RURAL WATER DIST. v. Miller Paving & Const., LLC

190 P.3d 973
CourtCourt of Appeals of Kansas
DecidedAugust 22, 2008
Docket98,890
StatusPublished

This text of 190 P.3d 973 (RURAL WATER DIST. v. Miller Paving & Const., LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RURAL WATER DIST. v. Miller Paving & Const., LLC, 190 P.3d 973 (kanctapp 2008).

Opinion

190 P.3d 973 (2008)

RURAL WATER DISTRICT NO. 3 OF MIAMI COUNTY, Kansas, Appellee,
v.
MILLER PAVING & CONSTRUCTION, L.L.C., Appellant.

No. 98,890.

Court of Appeals of Kansas.

August 22, 2008.

*975 Cline I. Boone, of Shawnee, for appellant.

Daniel D. Covington, of Anderson & Byrd, L.L.P., of Ottawa, for appellee.

Before HILL, C.J., PIERRON and GREEN, JJ.

GREEN, J.

Miller Paving and Construction, L.L.C. (Miller) appeals from the trial court's judgment in favor of Rural Water District No. 3 of Miami County, Kansas (Water District) on the Water District's claim of negligence in the amount of $6,116.33. On appeal, Miller contends that the trial court erred in determining that Miller was negligent. In addition, Miller asserts that the trial court erred in determining that the Water District met its duty of care on all but two occasions. We disagree. Accordingly, we affirm.

Miller was the general contractor on a 14-mile gas line installation project for the City of La Cygne. The project lasted from approximately June 2004 to September 2004. During this time, the Water District received tickets from Kansas One-Call, notifying it that Miller would be doing work in an area where the Water District had water lines. The Water District was a member of and had a contractual agreement with Kansas One-Call. Under its contract with Kansas One-Call, the Water District had agreed that once it was notified of a contractor's work in a particular area, it would locate, mark, or otherwise provide the approximate location of the underground facilities in a manner as to allow the use of hand-dug test holes to determine the precise location of the underground facility.

Rick Courtney, who owned Courtney Construction, was the water line locator for the Water District. Courtney picked up the Kansas One-Call tickets and proceeded to locate the water lines in the areas where work was being done by Miller. Doug Simms, Miller's foreman on the gas line installation *976 project, met with Courtney and showed him a map of the area where Miller would be installing gas lines. Courtney then showed Simms the general location of the Water District's water lines on the map. Courtney also physically marked the approximate location of the water lines with flags.

The water lines located in the area of the gas line installation project had been in place since the late 1960's, were made of PVC plastic, and did not have tracer wire. In locating these water lines, Courtney referred to the Water District's maps and diagrams. According to Courtney, however, the Water District's maps and diagrams were vague and basically told him on which side of a road a water line was located. As a result, Courtney had to rely on his knowledge about the location of several of the water lines during previous repairs. Moreover, Courtney looked for ditch lines and differentials in soil conditions that would indicate where the water lines had been placed.

Kevin James, the managing member of Miller, acknowledged that Courtney had told him that the water lines could not be located with any accuracy.

Apparently, during his contact with Miller, Courtney had stated on numerous occasions that the plastic lines could not be accurately located due to the absence of tracer wire in the pipes. James testified about his experience in using two particular pieces of equipment to ascertain the location of underground utility lines. According to James, when PVC pipes do not have tracing wires, the equipment can be used to attempt to induce a signal in the pipes and then to detect the location of the signal within the pipe. Nevertheless, James did not use this equipment to detect the location of the water lines during the gas installation project. Moreover, although Courtney had heard of the concept of using sonar technology to detect the location of underground utility pipes that did not have tracer wire, he had never been trained on such equipment.

