Rucinski Inc v. Randall H Hetzner

CourtMichigan Court of Appeals
DecidedOctober 29, 2024
Docket367208
StatusUnpublished

This text of Rucinski Inc v. Randall H Hetzner (Rucinski Inc v. Randall H Hetzner) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rucinski Inc v. Randall H Hetzner, (Mich. Ct. App. 2024).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

RUCINSKI, INC., also known as RUCINSKI UNPUBLISHED CONSTRUCTION, INC., October 29, 2024 12:08 PM Plaintiff-Appellant,

v No. 367208 Iron Circuit Court RANDALL H. HETZNER and ETHEL M. LC No. 2018-005724-CH HETZNER,

Defendants-Appellees,

and

MINERS STATE BANK,

Defendant.

Before: RIORDAN, P.J., and YOUNG and WALLACE, JJ.

PER CURIAM.

In this construction-contract dispute, plaintiff, Rucinski, Inc., also known as Rucinski Construction, Inc. (“Rucinski”), appeals as of right the trial court’s order granting defendants’ motion for judicial admissions, entering judgment in favor of defendants Randall Hetzner and Ethel Hetzner (“the Hetzners”), and dismissing Rucinski’s complaint.1 We reverse and remand to the trial court for proceedings consistent with this opinion.

I. FACTUAL BACKGROUND

1 Miners State Bank holds a mortgage on the Hetzners’ real property. In Rucinski’s claim for a construction lien on the property, Miners State Bank was added as a party. However, it has taken no part in these proceedings and is not involved in this appeal.

-1- The Hetzners hired Rucinski to build a residential house, but the project was never completed because of disagreements between the parties about the specifications of the build. Rucinski brought suit alleging two counts: a construction lien on the Hetzners’ property where the residence was supposed to be built (Count I), and breach of contract for failing to pay for completed work on the project (Count II). The Hetzners filed their answer and affirmative defenses in 2018. They included a demand for reply, but Rucinski failed to respond. The Hetzners took no action based on this, and the parties continued to litigate the case.

Multiple pretrial conferences were held in July 2019, November 2019, and November 2022. The memorandum of pretrial conference for the November 2019 conference detailed that if case evaluation was unsuccessful, a supplemental pretrial conference would be held in February 2020, where all remaining issues would be addressed and a trial date would be set. The case remained in the trial court for another few years. At the final pretrial conference held in November 2022, the parties were ordered to file trial briefs by March 28, 2023, and hold another pretrial conference, without the trial court’s involvement, in the second half of March 2023 for the parties to “stipulate to exhibits for trial.” The parties timely filed their trial briefs, and neither party’s briefs mentioned Rucinski’s failure to reply to the Hetzners’ answer and affirmative defenses.

The parties proceeded to a bench trial in April 2023. During trial and after Rucinski rested, the Hetzners moved for a directed verdict, where again, no reference was made to Rucinski’s failure to reply to the Hetzners’ answer. The Hetzners raised this issue for the first time at the hearing on their motion for a directed verdict, and the trial court expressed concern that Rucinski failed to reply to the Hetzners’ answer. The trial court partially denied the Hetzners’ motion for directed verdict, disagreeing with the contention that Rucinski’s construction lien claim should be dismissed because Rucinski “did not file any Doing Business Under an Assumed Name with the State of Michigan . . . .” The trial court accepted Rucinski’s argument that through judicial admissions, the Hetzners admitted Rucinski, Inc., and Rucinski Construction, Inc., were the same entity. The trial court also reasoned there is no requirement that a d/b/a be filed with the Michigan Department of Licensing and Regulatory Affairs (LARA). The trial court then asked the parties to brief the issue of judicial admissions instead of directing the Hetzners to move for a default judgment to give Rucinski an opportunity to cure the default. MCR 2.603(D). The trial court did not mention the previously set deadlines from the pretrial conference, which had long since passed.

The Hetzners moved in writing for judicial admissions and dismissal of the entire complaint against them, based on Rucinski’s failure to reply to the answer’s demand for reply. Rucinski filed a late response to the Hetzners’ answer, which the Hetzners argued was improper because it came 30 days after Rucinski rested at trial, and effectively allowed Rucinski to amend pleadings after concluding its case in chief. Given that Rucinski had failed to deny the Hetzners’ answer in a responsive pleading within 21 days, MCR 2.108(a)(5), the Hetzners argued that Rucinski had admitted to the entire answer, thereby warranting dismissal of all claims without any further fact finding. The trial court agreed, granted the motion for judicial admissions, and dismissed the complaint. Rucinski now appeals.

