R & D Corp. v. New Bedford Redevelopment Authority

437 N.E.2d 556, 14 Mass. App. Ct. 944, 1982 Mass. App. LEXIS 1395
CourtMassachusetts Appeals Court
DecidedJuly 16, 1982
StatusPublished

This text of 437 N.E.2d 556 (R & D Corp. v. New Bedford Redevelopment Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R & D Corp. v. New Bedford Redevelopment Authority, 437 N.E.2d 556, 14 Mass. App. Ct. 944, 1982 Mass. App. LEXIS 1395 (Mass. Ct. App. 1982).

Opinion

The Trial Judge’s Findings

(A) On December 18, 1970,3 R&D made a contract (the 1970 contract) with the Authority to buy Lot C shown on a plan (the 1970 plan) recorded on September 24, 1970. On the same day the Authority conveyed Lot C to R & D by quitclaim deed (the 1970 deed). Lot C was part of a redevelopment project, by which “the Authority proposed to extend . . . the shortline in the [project] area ... by constructing a bulkhead along” the Federal bulkhead line for “1650 feet and then to fill in the area landward [to the west] of the bulkhead, thereby preparing the adjacent parcels for industrial” and other specified uses. “Part of the bulkhead (1150 feet) was to be . . . adjacent to water of twenty-foot draft, while five hundred feet of bulkhead . . . [were] to adjoin water of thirty-foot draft.” The judge also found that “[t]he construction of the bulkhead, filling of the land, and the division of the [p]roject area into lots . . . [were] reflected in the” 1970 plan. (This finding, as later language of the judge shows, must mean at most only that the 1970 plan sets out the general relationship of Lots C and D, the bulkhead line, and adjacent land.) “The Authority hoped to interest fish processors ... in purchasing land in the [p]roject area” and approached R & D to see if it would purchase a lot for use by Tichon Seafood Corp. (Tichon Seafood). This corporation was controlled and owned by the Tichon family, which also owned R&D.

(B) Negotiations began with R&D about the possible sale to it of various “lots adjacent to twenty-foot draft water” (on which, in 1967 and 1969, R&D in fact made offers). In the spring of 1970, however, R&D made an offer to purchase Lot C which, for the most part, was near water of thirty-foot draft. “Although the Authority was. . . reluctant to sell the entire” frontage on 30-foot depth water to one purchaser, it finally accepted R & D’s offer on May 11, 1970. Thereafter (before December 18, 1970, the date set for the closing) R&D submitted (as required by the [945]*945proposed 1970 contract, for the Authority’s approval) plans for the plant which it proposed to build on Lot C.

(C) The Authority received on July 28, 1969, from the Department of Public Works (DPW) of the Commonwealth a license to build a bulkhead (east of Lots C and D) and to fill adjacent land. One plan accompanying the license differed from the 1970 plan in showing only 480 feet of bulkhead along Lot C and the river where there was thirty-foot depth, instead of 500 feet. When the bulkhead in fact was built, and the adjacent land was filled, the completed bulkhead extended (approximately north and south) only about 464 feet along the thirty-foot depth section. “Before December 18 . . . the bulkhead had been substantially built, and the land behind it was being filled and graded, although [the Authority’s] formal acceptance of the . . . work . . . did not occur until July or August, 1971.” R & D’s plant was built by October, 1971.

(D) On December 7, 1970, the Authority conveyed to the city of New Bedford (the City) the strip of land five feet wide next east of the eastern boundary of Lot C on which the seaward (east) part of the bulkhead rests. The Authority then also gave the City an easement across Lot C for a box culvert “to carry runoff from . . . adjacent streets into the Acushnet River.” (This conveyance also gave to the City an easement twenty feet wide over Lot D [just south of Lot C] from Hassey Street [which lies to the west of Lots C and D] to the bulkhead area. By the acceptance of this conveyance the City undertook to keep the bulkhead in repair until June 28, 2015.)

(E) On December 18, 1970, the Authority executed (a) the 1970 contract, the provisions of which survived the 1970 deed, and (b) the 1970 deed. Under the 1970 contract R&D was obligated to make carefully specified improvements on Lot C “in accordance with plans approved by the Authority.” A certificate of completion of these R&D improvements was issued on December 4, 1972.

