Rush v. Norfolk Electric Co.

874 N.E.2d 447, 70 Mass. App. Ct. 373
CourtMassachusetts Appeals Court
DecidedOctober 4, 2007
DocketNo. 06-P-1105
StatusPublished
Cited by2 cases

This text of 874 N.E.2d 447 (Rush v. Norfolk Electric Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rush v. Norfolk Electric Co., 874 N.E.2d 447, 70 Mass. App. Ct. 373 (Mass. Ct. App. 2007).

Opinion

Cowin, J.

We address a claim for indemnification following a judgment for damages arising from significant physical injuries sustained by the plaintiff, Michael Rush, when he was working at the Deer Island secondary waste treatment project of the Massachusetts Water Resources Authority (the authority). Plaintiff Colleen Rush also obtained a judgment for loss of consortium. Acting on a posttrial motion for summary judgment, a judge of the Superior Court, in a comprehensive and well-reasoned opinion, allowed the claim of the codefendant, Modern Continental Construction Co., Inc. (Modem Continental), for indemnification by the third-party defendant, Harding & Smith, Inc. (Harding & Smith), but only with respect to Colleen Rush’s judgment for loss of consortium and Modem Continental’s expenses of defending both the Michael Rush and the Colleen Rush claims. Asserting that it is entitled to indemnification with respect to the Michael Rush judgment also,3 Modem Continental filed a timely notice of appeal. We affirm.

1. Background. The underlying facts are not disputed. The authority contracted with Modern Continental to perform as general contractor on the project, with those parties entering into a contract containing general conditions set forth in 109 single-spaced printed pages. Modem Continental subcontracted electrical work to the codefendant, Norfolk Electric Company, Inc. (Norfolk Electric), and plumbing work to the third-party defendant, Harding & Smith. Harding & Smith in turn entered into a sub-subcontract with the fourth-party defendant, New England Insulation Co. (NEI), under which NEI would provide insulation and piping systems for the project. Plaintiff Michael Rush was employed by NEI at the time of his injuries.

Rush commenced an action alleging that his injuries were attributable to the negligence of both Modern Continental and Norfolk Electric. Liberty Mutual Insurance Company (Liberty Mutual), Norfolk Electric’s general liability insurer, assumed the defense of both defendants after Modem Continental, pursuant to an indemnification agreement, tendered the defense to Norfolk Electric. A Superior Court jury found that each defend[375]*375ant was thirty-seven and one-half percent negligent, while Rush was twenty-five percent contributorily negligent. The jury determined that Rush had incurred damages in the amount of $1,153,445; reduced to account for his negligence of twenty-five percent, see G. L. c. 231, § 85, he was awarded $865,083.75 before the addition of interest. As indicated, Colleen Rush received a judgment of $25,000 before interest for loss of consortium. Liberty Mutual paid in full the judgments entered against both defendants,4 but did so in the name of Modem Continental alone.

Various claims for indemnification were reserved by agreement until the plaintiffs’ claims were resolved. By means of a third-party complaint, Modem Continental asserted a claim for complete indemnification (judgment and defense costs) against Harding & Smith pursuant to the subcontract between those parties.5 Harding & Smith in turn filed a fourth-party complaint seeking indemnification pursuant to its sub-subcontract with NEI.6 As indicated, the judge allowed Modern Continental’s indemnification claim only in part. In addition, he allowed Harding & Smith’s claim against NEI for the same amounts for which Harding & Smith was found to be liable to Modem Continental.7 Disputes regarding the amount of defense costs, including attorney’s fees, have been settled, and all that remains is Modem Continental’s contention that it has been deprived erroneously of full indemnification by Harding & Smith.

2. The indemnification provisions. Modem Continental’s claim that it is entitled to full indemnification from Harding & Smith is based principally on paragraph 1.3 of the parties’ subcontract. [376]*376Paragraph 1.3 appears in Article I, which is entitled “Work to be performed.” That paragraph states in relevant part:

“Subcontractor [Harding & Smith] does further agree to be bound to the General Contractor [Modem Continental] by the aforementioned General Contract Documents and all other instmments herein referred to and further to assume toward the General Contractor all the obligations and responsibilities pertaining to the work that the General Contractor by the aforesaid General Contract Documents has assumed to the owner including the furnishing of such warranties and guarantees as are required in the General Contract Documents for the work of this subcontractor” (emphasis in original).

The paragraph continues by providing that Harding & Smith shall, with respect to the work to which it committed itself, comply with all of the directives of Modern Continental, and extend to Modem Continental all of the rights, privileges, and immunities which the owner (the authority) enjoys under its contract with Modem Continental.

Pursuant to this language, according to Modem Continental, each and every part of the general contract applies to the plumbing work undertaken by Harding & Smith. This includes paragraph 6.29.1 of the said general contract which provides in relevant part:

“To the fullest extent permitted by Laws and Regulations, the Contractor [Modem Continental] shall indemnify and hold harmless the Authority (the owner) and the CM [defined elsewhere as the construction manager] and their consultants, agents and each of their directors, officers and employees from and against all claims, damages, losses and expenses, direct, indirect and consequential (including but not limited to fees and charges of engineers, architects, attorneys and other professionals and court costs) arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (a) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property including the loss of use, and (b) is caused in whole or in part by any negligent act or omission of the Contractor, [377]*377any Subcontractor, any person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, regardless of whether it is caused in part by a party indemnified hereunder or arises by or is imposed by Laws and Regulations regardless of the negligence of any such party.”

The language thus obligated Modern Continental to hold harmless and to indemnify the authority with respect to claims for personal injuries or property damage incurred in connection with the work performed by Modem Continental on the project if such personal injuries occurred, even in part, as a result of the negligence of Modern Continental or any person or entity for which it was responsible. By means of paragraph 1.3 of its subcontract with Harding & Smith, Modem Continental argues, it effectively obtained from Harding & Smith indemnification that is the equivalent of what Modem Continental provided to the authority in the event that the negligence of Harding & Smith or the negligence of those for whom it was responsible contributed in any way to losses or expenses suffered by Modem Continental. An undertaking by a subcontractor to indemnify for the entirety of a loss or expense notwithstanding that its negligence is only partially responsible is legally permissible. See G. L. c. 149, § 29C; Herson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hayes v. CRGE Foxborough, LLC
167 F. Supp. 3d 229 (D. Massachusetts, 2016)
Noonan v. Wonderland Greyhound Park Realty LLC
723 F. Supp. 2d 298 (D. Massachusetts, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
874 N.E.2d 447, 70 Mass. App. Ct. 373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rush-v-norfolk-electric-co-massappct-2007.