During the course of the gas line installation project, Miller struck and damaged the Water District's water lines approximately 14 times. Two of the water lines that Miller struck had never been marked by Courtney. James acknowledged that on two or three of the strikes, Miller had hand exposed the water line before striking it. Courtney testified that several of his markings were very close to the location of the water lines (6 inches to 3 feet) and that none of his markings were farther than 5 to 7 feet from the water lines. Simms testified about each line strike and indicated that, aside from the water pipes that Courtney had neglected to mark and the pipes that Miller had hand exposed before striking them, Courtney's markings were 1 to 5 feet from where the strikes had occurred.

When Miller would strike a water line, Simms would call Courtney who would go to the site for repairs. James testified that on all but one occasion, Miller dug out the water line for Courtney to make repairs. On the other hand, Courtney testified that in approximately 50 percent of the strikes, Miller would assist in exposing the water line so that repairs could be made. Courtney testified about the repairs he made after each water line strike and indicated that Miller helped him with the actual repairs on several of the water line strikes. Based on Courtney's testimony, when Miller struck the water lines, the Water District sustained damages in the form of lost water from the strike, parts used to repair the water lines, additional water used to flush out the water lines, and the amount charged by Courtney for the service call.

In September and October 2004, the Water District sent out invoices to Miller for the damages that it claimed resulted from Miller's strikes to the water lines. In March 2005, the Water District sued Miller for negligence. Based on the pretrial order in this case, the Water District proceeded to a bench trial under three theories: (1) negligence; (2) strict liability for trespassing; and (3) liability for intentional trespassing for the damages that occurred after Miller became aware of the location of the water lines. Miller raised the defenses of comparative fault, failure to mitigate damages, and consent to enter. In addition, Miller counterclaimed that the Water District was negligent in failing to locate or in failing to properly mark its water lines and claimed *977 damages for its costs for downtime and for repairing the water lines. The Water District alleged the defense of comparative fault.

At the conclusion of the bench trial, the trial court found that Miller owed a duty to exercise reasonable care in its excavation to avoid causing injury to others or to the property of others. The trial court determined that an excavator's standard of care is to exercise ordinary care to locate the lines to avoid injury to the property of others when underground lines fall outside the scope of the Kansas Underground Utility Damage Prevention Act (KUUDPA) and when the lines are difficult to locate. Conversely, the trial court determined that the owner or operator of such underground lines does not owe to the excavator a per se duty to specifically locate and mark the lines. The trial court determined that the Water District had fulfilled its duty when it took reasonable steps to put Miller on notice that its water lines were located in the path of the intended areas of excavation and gave Miller its best information about the location of the water lines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wahwasuck v. Kansas Power & Light Co.
828 P.2d 923 (Supreme Court of Kansas, 1992)
Ling v. Jan's Liquors
703 P.2d 731 (Supreme Court of Kansas, 1985)
Willmar Gas Co. Inc. v. Duininck
53 N.W.2d 225 (Supreme Court of Minnesota, 1952)
State v. Bloom
44 P.3d 305 (Supreme Court of Kansas, 2002)
Sall Ex Rel. Sall v. T'S, Inc.
136 P.3d 471 (Supreme Court of Kansas, 2006)
Miller v. Bartle
150 P.3d 1282 (Supreme Court of Kansas, 2007)
LSF FRANCHISE REO I, LLC v. Emporia Restaurants, Inc.
152 P.3d 34 (Supreme Court of Kansas, 2007)
McCain Foods USA, Inc. v. Central Processors, Inc.
61 P.3d 68 (Supreme Court of Kansas, 2002)
R. B. Tyler Co. v. Southern Bell Telephone & Telegraph Co.
347 S.W.2d 669 (Court of Appeals of Kentucky, 1961)
Southwestern Bell Telephone, L.P. v. APAC-Kansas, Inc.
138 P.3d 1238 (Court of Appeals of Kansas, 2006)
Rural Water District No. 3 v. Miller Paving & Construction, L.L.C.
190 P.3d 973 (Court of Appeals of Kansas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
190 P.3d 973, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rural-water-dist-v-miller-paving-const-llc-kanctapp-2008.