(F) R & D paid “no attention to its northeastern boundary . . . until . . . 1975, when the abutter to the north (Ell Vee Dee Freezer Corp.)” built a fence along part of the northern boundary of Lot C. R&D then had a survey made and markers were placed. One marker indicated that the northeast comer of Lot C (as shown by the 1970 plan) was under water. R & D’s officers took no notice of the marker and did not discuss the situation with the surveyor whom they had hired.

(G) In 1977 Tichon Seafood decided to build an addition to its plant along the bulkhead to the north of its then existing building. Examination of Lot C at that time showed that R & D’s frontage on the bulkhead (thirty-six feet less than that indicated on the 1970 plan) was insufficient for the proposed addition. R&D reported this to the Authority and asked that the Authority build an additional thirty-six feet of bulkhead and fill the adjacent land. The Authority refused, and this suit resulted.

(H) The facts concerning the northeast corner of Lot C were confirmed by a 1978 survey which revealed (1) that the total area of Lot C, as [946]*946shown on the 1970 plan, was 280,962 square feet and that the total area under water was only about 3,000 square feet, and (2) that the bulkhead frontage was only about 464 feet.

(I) Officers of R & D “were on Lot C during the construction of the” existing building and were there regularly “after its completion.” They had opportunity to observe the site and the bulkhead for seven years before R & D made claim against the Authority.

The Trial Judge’s Rulings

The trial judge made the following rulings among others.

(1) The 1970 deed and the 1970 contract each make reference to the 1970 plan. “The [1970 p]lan is merely a visual representation of the metes and bounds description contained in the [1970 c]ontract and the [1970 d]eed . . . with the exception . . . that the bulkhead is represented not as a single . . . line, but as a strip 5.00 to 5.03 feet in width.”

(2) The Authority by the 1970 deed purported to “remise, release and quitclaim” Lot C to R & D. This effected a conveyance by the Authority of “all of its interest in Lot C.” (This, of course, included the land west of and next to the whole 500 feet [north and south] of the City’s strip of land about five feet wide.) See finding (D), supra. See also G.L. c. 183, §§ 11, 17. The trial judge did not find it necessary, nor do we, to decide whether there could be private ownership in land below the historic low water marks. See Boston Waterfront Deo. Corp. v. Commonwealth, 378 Mass. 629 (1979). He concluded merely that, as between the Authority and R & D, the latter had good title to the area, even though there had been no filling of, or building upon, the submerged area.

(3) The easterly boundary of Lot C, defined in the 1970 deed, as “south 14°, 26' 00" east in the west line of said [b]ulkhead 500.00 feet to Lot D of said [p]lan,” must have reference to the west line of the bulkhead area conveyed to the City as indicated with precision on the 1970 plan. It cannot have reference to any physical aspect of the bulkhead as a “monument” (which would control courses and distances) for the bulkhead structure is a broad physical mass in “width . . . over fifty feet.” (Thus the precise metes and bounds set out in the 1970 deed [consistently with the 1970 plan] were controlling. See Park, Real Estate Law §§ 241-246, especially at 317 [1981]. Compare

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horace Case v. Arthur E. Morrisette
475 F.2d 1300 (D.C. Circuit, 1973)
Stop & Shop, Inc. v. Ganem
200 N.E.2d 248 (Massachusetts Supreme Judicial Court, 1964)
Norton v. West
394 N.E.2d 1125 (Massachusetts Appeals Court, 1979)
Boston Waterfront Development Corp. v. Commonwealth
393 N.E.2d 356 (Massachusetts Supreme Judicial Court, 1979)
Overly v. Treasurer & Receiver General
181 N.E.2d 660 (Massachusetts Supreme Judicial Court, 1962)
Thomas v. Christensen
422 N.E.2d 472 (Massachusetts Appeals Court, 1981)
Noble v. Googins
99 Mass. 231 (Massachusetts Supreme Judicial Court, 1868)
Russo v. Enterprise Realty Co.
199 N.E.2d 689 (Massachusetts Supreme Judicial Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
437 N.E.2d 556, 14 Mass. App. Ct. 944, 1982 Mass. App. LEXIS 1395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-d-corp-v-new-bedford-redevelopment-authority-massappct-1982.