R.P. Fuller v. Phillips Petroleum Company

872 F.2d 655, 108 Oil & Gas Rep. 135, 1989 U.S. App. LEXIS 14565, 1989 WL 38685
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 10, 1989
Docket88-1531
StatusPublished
Cited by22 cases

This text of 872 F.2d 655 (R.P. Fuller v. Phillips Petroleum Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.P. Fuller v. Phillips Petroleum Company, 872 F.2d 655, 108 Oil & Gas Rep. 135, 1989 U.S. App. LEXIS 14565, 1989 WL 38685 (5th Cir. 1989).

Opinion

JOHNSON, Circuit Judge:

Plaintiff R.P. Fuller appeals an order of the district court entering a judgment notwithstanding the verdict in favor of defendant Phillips Petroleum Company (Phillips) on a breach of contract claim asserted by Fuller against Phillips. Persuaded that the district court did not err in construing the language of the joint operating agreement between Phillips and Fuller, we affirm.

I. FACTS AND PROCEDURAL HISTORY

The instant controversy arose as a result of a dispute over the interpretation of a joint oil and gas operating agreement entered into between R.P. Fuller and Phillips on July 16, 1964, covering certain oil and casinghead gas leases on an approximately 160-acre tract of land described in the operating agreement as the “Unit Area.” Phillips owned two oil and gas leases covering an undivided two-thirds interest in the Unit Area, while Fuller owned a single oil and gas lease covering the remaining undivided one-third interest in the Unit Area.

Pursuant to the provisions of the operating agreement between the parties, Phillips drilled a well in 1964 within the Unit Area referred to as the Holliday A-l Well. The Holliday A-l well was the only well drilled by Phillips within the Unit Area. Thereafter, the Holliday well ceased production on January 12, 1983, apparently after problems developed due to a casing leak. Because both oil and gas leases owned by Phillips covering the Unit Area provided for the expiration or termination of the leases sixty days following cessation of operations, the two leases expired by their own terms on approximately March 13, 1983, due to the cessation of operations on the leased premises.

After Phillips’ two leases had terminated, Phillips notified Fuller in writing on April 26, 1983, of its intent to plug and abandon the Holliday well. Following his receipt of such notice, Fuller stated the following in a letter to Phillips:

This is to inform you per your request in your letter ... that I do not concur with *657 your intentions or with the contents of the letter.

Despite the above letter by Fuller, Phillips subsequently plugged and abandoned the Holliday well.

Thereafter, Fuller filed the instant action against Phillips claiming that the failure of Phillips to notify Fuller of its intent to plug and abandon the Holliday well prior to the expiration of Phillips’ two oil and gas leases constituted a compensable breach of the joint operating agreement between Fuller and Phillips. In response, Phillips filed a counterclaim seeking damages from Fuller for Fuller’s alleged failure to pay a proportionate share of the operating expenses for the Holliday well in accordance with the provisions of the operating agreement.

Ultimately, the case was tried before a jury. Answering special issues submitted by the parties, the jury found that Fuller would have taken over Phillips’ two-thirds interest in the Unit Area leases if Fuller had been notified by Phillips that those leases were going to expire. The jury then found the amount of damages suffered by Fuller as a result of the breach of the operating agreement by Phillips. The jury further found that Fuller owed Phillips $13,894.61 in operating expenses under the operating agreement. After the jury issued its findings, both Phillips and Fuller filed motions for judgment notwithstanding the verdict of the jury with the district court. In a complete and thorough order issued April 4, 1988, the district court granted the motions for judgment notwithstanding the verdict of both parties, thereby rendering neither party liable to the other. Only Fuller now appeals the order of the district court.

II. DISCUSSION

On appeal, Fuller maintains that the district court erred in concluding as a matter of law that Phillips did not breach the joint operating agreement between the parties by failing to notify Fuller of its intent to plug and abandon the Holliday well prior to the termination of Phillips’ two leases covering the Unit Area. Specifically, Fuller insists that Phillips breached the operating agreement by failing to notify him that both of Phillips’ leases would expire at the end of sixty days following January 12, 1983, the date on which production on the Holliday well ceased. In making the above assertion, Fuller relies primarily on two provisions in the operating agreement which we will consider in turn. Initially, however, it is noted that there exists no express provision in the operating agreement which directly requires the operator (Phillips) to notify the nonoperator (Fuller) of an impending lease termination. Thus, Fuller is asking this Court to imply such a duty of notification by virtue of other terms contained in the operating agreement.

A. Principles of Contract Construction

As previously noted, in the instant case, the district court concluded as a matter of law that Phillips did not breach the operating agreement between the parties. In so concluding, the district court determined that neither Phillips nor Fuller raised any allegation of ambiguity regarding the language contained in the operating agreement. The fact that the district court did not consider there to be an issue of ambiguity in the instant contractual dispute is significant since this Court characterizes the determination by a district court of the non-ambiguity of a contract as a conclusion of law and accordingly, reviews that conclusion de novo. Southern Natural Gas Co. v. Pursue Energy, 781 F.2d 1079, 1081 (5th Cir.1986).

It is well established that the primary concern of a court in construing a contract is to ascertain and give effect to the intent of the parties as expressed in the contract. Gracia v. RC Cola-7-Up Bottling Co., 667 S.W.2d 517, 520 (Tex.1984). Further, objective, not subjective, intent of the parties controls and, in the absence of an allegation of ambiguity as to the contract language, the instrument alone will be deemed to express the intent of the parties. Phillips v. Inexco Oil Co., 540 S.W.2d 546, 548 (Tex.Civ.App.—Tyler 1976, writ ref’d n.r.e). Applying Texas principles *658 of contract construction which govern the instant diversity action, it is noted that Texas courts have stated the following regarding the implication of additional contractual obligations from the express terms of a written agreement:

In order for a court to read additional provisions into the contract, the implication must clearly arise from the language used, or be indispensable to effectuate the intent of the parties. It must appear that the implication was so clearly contemplated by the parties that they deemed it unnecessary to express it.

Kutka v. Temporaries, Inc., 568 F.Supp. 1527, 1535 (S.D.Tx.1983). We now apply the above legal principles to the specific assertions made by Fuller in the instant appeal.

B. Plug and Abandon Clause

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeffrey Reed v. Florida Metro University, Inc., et
681 F.3d 630 (Fifth Circuit, 2012)
MacQuarie Bank Ltd. v. Knickel
723 F. Supp. 2d 1161 (D. North Dakota, 2010)
Ultra Resources, Inc. v. Hartman
2010 WY 36 (Wyoming Supreme Court, 2010)
AXA S.A. v. Union Pacific Railroad
269 F. Supp. 2d 863 (S.D. Texas, 2003)
Norman v. Apache Corp.
19 F.3d 1017 (Fifth Circuit, 1994)
United States v. Associated Indemnity Company
969 F.2d 83 (Fifth Circuit, 1992)
Huggs, Inc. v. LPC Energy, Inc.
889 F.2d 649 (Fifth Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
872 F.2d 655, 108 Oil & Gas Rep. 135, 1989 U.S. App. LEXIS 14565, 1989 WL 38685, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rp-fuller-v-phillips-petroleum-company-ca5-1989.