Royalite Co. v. Federal Insurance

457 N.W.2d 96, 184 Mich. App. 69, 1990 Mich. App. LEXIS 181
CourtMichigan Court of Appeals
DecidedJune 4, 1990
DocketDocket 114174
StatusPublished
Cited by7 cases

This text of 457 N.W.2d 96 (Royalite Co. v. Federal Insurance) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royalite Co. v. Federal Insurance, 457 N.W.2d 96, 184 Mich. App. 69, 1990 Mich. App. LEXIS 181 (Mich. Ct. App. 1990).

Opinions

Cynar, J.

Defendant appeals as of right from a circuit court order granting plaintiff summary disposition on its construction bond claim. We affirm.

The facts in this case are not in dispute. Granger Construction Company was the primary con-

[71]*71tractor on a project involving the construction of the Genesee County jail. As required by the Michigan public works bond act, MCL 129.201 et seq.; MSA 5.2321(1) et seq., Granger furnished a payment bond, issued by defendant as surety, for the protection of certain claimants supplying labor or materials for the project. MCL 129.201, 129.203; MSA 5.2321(1), 5.2321(3). In connection with the project, plaintiff supplied materials to Hatzel-Buehler, Inc., a subcontractor to Granger. After Hatzel-Buehler failed to pay plaintiff for the materials supplied, plaintiff commenced the instant action seeking recovery under the payment bond.

Section 7 of the act, MCL 129.207; MSA 5.2321(7), specifies the procedure by which a claimant not having a direct contractual relationship with the primary contractor may perfect a claim against the payment bond:

A claimant who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which payment bond is furnished under the provisions of section 3, and who has not been paid in full therefor before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which claim is made, may sue on the payment bond for the amount, or the balance thereof, unpaid at the time of institution of the civil action, prosecute such action to final judgment for the sum justly due him and have execution thereon. A claimant not having a direct contractual relationship with the principal contractor shall not have a right of action upon the payment bond unless (a) he has within 30 days after furnishing the first of such material or performing the first of such labor, served on the principal contractor a written notice, which shall inform the principal of the nature of the materials being furnished . . . , and (b) he has given written notice [72]*72to the principal contractor and the governmental unit involved within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which the claim is made, stating with substantial accuracy the amount claimed ....

Among the conditions concerning giving notice contained in the payment bond issued by defendant was the following:

3. No suit or action shall be commenced hereunder by any claimant:
a) Unless claimant, other than one having a direct contract with the Principal, shall have given written notice to any two of the following, the Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed.

While the bond referenced that portion of the statute requiring ninety days notice, it did not include a similar provision referring to the thirty-day notice requirement also set forth in the statute.

It is undisputed that plaintiff met the statutory definition of a claimant entitled to bring suit on the bond. MCL 129.206; MSA 5.2321(6). It is also undisputed that plaintiff did not have a direct contractual relationship with the principal contractor. Finally, the parties agree that, although plaintiff complied with the ninety-day notice requirement set forth in both the statute and the bond, it did not comply with the portion of the statute requiring thirty days notice from the date materials were first supplied.

[73]*73Cross-motions for summary disposition were brought by the parties. Defendant argued that plaintiffs failure to comply with the thirty-day notice requirement precluded it from maintaining an action on the bond. However, it was plaintiffs position that, because the actual payment bond only contained a ninety-day notice provision and it had complied with that provision, it was entitled to recovery. On the basis of Hub Electric Co, Inc v Gust Construction Co, Inc, 585 F2d 183 (CA 6, 1978), cert den 440 US 936; 99 S Ct 1282; 59 L Ed 2d 495 (1979), the trial court granted the motion in favor of plaintiff and awarded it judgment in the amount of $23,433.94.

Where there is no surety bond contract language covering a subcontractor, our Court has held the statute to be constitutional and required that its notice requirements be strictly construed. Square D Environmental Corp v Aero Mechanical, Inc, 119 Mich App 740; 326 NW2d 629 (1982). The purpose and intent of the Michigan public works bond act is to safeguard and protect contractors and material suppliers in the public sector. Adamo Equipment Rental Co v Mack Development Co, Inc, 122 Mich App 233, 236; 333 NW2d 40 (1982); Skyline Steel Corp v A J Dupuis Co, 648 F Supp 360, 370 (ED Mich, 1986).

In Pi-Con, Inc v A J Anderson Construction Co, 169 Mich App 389, 394; 425 NW2d 563 (1988), lv gtd 432 Mich 891 (1989), our Court held that strict compliance with the statute’s notice requirements was required. Liberal construction was appropriate only where the statutory language was susceptible to different interpretations. Pi-Con, supra at 395. However, in Pi-Con, supra, there was a contract between the principal and the surety which directly covered the notice requirements of a claimant other than one having a direct contract with [74]*74the claimant. Here, the bond itself contains specific language in which the surety grants the principal more liberal coverage than the statute. In Pi-Con, supra, the issue was whether the statutory notice requirements could be met by sending notice by regular mail as opposed to the statutorily required certified mail.

In Tempco Heating & Cooling, Inc v A Rea Construction, Inc, 178 Mich App 181; 443 NW2d 486 (1989), this Court held that strict compliance with the notice requirements of the statute was necessary in a case where the bond was written in direct compliance with the statute. There was a genuine issue of material fact related to both the thirty-day and ninety-day notices given. Tempco, supra at 190-192.

Here, the circuit court found the Sixth Circuit’s opinion persuasive. The question in Hub Electric, supra, was whether a subcontractor’s satisfaction of the ninety-day notice requirement in the bond executed between the parties, the principal and the surety, was sufficient to permit the subcontractor to recover on its claim, or whether the thirty-day notice requirement of the statute must also be met. The Sixth Circuit stated:

We therefore hold that the surety by its bonding contract may agree to accept a greater liability than that required under the Michigan bonding statute, although for reasons of public policy it may not contract for less. The statute specifically provides that the payment bond is solely for the benefit of the claimants, and nothing suggests that the Act was intended to establish a ceiling as well as a floor upon the liability which a surety may undertake by contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. Owens-Corning Fiberglas Corp.
571 N.W.2d 530 (Michigan Court of Appeals, 1997)
W T Andrew Co. v. Mid-State Surety Corp.
562 N.W.2d 206 (Michigan Court of Appeals, 1997)
Royalite Co. v. Federal Insurance
457 N.W.2d 96 (Michigan Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
457 N.W.2d 96, 184 Mich. App. 69, 1990 Mich. App. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royalite-co-v-federal-insurance-michctapp-1990.