R.P. Farnsworth v. Estrade, Cotton Fricke

166 So. 160
CourtLouisiana Court of Appeal
DecidedFebruary 24, 1936
DocketNo. 16252.
StatusPublished
Cited by8 cases

This text of 166 So. 160 (R.P. Farnsworth v. Estrade, Cotton Fricke) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.P. Farnsworth v. Estrade, Cotton Fricke, 166 So. 160 (La. Ct. App. 1936).

Opinion

McCALEB, Judge.

. R. P. Farnsworth & Co., Inc., a general contractor, brings this suit against Herman J. Estrade, Henry Fricke, and Edward P. Cotton, subcontractors, and their surety, Fidelity & Deposit Company of Maryland, for damages arising from an alleged breach of contract.

Inasmuch as the record is voluminous and the testimony conflicting, we deem it essential to find certain facts presented, in order to determine the questions of law involved.

On March 4, 1932, plaintiff, a corporation engaged in the general contracting business, entered into a written contract to build a “factory building at Harvey, Louisiana,” for the Continental Can Company, Inc., in accordance with certain plans and specifications attached to the contract.

Thereafter, on March 28, 1932, plaintiff engaged, by written subcontract, the co-partnership of Estrade, Cotton & Fricke to unload and tie in place certain steel to be used in the erection of the factory, for which service to be performed by the subcontractors the plaintiff agreed to pay the sum of $6 for each ton of steel unloaded and fixed in place, in accordance with the architect’s plans and specifications annexed to the general contract between the owner and the plaintiff. There is no definite time fixed in the subcontract for the completion thereof, but we discern therefrom that it was the intention of the parties for the subcontractors to be ready for work upon twelve hours’ notice previously given by the plaintiff to them, and that the steel work would be performed at such times as needed, in keeping with the progression of the general contract.

It is provided, however, among other things in the subcontract, that, if the subcontractors fail to complete the work or delay the progress of the job, the plaintiff, in such case, is entitled to $50 per day liquidated damages.

This contract further provides for the furnishing of a bond by the subcontractors, and accordingly, on the same date upon which the subcontract was signed, the subcontractors, with the Fidelity & Deposit Company of Maryland as surety, executed a bond in the sum of $1,000 to the plaintiff, conditioned that the subcontractors “ * * * shall well and truly and faithfully comply with all of the conditions and obligations of the said contract, and shall promptly pay all laborers, mechanics and furnishers of material doing labor and supplying material therefor, and deliver his said work free of liens, as well as pay all liquidated damages due under said contract. ⅜ ⅜ ⅜ »

The record shows that on March 28, 1932, certain steel arrived at the site of the job, and that defendant subcontractors became engaged in the unloading of the same, shortly after that time. They worked in harmony for apparently two or three weeks, when friction began to exist between the partners. Estrade, Cotton, and Fricke had, at no time previous to this contract, been engaged as partners, and the copartnership was evidently formed for the purpose of this particular undertaking. There is nothing in the record to show whether the partnership agreement was in writing, and the evidence leads us to the conclusion that there was merely a verbal agreement between the partners.

Soon after the unloading of steel had begun, there was a delay in operations caused by the architect’s rejection of certain piling used by the plaintiff in the construction of the work. Fricke, one of the partners, became employed by the plaintiff, for his own account, doing pile-driving work. Estrade left the job and engaged himself in another enterprise at Biloxi, Miss., and Cotton (although the testimony is not clear on this point) remained on the job. During all this time the relationship between the three partners was becoming more and more strained. Their workmen were not being paid, and the plaintiff and the bonding company were receiving letters from the attorney of Estrade complaining of delays in the work and of the unsatisfactory relations between the partners. In short, both the plaintiff and the bonding company were aware of the internal disputes between the partners, and many conferences were held and letters written, having in view an amicable solution of the problem, so that the subcontract could be carried on to completion without default.

On June 3, 1932, Fricke, one of the partners, wrote to the plaintiff that he was abandoning the work, and that he was withdrawing from the copartnership of Estrade, *162 Cotton & Fricke. On the following day, June 4th, the plaintiff communicated this information to the bonding company, and advised it that prompt attention should be given by it (the surety) to these matters, and that the plaintiff would neither accept any assignment or recognize or take part in any disputes among the partners, and that plaintiff believed it to be the duty of the surety to see that the work progressed in accordance with the terms of the contract and without damage or delay to the plaintiff.

Notwithstanding the internal disputes between the partners, the abandonment of the work by Fricke, and the ostensible friction between Estrade and Cotton, the plaintiff co-operated with the surety to the fullest extent, with a view of allowing the partners to complete the subcontract.

However, on June 15, 1932, Estrade, together with two or three other men, went to the site of the work. He contends that he went there to pay off the gang'of workmen, who had not been paid in some time.' Contra, plaintiff contends that Estrade told the workmen that they were not going to be paid and that they might as well get off the job. The result was that Estrade was struck over the head with a piece of iron by one of his own workmen, rendered unconscious, and had to be transported to the hospital for treatment. He never went back to the job, and he stated on the witness stand that he would not have returned to work unless plaintiff could have guaranteed him police protection.

To request this court to believe Estrade’s fanciful story, viz., that when he offered to pay off his laborers he was assaulted by them or one of them, is to assume that we are credulous.

Indeed, it strikes us that Esti'ade went to the site of the work for the -specific purpose of inciting discord between the workmen, who were apparently friendly to Cotton, his partner. When he told these men that they were not to be paid and suggested that they leave the job, one of their number, justifiably enraged, committed the assault.

After June 15, 1932, until June 24, 1932, 'Cotton continued with the work under the contract. On June 24th he told Mr. Richard Farnsworth (plaintiff’s representative) that he (Cotton) had no money to meet his pay rolls,, and could not continue the work any longer. Farnsworth notified him that, under these circumstances, the job was abandoned, and that plaintiff would probably have to complete it. In order to minimize its damage, plaintiff engaged Cotton and his workmen to work for it, starting June 25, 1932.

On the date of the abandonment of the work by Cotton, the plaintiff wrote the bonding company the following letter:

“June 24, 1932
“Subject: Continental Can Company
“Fidelity & Deposit Co., c/o Black-Rogers & Co. Ltd., Agents 1217 Hibernia Bank Bldg., City.
“Gentlemen:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hibernia National Bank v. John W. Carner
997 F.2d 94 (Fifth Circuit, 1993)
Hibernia Nat. Bank v. Carner
Fifth Circuit, 1993
House of Lights, Inc. v. Diecidue
222 So. 2d 603 (Louisiana Court of Appeal, 1969)
Williams Lumber Co. v. Stewart Gast Bro.
21 So. 2d 773 (Louisiana Court of Appeal, 1945)
Modern Appliance Supply Co. v. B.F. Ibos Sons
16 So. 2d 552 (Louisiana Court of Appeal, 1944)
Langston v. Red Iron Drilling Co.
38 F. Supp. 136 (W.D. Louisiana, 1941)
Durrett Hardware & Furniture Co. v. Howze
174 So. 205 (Louisiana Court of Appeal, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
166 So. 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rp-farnsworth-v-estrade-cotton-fricke-lactapp-1936.