-2- II. ANALYSIS

A. PRESERVATION AND ISSUE ABANDONMENT

“In civil cases, Michigan follows the raise or waive rule of appellate review.” Tolas Oil & Gas Expl Co v Bach Servs & Mfg, LLC, ___ Mich App ___, ___; ___ NW3d ___ (2023) (Docket No. 359090); slip op at 2 (quotation marks and citation omitted). “Under that rule, litigants must preserve an issue for appellate review.” Id. For an issue to be preserved for appellate review, it must be raised in or addressed by the trial court. Glasker-Davis v Auvenshine, 333 Mich App 222, 227; 964 NW2d 809 (2020). During oral argument on the Hetzners’ motion for a directed verdict, the Hetzners argued for the first time that Rucinski failed to reply to their answer and demand for reply. Rucinski responded, arguing the Hetzners never raised this argument in their motion for a directed verdict. Rucinski went on to say:

And here I stand again with a case that’s been lasting five years and I’m supposed to respond to that today? It’s not even in his brief, ah, or his motion. So, we get off on these tangents that should have been raised. I mean this case is five years old.

These comments were in reference to the untimeliness of the Hetzners’ argument regarding judicial admissions, which were not raised during discovery or at any pretrial conferences.

On appeal, Rucinski argues that the trial court erred by granting the Hetzners’ motion for judicial admissions and dismissing the entire complaint. Rucinski advances a number of arguments in support, but critically, fails to fully develop on appeal its argument made in the trial court that the Hetzners’ judicial-admissions argument was untimely. Rucinski’s brief on appeal makes only a cursory reference to the untimeliness of the Hetzners’ argument: “If the procedure adopted by the Trial Court in this matter is upheld, then issues of failure to file a responsive pleading will be allowed to be put off until the trial begins and then dealt with as judicial admissions in order to circumvent the due process procedures afforded the parties under the default rules.”

Rucinski’s brief lacks citation to any legal authority in support of this argument, which renders the issue abandoned on appeal. “However, even if a party abandons an issue by failing to support it with sufficient authority, a reviewing court may nevertheless consider the issue.” Bitterman v Village of Oakley, 309 Mich App 53, 66; 868 NW2d 642 (2015). Thus, we consider the issue of the timeliness of the Hetzners’ judicial-admissions argument.

B. STANDARD OF REVIEW

“A trial court’s decision to dismiss an action is reviewed for an abuse of discretion.” Donkers v Kovach, 277 Mich App 366, 368; 745 NW2d 154 (2007).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hilgendorf v. St. John Hosp. and Medical Center Corp.
630 N.W.2d 356 (Michigan Court of Appeals, 2001)
Radtke v. Miller, Canfield, Paddock & Stone
551 N.W.2d 698 (Michigan Supreme Court, 1996)
Kolton v. Nassar
89 N.W.2d 598 (Michigan Supreme Court, 1958)
Donkers v. Kovach
745 N.W.2d 154 (Michigan Court of Appeals, 2008)
Kromat v. Vestevich
165 N.W.2d 428 (Michigan Court of Appeals, 1968)
Vyletel-Rivard v. Rivard
777 N.W.2d 722 (Michigan Court of Appeals, 2009)
Bailey v. Schaaf
835 N.W.2d 413 (Michigan Supreme Court, 2013)
Bitterman v. Village of Oakley
868 N.W.2d 642 (Michigan Court of Appeals, 2015)
Pirgu v. United Services Automobile Association
884 N.W.2d 257 (Michigan Supreme Court, 2016)
McCracken v. City of Detroit
806 N.W.2d 337 (Michigan Court of Appeals, 2011)
Bailey v. Schaaf
810 N.W.2d 641 (Michigan Court of Appeals, 2011)
Jilek v. Stockson
825 N.W.2d 358 (Michigan Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Rucinski Inc v. Randall H Hetzner, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rucinski-inc-v-randall-h-hetzner-michctapp-2024.