Roy Zenere Trucking & Excavating, Inc. v. Build Tech, Inc.

2016 IL App (3d) 140946, 65 N.E.3d 340
CourtAppellate Court of Illinois
DecidedAugust 2, 2016
Docket3-14-0946
StatusUnpublished
Cited by2 cases

This text of 2016 IL App (3d) 140946 (Roy Zenere Trucking & Excavating, Inc. v. Build Tech, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roy Zenere Trucking & Excavating, Inc. v. Build Tech, Inc., 2016 IL App (3d) 140946, 65 N.E.3d 340 (Ill. Ct. App. 2016).

Opinion

2016 IL App (3d) 140946

Opinion filed August 2, 2016 ____________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

ROY ZENERE TRUCKING & ) Appeal from the Circuit Court EXCAVATING, INC., OAK LAWN ) of the 12th Judicial Circuit, BLACKTOP PAVING COMPANY, INC., and ) Will County, Illinois, ALPINE CONCRETE, INC., ) ) Plaintiffs, ) ) v. ) ) BUILD TECH, INC., JEFFERSON REGER ) DEVELOPMENT, LLC, NATIONAL CITY ) BANK COMPANY, WALGREENS ) COMPANY, UNKNOWN OWNERS and ) NONRECORD CLAIMANTS, JEFFERSON ) REGER, LLC, BUILD TECH, INC., HEALEY ) Appeal No. 3-14-0946 COURT APARTMENTS, LLC, JOHN ) Circuit Nos. 08-CH-4701, 09-CH-875, STREET APARTMENTS, LLC, and BUSEY ) and 09-AR-636 BANK, ) ) Defendants. ) ) (Oak Lawn Blacktop Paving Company, ) Inc. and Alpine Concrete, Inc., Plaintiffs- ) Appellees and Cross-Appellants; Jefferson ) Reger, LLC, Build Tech, Inc., Healey Court ) Apartments, LLC, John Street Apartments, ) LLC, and Busey Bank, Defendants-Appellants ) Honorable and Cross-Appellees). ) Raymond E. Rossie, ) Judge, Presiding. ) _____________________________________________________________________________ JUSTICE LYTTON delivered the judgment of the court, with opinion. Justices Schmidt and Wright concurred in the judgment and opinion. _____________________________________________________________________________

OPINION

¶1 Defendant, Jefferson Reger, LLC, appeals the trial court’s finding in favor of plaintiffs,

Oak Lawn Blacktop Paving Company, Inc. (Oak Lawn) and Alpine Concrete, Inc. (Alpine) for

the balance of the subcontracts underlying their mechanics liens and denying defendant’s

counterclaims for constructive fraud and slander of title. Plaintiffs cross-appeal from the trial

court’s denial of attorney fees. We affirm in part, reverse in part, and remand for calculation and

imposition of attorney fees.

¶2 FACTS

¶3 Defendant owned a parcel of real estate in Shorewood, Illinois. Defendant planned to

develop the property and lease it for the operation of a Walgreens store. In November 2007,

defendant entered into a general contract with codefendant, Build Tech, Inc. (Build Tech), to

build the Walgreens store on the property. Build Tech subsequently entered into subcontracts

with plaintiffs. Disputes arose between defendant and Build Tech and with several of the

subcontractors. The disputes between defendant and Build Tech and all subcontractors other than

plaintiffs were settled before trial. Plaintiffs asserted mechanics lien foreclosure claims against

defendant.

¶4 In 2009, plaintiffs each filed separate complaints against each defendant asserting

mechanics lien foreclosure claims. Alpine’s complaint alleged that Alpine and Build Tech

entered into a subcontract on January 8, 2008. The subcontract required Alpine to perform

concrete work, for which Alpine would be paid $217,752, which equaled the subcontract price of

$208,000 plus extras. Alpine completed the obligations on September 14, 2008, that $30,522

2 remained unpaid, and that a lien was placed on the property on November 25, 2008. Oak Lawn’s

complaint alleged that Oak Lawn and Build Tech entered into a written subcontract on April 24,

2008, under which Oak Lawn would perform paving work around the Walgreens store and be

paid a subcontract price of $112,800 plus extras. Oak Lawn completed the work on September

16, 2008, at which time $36,655 remained owing to Oak Lawn. Oak Lawn then placed a lien on

the property on November 26, 2008.

