Route 9 Opposition Legal Fund v. Mineta

75 F. App'x 152
CourtCourt of Appeals for the Fourth Circuit
DecidedSeptember 15, 2003
Docket02-2007
StatusUnpublished
Cited by2 cases

This text of 75 F. App'x 152 (Route 9 Opposition Legal Fund v. Mineta) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Route 9 Opposition Legal Fund v. Mineta, 75 F. App'x 152 (4th Cir. 2003).

Opinion

OPINION

PER CURIAM.

Several organizations and individuals (collectively, “Appellants”) appeal a district court order granting summary judgment to federal and West Virginia highway officials in Appellants’ suit challenging the approval of a highway construction project. Finding no reversible error, we affirm.

I.

The project at issue involves the construction of a new 4.6-mile four-lane highway in Jefferson County, West Virginia, extending from Charles Town to the Virginia state line. The proposed highway would be built near existing West Virginia Route 9, a winding two-lane highway constructed in the 1930s. Because of rapid population growth in Jefferson County, the relevant portion of Route 9 has become more developed. Numerous residences and businesses now have driveways accessing the highway, and there are many school bus stops along the road.

Due to the increased traffic on Route 9, the highway now has physical and functional deficiencies, including inadequate roadway geometries and intersection configurations, a lack of climbing and turning lanes, and inadequate sight distance at intersections. These deficiencies have resulted in unsafe driving conditions, which are reflected in accident, injury, and fatality rates significantly higher than statewide averages. Further, the increased traffic has prevented Route 9 from functioning at an acceptable level of service (LOS). 1

For these reasons, the West Virginia Department of Transportation (WVDOT) determined that improvements to Route 9 were necessary and sought federal funding for this purpose. Pursuant to a provision of the National Environmental Policy Act of 1969 (NEPA), see 42 U.S.C.A. § 4332(2)(C) (West 1994), and Section 4(f) of the Department of Transportation Act of 1966 (“Section 4(f)”), see 49 U.S.C.A. § 303(c) (West 1997), the Federal Highway Administration (FHWA) and WVDOT (collectively, “the Agencies”) issued a Draft Environmental Impact Statement and Section 4(f) Evaluation for public comment in December 1993. In October 2000, the Agencies issued a Final Environmental Impact Statement and Section 4(f) Evaluation (FEIS). The FEIS identified a variety of possible alternatives for the project, including a No-Build Alternative (leaving the existing Route 9 unchanged), a Transportation Systems Management (TSM) Alternative (making improvements to the ex *154 isting two-lane highway, such as adding turning and climbing lanes, widening and repaving shoulders, and installing traffic signals and additional signs), a Public Transit Alternative (making greater use of existing and potential public transportation options), a Two-Lane Upgrade Alternative (upgrading existing Route 9, likely by constructing a two-lane highway on a new alignment in order to provide adequate stopping sight distance and sufficient road and shoulder width, limit roadway grade and horizontal curvature, and improve side road intersections), a Four-Lane Upgrade Alternative (expanding the existing highway to four lanes), and five different Four-Lane Build Alternatives (constructing a new four-lane highway on one of five new alignments).

The FEIS evaluated these alternatives in two stages. First, the Agencies assessed whether each of the alternatives would meet the purpose and needs of the project. This analysis was intended “to determine which preliminary alternatives demonstrated merit to be retained for detailed study and which alternatives should be dismissed from further consideration.” J.A. 446. During this stage, the Agencies determined that the No-Build Alternative, the TSM Alternative, the Public Transit •Alternative, the Two-Lane Upgrade Alternative, and the Four-Lane Upgrade Alternative should be eliminated from further consideration because, inter alia, none of these alternatives would meet the capacity and safety needs of the project. By contrast, the Agencies determined that the five Four-Lane Build Alternatives would meet the capacity and safety needs of the project. Thus, these alternatives and the No-Build Alternative were retained for more detailed study. 2

The second stage of the alternatives analysis involved a more detailed engineering and environmental impact assessment of the alternatives that were carried forward from the first stage. After analyzing each of the Four-Lane Build Alternatives (Alternatives A-E), the Agencies identified Alternative E as the Preferred Alternative.

The Agencies recognized in the FEIS that Alternative E would involve the acquisition of property from sites protected by Section 4(f). 3 However, based on their determination that several of the proposed alternatives would not meet project needs and an analysis showing that all of the Four-Lane Build Alternatives would use land from Section 4(f) properties, the Agencies concluded that (1) there were no prudent alternatives that would entirely avoid the use of Section 4(f) properties, (2) Alternative E was the prudent alternative that least harmed these properties, and (3) Alternative E incorporated all possible planning to minimize harm. In January 2001, FHWA issued a Record of Decision approving the selection of Alternative E based on the findings in the FEIS.

In December 2001, Appellants brought this action, claiming, inter alia, that the Agencies had violated NEPA and Section 4(f) by failing to adequately consider two-lane alternatives that would add climbing, passing, and turning lanes; realign curves; *155 improve intersections; and widen and resurface shoulders. Both sides moved for summary judgment. With regard to NEPA, the district court held that the Agencies had adequately considered alternatives involving the upgrading of the existing two-lane highway and had reasonably determined that such alternatives would not meet the capacity and safety needs of the project. Similarly, the court rejected Appellants' Section 4(f) claim, concluding that the Agencies’ findings regarding the lack of prudent alternatives and the efforts to minimize harm to Section 4(f) properties were reasonable. The court therefore granted summary judgment to the Agencies. 4

II.

On appeal, Appellants maintain that the Agencies violated NEPA and Section 4(f) by failing to adequately consider two-lane alternatives to the proposed project. We review the grant of summary judgment to the Agencies de novo. See Hodges v. Abraham, 300 F.3d 432, 445 (4th Cir.2002), cert. denied, 537 U.S. 1105, 123 S.Ct. 871, 154 L.Ed.2d 775 (2003). We may overturn the FHWA’s decision to approve the project only if that decision was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C.A. § 706(2)(A) (West 1996). ‘When reviewing an agency’s decision to determine if [it] was arbitrary and capricious, the scope of our review is narrow. Like the district court, we look only to see if there has been a ‘clear error of judgment.’ ” Hughes River Watershed Conservancy v. Johnson, 165 F.3d 283, 287 (4th Cir.1999) (quoting Marsh v. Or. Natural Res. Council,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
75 F. App'x 152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/route-9-opposition-legal-fund-v-mineta-ca4-2003.