2d 689 (Russo v. Enterprise Realty Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Russo v. Enterprise Realty Co., 199 N.E.2d 689, 347 Mass. 655, 1964 Mass. LEXIS 815 (Mass. 1964).

Opinion

Beardon, J.

This is a bill in equity brought by the buyer for the specific performance of a contract to sell land. The judge filed a report of material facts. From a decree granting relief to the plaintiff the defendant has appealed. The evidence is reported.

[657]*657The facts appear as follows: On January 11, 1960, after extensive negotiations Russo agreed in writing to buy, and Enterprise Realty Co., Inc. (Enterprise) to sell, for $20,000, a certain parcel of land (lot B) on the north bank of the Mystic River in Medford. The plaintiff wished to use the land for the operation of a marina. By the same agreement an option was granted to Russo to purchase for an additional $10,000 another plot (lot C) which adjoined lot B on the latter’s eastern side.

Lots B and C occupied respectively the southwestern and southeastern corners of a large undivided tract of land (lot 15) owned by Enterprise under a registered land title. Lot 15 ran from the Revere Beach Parkway south to the Mystic River. The parties contemplated that Enterprise would build a road from the Revere Beach Parkway to the Mystic River along the western edge of lot 15. The sale and option of lots B and C were predicated in part upon the filing with and approval by the planning board of Medford (board) of a subdivision plan of lot 15. A private road connecting lot B to the public road system was necessary in order to secure board approval. Such approval was also required in order to record a deed to lot B in the land registration office. Attached to and made a part of the agreement of sale was a drawing entitled “Plan of Land Russo’s Marine Mart” (the attached plan), which showed lots B and C, the remaining portion of lot 15, and the contemplated road designated as a “50' roadway.” The agreement contains the following: ‘ ‘ There is to be excepted from the premises to be conveyed [lot B] so much thereof as may be required by the Seller so as to comply with the requirements of the Planning Board of . . . Medford ... so as to validate the creation of the proposed street running from Revere Beach Parkway substantially as shown on said plan [and] obtain the approval by said Planning Board ... of the plan to be filed with the Planning Board creating said proposed street so that the same may be filed for registration with Middlesex South Registry District so as to permit the Seller to subdivide its remaining land shown on [658]*658said plan .... As appurtenant to the premises to be conveyed the Seller shall grant to the Buyer the right to use the proposed street . . ..” Also: “ The Buyer agrees that he will pay to the Seller an amount equal to twenty per cent (20%) of the cost to the Seller for the installation of water and other utility lines, sewerage and drainage lines from Revere Beach Parkway or from such other existing terminus to a point in the private street at or near the premises to be conveyed hereunder.”1 The contract stipulated July 28, 1960, as the closing date “unless otherwise agreed upon in writing. . . . [T]ime is of the essence of this agreement.” The parties further agreed that “if at closing time . . . [the subdivision] plan shall not have been approved by the . . . [b] card . . . and the time within which an appeal from such decision shall not have terminated, then the closing time shall be postponed to a date . . . [fifteen days after either the decision on the appeal or approval by the board].” Finally, the contract provides that “ [i]f the Seller shall be unable to give title or to make conveyance as herein stipulated, then any payments made under this agreement shall be refunded and all other obligations of the parties hereto shall cease and this agreement shall be void . . ..”

Enterprise had submitted to the board in 1959 a subdivision plan (the initial plan) drawn for it by one H. J. Nicholson, an experienced civil engineer and a former consultant to the board. On October 15, 1959, the board first informed Enterprise that the proposed roadway would have to be widened from 50 feet to 60 feet. Before submission of the initial plan Nicholson had estimated that an expenditure of between $30,000 and $40,000 would be sufficient to secure board approval of the plan. There is no evidence that such an estimate was ever communicated to Russo. In addition to the 60 foot roadway the board requested that other changes be made in the initial plan involving expense [659]*659beyond what was originally estimated. In one such change the board required construction of the drainage system which would cost some $38,000 at the time of the building of the road. Nicholson had originally anticipated that the drainage could be put in at a later stage in the development of Enterprise’s remaining portion of lot 15. The board also required present construction of the water mains and the sewerage system. From what appears the board made all the requests for changes prior to January 11, 1960, the date of the purchase and sale agreement. With the changes incorporated the road with improvements was to cost some $105,000.

A board hearing on a revised definitive plan submitted by Enterprise and dated February 5,1960, which embodied the changes as requested, was held on April 27, 1960. Shortly thereafter the board tentatively approved the revised plan. Final approval could not be granted until either a construction bond was posted by Enterprise or the road and other improvements were actually constructed. The bond has never been posted nor the road ever constructed. As a result the application for approval was dismissed by the board without prejudice on September 13,1961.

Extensions of the time of performance of the contract running until January 31,1962, were mutually agreed upon by the parties. Since that date Enterprise has regarded its contractual obligation at an end.

On September 6,1960, the parties agreed that “until September 7, 1961, or until the aforesaid purchase and sale agreement, as amended, is terminated, whichever event occurs first, ’ ’ Russo should have the right to occupy and improve lots B and C. The plaintiff went on the premises, dredged the land, put in fill, made considerable grading of a large area so as to make it usable for his operation . . . built a [mjarina and hot-topped the roadway leading into the same . . He spent some $53,500 on these improvements until March 6, 1962, as indicated by evidence which was properly admitted.

The final decree ordered Enterprise to resubmit the definitive plan dated February 5, 1960, to the board for [660]*660approval. Within thirty days after such, approval the defendant was directed either to post the necessary construction bond or to begin construction subject to weather limitations of the road designated in the plan and convey lots B and C to the plaintiff by a deed entitling him to a certificate of title. Until the conveyance of the land Enterprise was enjoined from terminating the license to occupy granted on September 6,1960. A counterclaim based upon a wrongful occupancy by Russo was dismissed.

1. The judge correctly concluded that Enterprise was obligated by contract to construct “the proposed street running from Revere Beach Parkway substantially as shown on said plan.” While the purchase and sale agreement does not contain an express promise by Enterprise to build the street, such an obligation was clearly intended by the parties. “An omission to express an intention cannot be supplied by conjecture.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGrath v. Braney
28 Mass. L. Rptr. 630 (Massachusetts Superior Court, 2011)
Sonoran Scanners, Inc. v. Perkinelmer, Inc.
585 F.3d 535 (First Circuit, 2009)
R & D Corp. v. New Bedford Redevelopment Authority
437 N.E.2d 556 (Massachusetts Appeals Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.E.2d 689, 347 Mass. 655, 1964 Mass. LEXIS 815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/russo-v-enterprise-realty-co-mass-1964.