¶5 Defendant filed counterclaims against plaintiffs alleging constructive fraud and slander of

title stating that plaintiffs knowingly overstated their lien claims, as they were based on unsigned

change orders.

¶6 The case proceeded to trial. Kevin Reger testified that he was “the sole member-manager

of Jefferson Reger, LLC.” Defendant entered into a written general contract with Build Tech on

November 5, 2007. Build Tech hired subcontractors to do the project, two of which were

plaintiffs. Reger said he became aware that plaintiffs were hired as subcontractors through the

general contractor’s sworn statement and through lien waivers provided by plaintiffs. However,

he never looked at any of the subcontractors’ contracts prior to starting the job, and he did not

believe he saw the contracts “until [they] got to the discovery portion of this lawsuit.”

¶7 Reger said he received both of plaintiffs’ partial lien waivers at the end of September or

October. He said the waivers came as backup to the general contractor’s sworn statement, so he

looked at the sworn statement before looking at the lien waivers. Reger testified that the normal

course of business was that he would receive a pay application asking for a certain amount of

money, then underlying that would be the sworn statement to verify the numbers, and then the

lien waivers would further solidify the numbers. Reger explained that he received four rounds of

pay applications and sworn statements. He stated he would look at the pay application, which

3 would state the amount of the contract, the amount of the change orders, the amount to be paid,

and the retainage. He would then look at the underlying sworn statement from the contractor.

The sworn statement listed each subcontractor, the scope of their work, the amount of the

subcontractor’s contract, the retention amount, the net previously paid, the amount of the current

payment, and the balance to completion. After he received the contractor’s sworn statement, he

prepared an owner’s sworn statement and submitted all of those documents to the title company.

The subcontractors would then bring the lien waivers to the title company, and the title company

would disperse a check to the subcontractors. Both plaintiffs received partial payments in this

manner.

¶8 Based on the third pay application submitted for work ending July 21, 2008, Reger

believed that both plaintiffs had fully completed their work on the project as of that date, as the

balance of each subcontract and the 10% retention were listed as the same amount.

¶9 Reger was shown Oak Lawn’s lien waiver. He stated that the lien waiver listed the

contract price as $95,500 and each of the contractor’s sworn statements listed it as $95,000;

therefore, there was a discrepancy of $500 between the documents. He interpreted that to mean

that the contract price, including extras, for Oak Lawn was $95,000. Reger became aware after

the lawsuit began that Oak Lawn claimed the subcontract was for $112,800. He said that Oak

Lawn did nothing to make defendant believe that it intended to discount its subcontract in

exchange for partial payment. Reger said that a subcontract between Build Tech and Oak Lawn

that listed the contract amount as $95,000 was never produced. Reger stated that he did not know

where the amount of $95,000 came from, but he relied on the contractor’s sworn statement.

Alpine’s lien waiver listed its subcontract price as $208,000. Reger stated he interpreted this to

4 mean that was the subcontract price including extras. Reger said if the numbers did not match up

between the documents, he would have discussed it with the general contractor.

¶ 10 Reger became aware that plaintiffs had some change orders on the project through

discovery; he did not see any change orders until after the lawsuit began. He did not recall

whether he approved any change orders for either plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MEP Construction, LLC v. Truco MP, LLC
2019 IL App (1st) 180539 (Appellate Court of Illinois, 2019)
Roy Zenere Trucking & Excavating, Inc. v. Build Tech, Inc.
2016 IL App (3d) 140946 (Appellate Court of Illinois, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 IL App (3d) 140946, 65 N.E.3d 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roy-zenere-trucking-excavating-inc-v-build-tech-inc-illappct-2016.