Rufkahr Construction Co. v. Weber

658 S.W.2d 489, 1983 Mo. App. LEXIS 3557
CourtMissouri Court of Appeals
DecidedSeptember 6, 1983
Docket44618, 44666
StatusPublished
Cited by17 cases

This text of 658 S.W.2d 489 (Rufkahr Construction Co. v. Weber) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rufkahr Construction Co. v. Weber, 658 S.W.2d 489, 1983 Mo. App. LEXIS 3557 (Mo. Ct. App. 1983).

Opinions

SNYDER, Judge.

There was a rehearing by the court en banc of an appeal by defendant homeowners, Fred R. Weber, Jr. and Ann E. Weber, and a cross-appeal by the general contractor, Rufkahr Construction Company (Ruf-kahr), from a judgment of the Circuit Court of St. Louis County in a mechanic’s lien case arising out of a contract for the construction of appellants’ residence. The judgment is reversed in part, reversed and remanded in part and affirmed in part.

Rufkahr sued Fred R. Weber, Jr. and Ann E. Weber and others for breach of a residential construction contract and for imposition of a mechanic’s lien on the residential real estate. The Webers counterclaimed for breach of contract by reason of the alleged failure of Rufkahr to construct the house in a workmanlike manner and on time.

Roofing subcontractor Stephenson Roofing Company (Stephenson) was permitted to intervene as a defendant and joined the Weyerhaeuser Company (Weyerhaeuser) as a third-party defendant. Stephenson also cross-claimed against Rufkahr for the amount alleged to be due on the roofing subcontract. Rufkahr then counterclaimed against Stephenson for any damages awarded to the Webers against Rufkahr because of defects in the roofing.

The trial court rendered judgment: (1) for Rufkahr and against the Webers in the amount of $22,422.34 plus interest on its petition, the amount of the judgment to constitute a mechanic’s lien on the residential real estate; (2) for Stephenson and against Rufkahr in the amount of $7,016.99 plus interest on its cross-bill, the amount of the judgment to constitute a mechanic’s lien on the residential real estate; (3) for the Webers and against Rufkahr in the amount of $3,100.00 on the Webers’ counterclaim; and (4) dismissing as moot Stephenson’s third party petition against Wey-erhaeuser and Rufkahr’s counterclaim against Stephenson.

Appellants Weber raise five points of error. First, they contend that the trial court’s finding that respondent and cross-appellant, Rufkahr, substantially performed its obligations under the contract was against the weight of the evidence. Second, appellants charge the trial court improperly admitted parol evidence. Third, they contend “the trial court exceeded its jurisdiction” by denying appellants, on the grounds of laches, estoppel and unclean hands, the remedy of specific performance. Fourth, appellants assert that a mechanic’s lien in favor of Rufkahr was erroneously granted because Rufkahr did not comply with the disclosure requirements of § 429.-012(1) RSMo. 1978. Fifth, they contend that a mechanic’s lien in favor of interve-nor-respondent Stephenson is invalid because Stephenson failed to serve appellants as owners with a ten day written notice of intent to file a mechanic’s lien as required by § 429.100 RSMo. 1978.

Respondent Rufkahr raises two allegations of error in its cross-appeal. Rufkahr first maintains that the trial court erroneously awarded appellants $3,100.00 on Count II of appellants’ counterclaim because there was no proof of damages. Ruf-kahr also charges the trial court erred in dismissing its counterclaim against Stephenson because in the event the cause is remanded, the counterclaim against Stephenson ought to be reinstated.

The parties were asked to brief three specific issues for consideration by the en banc court:

[492]*492(1) Whether the October 25, 1976 letter signed by Marshall R. Ritchie which was an attachment to Exhibit W was received in evidence.
(2) If the Ritchie letter was received is a finding that the specified shingles were applied against the weight of the evidence?
(3) Was the statutory notice of the possibility of a mechanic’s lien sufficient when given to the Weber’s architect?

I. THE FACTS

On April 14, 1976 appellants and respondent Rufkahr entered into a contract for the construction of appellants’ home by Rufkahr as the general contractor. As increased by subsequent change orders, the total price for the construction of appellants’ home was $398,267.60.

The contract included specifications. Among other things, the specifications stated that the architect was the owner’s (appellants’) representative with authority to act on behalf of appellants to the extent provided in the contract documents. Another contract, the escrow agreement, required all changes from the specifications for the house to be made by written change orders. Construction of the house was to be substantially completed by December 1, 1976. Rufkahr was to pay $100 per diem as liquidated damages for each day beyond December 1 until the day of substantial completion.

