Rueben and Nicole Casarez v. Alltec Construction Co., Inc.

CourtCourt of Appeals of Texas
DecidedNovember 6, 2007
Docket14-07-00068-CV
StatusPublished

This text of Rueben and Nicole Casarez v. Alltec Construction Co., Inc. (Rueben and Nicole Casarez v. Alltec Construction Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rueben and Nicole Casarez v. Alltec Construction Co., Inc., (Tex. Ct. App. 2007).

Opinion

Reversed and Rendered in Part, Reversed and Remanded in Part, and Memorandum Opinion filed November 6, 2007

Reversed and Rendered in Part, Reversed and Remanded in Part, and Memorandum Opinion filed November 6, 2007.

In The

Fourteenth Court of Appeals

____________

NO. 14-07-00068-CV

RUEBEN AND NICOLE CASAREZ, Appellants

V.

ALLTEC CONSTRUCTION CO., INC., Appellee

On Appeal from the 55th Judicial District

Harris County, Texas

Trial Court Cause No. 04-13358

M E M O R A N D U M  O P I N I O N


Appellants, Ruben and Nicole Casarez, sued Alltec Construction, Co. (Alltec) and Robert Stoll for breach of contract, fraud, and violations of the Texas Deceptive Trade Practices Act.  Alltec and Stoll filed a counterclaim alleging breach of contract and unjust enrichment.  A jury found both parties had breached the construction contract, neither Alltec nor Stoll committed fraud or violations of the Texas DTPA, and  neither party was damaged.  The trial court subsequently signed a take nothing judgment.  On appeal, appellants claim the trial court erred in submitting the question regarding whether appellants breached the contract because the evidence conclusively established Alltec breached the contract first, thereby excusing appellants= performance.  Appellants also argue the evidence is legally and factually insufficient to support the breach of contract and no damage jury verdicts against them.  We reverse and render in part and reverse and remand in part.

Factual and Procedural Background

In June 2001, Tropical Storm Allison hit the Houston area and flooded appellants= house with approximately two feet of water.  Since their house was located below the flood plain and because they had experienced similar trouble in the past, appellants decided something had to be done.  While contemplating their options, appellants were introduced through a mutual acquaintance to Robert Stoll, the owner of Alltec.  Stoll proposed a plan to appellants which would enable them to keep their old house, which was appellants= main goal.  Stoll=s proposal was to lift the frame of the house off the slab and get the frame of the house out of the flood plain.  Appellants agreed to hire Alltec and Stoll for the job.

Around November 2001, Stoll began performing a feasibility study to determine whether it was possible to lift such a large house.  Stoll testified this method of lifting appellants= house was new, so he built a prototype before beginning work on the house. According to Stoll, the prototype was successful, so Alltec went forward with the work on appellants= house.  Although appellants were aware of the feasibility study and prototype, they both testified Stoll represented to them he had performed this process before.  After the feasibility study was completed, Alltec began preliminary work on appellants= house, and in October 2002, appellants signed a contract with Alltec.  The parties agreed the price for Alltec=s work would be $400,000, time was of the essence, and the work would be substantially completed by July 1, 2003.  Alltec did not actually begin working on the project until December 2002 because appellants were waiting for funding approval.


By April 2003, Alltec was approximately one month behind schedule.  Around May or June 2003, Stoll approached appellants and informed them he was out of money and unable to continue work unless appellants paid approximately $28,000 out of sequence.  Stoll asked appellants to directly pay $8,000 to the plumber, $6,000 to the electrician, and $14,000 to Juan Duran.  Each of these people were subcontractors for Alltec, and under the contract, it was Alltec=s responsibility to pay them.  In addition, appellants had already paid Alltec a portion of the money owed to the plumber, but Alltec put the money into its account and used it for something else.  Therefore, Alltec was unable to pay the plumber and was essentially asking for double payment by the appellants.  Appellants refused to pay the additional money to Alltec.

At this point, Alltec could not go forward with the project.  As a solution, Stoll proposed to appellants the option of having Duran, one of Stoll=s subcontractors, finish the work independently.  Stoll proposed the option of appellants paying Duran directly and Stoll staying on the project solely as a consultant.  Appellants were not willing to entrust the completion of the work to Duran, so they decided not to go forward with the proposal.


At some point after Alltec informed appellants it could not go forward, appellants sent Alltec and Stoll a termination letter.  According to the construction contract entered into by appellants and Alltec, section 19.2 allows the owner to terminate the contract with the contractor for a number of reasons.  However, under section 19.2.2 ,the owner was required to obtain certification by the architect that sufficient cause existed to justify the termination.  During trial, Rueben Casarez testified that after Stoll refused to go forward with the contract, he did in fact send a termination letter.  But, he also testified the architect certified sufficient cause existed to justify the termination before he sent the letter.  However, Stoll testified he received a termination letter from appellants but also testified the architect never certified sufficient cause existed to justify the termination.  In addition, Kamran Mouzoon, the architect on the project, never testified that he certified sufficient cause existed to terminate the contract.  In fact, Mouzoon testified there was no cause for stopping the project and no reason he could think of to put the project on hold.  He also testified he was unaware of Stoll=s refusal to go forward unless appellants paid him more money and his failure to pay the plumber.

In July 2003, Stoll sent appellants another draw request for work that had been done on their home and work yet to be done on their home.  Rueben testified he did not pay the request because the contract was terminated at that point and because the architect had not certified the payment, which was a requirement under the contract.

Because appellants=

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Toles v. Toles
45 S.W.3d 252 (Court of Appeals of Texas, 2001)
Continental Dredging, Inc. v. De-Kaizered, Inc.
120 S.W.3d 380 (Court of Appeals of Texas, 2003)
Varme v. Gordon
881 S.W.2d 877 (Court of Appeals of Texas, 1994)
Walker v. Gutierrez
111 S.W.3d 56 (Texas Supreme Court, 2003)
4901 Main, Inc. v. TAS Automotive, Inc.
187 S.W.3d 627 (Court of Appeals of Texas, 2006)
Patel v. Ambassador Drycleaning & Laundry Co.
86 S.W.3d 304 (Court of Appeals of Texas, 2002)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
City of Brownsville v. Alvarado
897 S.W.2d 750 (Texas Supreme Court, 1995)
Triton Oil & Gas Corp. v. Marine Contractors and Supply, Inc.
644 S.W.2d 443 (Texas Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Rueben and Nicole Casarez v. Alltec Construction Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rueben-and-nicole-casarez-v-alltec-construction-co-texapp-2007.