A certificate of substantial completion was issued by one of the architects, George Winkler, on November 30, 1976. However, a “punch list” of a number of items which the architect or the owner felt needed to be corrected, was attached to the certificate. A number of the items on the punch list were never satisfactorily corrected or completed according to appellants.

The main dispute centered around whether the proper roofing was installed on the house. The contract called for the roof to be made of Certigrade No. 1 Blue Label shingles, 24" Royals, 100% heartwood, 100% clear and 100% edge grain. Rufkahr hired Stephenson as a subcontractor to install the roof.

Stephenson ordered the Blue Label shingles from the Weyerhaeuser Company along with some Red Label shingles, which are an inferior grade of wood shingles, the Red Label shingles to be used as under-coursing. The order actually called for “Blue Label” and “Red Label” but did not specify whether shingles or shakes1 were to be shipped, but Weyerhaeuser invoiced Stephenson for shingles. When the order came in, two employees of Stephenson, John Stephenson and Bill Tomschin, went to pick up the order. Mssrs. Stephenson and Tom-schin observed Blue Labels on the bundles of shingles, but did not see any Red Labels. However, nothing more than a casual; observation of the shingles was done to confirm that all of the shingles were indeed Certi-grade No. 1 Blue Labels.

All the roofing from Weyerhaeuser was installed on the Weber residence by Mssrs. John Stephenson and Tomschin. Neither John Stephenson nor Tomschin had ever worked with Blue Label shingles before roofing the appellants’ residence, nor have they worked with that type of shingle since, although Tomschin had been a roofer for twenty-seven years.

Stephenson ran out of shingles after having completed the roof of the main house and the garage, leaving the north slope of the tool house and the roof of the gazebo remaining to be done. Weyerhaeuser Co. could not fill the re-order, so Stephenson ordered the extra shingles from the Superi- or Lumber Co. The shingles which were placed on the gazebo and north slope of the tool house were thinner than the shingles obtained from Weyerhaeuser.

Much testimony was given as to whether the proper shingles were installed. Mr. Weber was firm in his conviction that the shingles were not Blue Labels. In addition, [493]*493it was the opinion of one of the architects, Mr. Winkler, that 90% of the shingles on the main house were not Blue Labels. The reason given was that the butt ends of the shingles on the house were too thick to be certigrade number one. However, Mr. Winkler admitted that his 90% figure was purely a guess.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nola Ventures, LLC v. Upshaw Insurance Agency, Inc.
48 F. Supp. 3d 916 (E.D. Louisiana, 2014)
Jennings v. SSM Health Care St. Louis
355 S.W.3d 526 (Missouri Court of Appeals, 2011)
Delgado v. Mitchell
55 S.W.3d 508 (Missouri Court of Appeals, 2001)
Nooney Krombach Co. v. Blue Cross & Blue Shield of Missouri
929 S.W.2d 888 (Missouri Court of Appeals, 1996)
Cameron v. Morrison
901 S.W.2d 171 (Missouri Court of Appeals, 1995)
Gibson v. Harl
857 S.W.2d 260 (Missouri Court of Appeals, 1993)
Wulfing v. Kansas City Southern Industries, Inc.
842 S.W.2d 133 (Missouri Court of Appeals, 1992)
Jake C. Byers, Inc. v. J.B.C. Investments
834 S.W.2d 806 (Missouri Court of Appeals, 1992)
Tumlinson v. Norfolk & Western Railway Co.
775 S.W.2d 251 (Missouri Court of Appeals, 1989)
Lawyers Title Insurance v. Dallam (In Re Dallam)
72 B.R. 120 (E.D. Missouri, 1987)
Estate of Sudduth
718 S.W.2d 149 (Missouri Court of Appeals, 1986)
Grate v. Richards
689 S.W.2d 635 (Missouri Court of Appeals, 1984)
Hardesty v. Mr. Cribbins's Old House, Inc.
679 S.W.2d 343 (Missouri Court of Appeals, 1984)
Sauer v. Newman
666 S.W.2d 811 (Missouri Court of Appeals, 1984)
Rufkahr Construction Co. v. Weber
658 S.W.2d 489 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
658 S.W.2d 489, 1983 Mo. App. LEXIS 3557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rufkahr-construction-co-v-weber-moctapp-1983.