Route 103 Quarry

CourtVermont Superior Court
DecidedNovember 22, 2006
Docket205-10-05 Vtec
StatusPublished

This text of Route 103 Quarry (Route 103 Quarry) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Route 103 Quarry, (Vt. Ct. App. 2006).

Opinion

STATE OF VERMONT VERMONT ENVIRONMENTAL COURT

} Route 103 Quarry } Docket No. 205-10-05 Vtec (Appeal of J.P. Carrara & Sons, Inc.) } (Act 250 Permit No. 1R0589-8) }

Decision on the Merits

J.P. Carrara & Sons, Inc. (hereinafter “Carrara”) has long operated a dolomite quarry on a portion of the 59± acre tract of land it owns along the northern boundary of Vermont Route 103, in Clarendon, across from the Rutland Airport. Carrara originally extracted dolomite rock from outcroppings above ground level. Beginning sometime in 1996, Carrara began extracting rock from below ground level, including through the use of explosive charges. Carrara first sought an Act 250 permit for its Route 103 quarry (the “Carrara Quarry”) in 1986. It subsequently sought several amendments to its Act 250 permit. Its most recent Act 250 amendment request is the subject of this appeal. Carrara’s current application requests that it be allowed to: (1) lower the Quarry floor by an additional 105 feet, to a depth of 517 feet above sea level; (2) increase the maximum limits of allowed explosives; (3) increase the number of truck trips to and from the Quarry; and (4) extend the life of the Carrara Quarry permit for 15 years.1

Carrara filed the initial appeal in this proceeding on September 30, 2005. The Neighbors identified below, some of whom have lived in this neighborhood since before Carrara began its quarry operations, filed a cross-appeal on November 1, 2005. This Court issued its initial Scheduling Order on December 1, 2005. After addressing a number of pre-trial motions, the Court conducted a site visit and completed a bench trial over the course of six calendar days. The parties were permitted an opportunity to file pre- and post-trial memoranda, proposed findings of fact and conclusions of law.

1 Carrara initially requested that its Permit be extended for an additional term of 30 years from the date of this Decision, but then subsequently reduced its request to 15 years, as noted in its proposed Findings and proposed Permit. Based upon the evidence admitted at trail, including evidence put in context by the site visit, the Court makes the following findings and determinations:

I. Procedural History and Determinations. When this Court addresses an appeal from an Act 250 district environmental commission determination, it is important to first reference the procedural history of the case, the parties who have standing in the pending appeal, and the Act 250 criteria that have been preserved for review in the appeal. Both the district commissions and the former Environmental Board established this procedure for drafting decisions, and their procedure often provided a clear announcement of decisions involving multiple issues, some of which were very technical. Such will be the case in this appeal. We therefore believe it appropriate to follow a similar format in this Decision, to the extent our court Rules and legal precedent permit.

A. Applicable Permit provisions: Carrara first obtained an Act 250 permit to operate its quarry in 1988, when the Vermont Environmental Board issued permit #1R0589-EB, along with its Findings of Fact and Conclusions of Law, on February 17, 1988. That permit was issued after Carrara appealed the denial of its permit application by the District Environmental Commission #1, per the Commission’s decision of December 22, 1986. From this first Act 250 permit issued by the former Environmental Board in 1988, Carrara was authorized to use explosives in the Quarry to retrieve rock. The Carrara Quarry was the subject of several other Act 250 applications and revocation proceedings. In connection with its application for a third amendment to its Act 250 permit (see Amended Land Use Permit, Findings of Fact and Conclusions of Law #1R0589-3-EB (3rd Revision),2 all dated April 21, 1994 and hereinafter collectively referred to as the “1994 Amended Permit”), the former Environmental Board established specific standards for notification and monitoring of the blasting and other commercial activities at the Carrara Quarry. While there have been several other permit amendments since then, as summarized below, the 1994 Amended Permit serves as the primary reference point from which Carrara made

2 This third amendment to the Carrara Quarry Permit, Findings and Conclusions went through three revisions as a consequence of various motions to alter filed by the parties who appeared before the former Environmental Board. The first version of this amended Permit, Findings and Conclusions was issued on February 2, 1994. Where the amended Permit is hereinafter referenced in this Decision, such reference is to the third revision to the third amendment to the Carrara Permit, Findings and Conclusions, dated April 21, 1994.

Page 2. application for amendment in the proceedings that are now subject to de novo review in this Court. Since the 1994 Amended Permit was issued, the District Environmental Commission #1 (“District Commission”) issued the following amended permits that govern the Carrara Quarry:

On March 31, 1994, Amended Land Use Permit #1R0589-4 was issued (the “-4 Permit”). It extended certain deadlines to December 31, 1994, relating to the requirement that Carrara acquire certain deer mitigation lands. This amendment also set the permit expiration date at December 31, 1994. On April 12, 1994, Amended Land Use Permit #1R0589-5 was issued (the “-5 Permit”). It established that Carrara has satisfied Conditions 11 and 17 of the 1994 Amended Permit that established a public information program and performance plan for blasting activities at the Carrara Quarry. The District Commission incorporated into this -5 Permit the blasting program and plan proposed by Carrara, pursuant to Conditions 11 and 17. On March 27, 1996, Amended Land Use Permit #1R0589-63 was issued (the “-6 Permit”). Carrara’s application in this proceeding sought and received several amendments to previous permit conditions, of which the following have some materiality to the pending appeal: • Authorization to continue to extract dolomite from the quarry to a depth of 70 feet below the previously permitted ground level; • Installation of a new stormwater discharge system; • Installation of new interior haul roads to serve the quarry facility; • Requirement that Carrara conduct a draw-down and three day pump test on the water supply well that serves homes in the Whispering Pines Mobile Home Park (“WPMHP”), as well as an additional requirement to monitor the WPMHP well for MTBE concentrations and whether increases in such concentrations were caused by the planned deepening of the quarry; • Implementation of further Bureau of Mine Standards for Carrara’s blasting operations; and • Renewed permit expiration date of June 1, 2016. On July 28, 2005, Amended Land Use Permit #1R0589-84 was issued (the “-8 Permit”). This is the permit from which Carrara and the Neighbors identified below appealed. The provisions of this Decision that the parties preserved for our review in this appeal are detailed below.

3 The District Commission subsequently received a request from Carrara for clarification of its -6 Permit. It treated Carrara’s request as a motion to alter and denied essentially all of Carrara’s requests by its Decision of April 16, 1996. 4 It appears that nearly all parties to the proceedings before the District Commission filed motions to alter the Commission’s July 28, 2005 Decision. The Commission granted some requests and denied others, as noted in its Memorandum of Decision on Motions to Alter dated September 20, 2005. To the extent that this latter Decision affected the issues preserved for appeal here, we note it below.

Page 3. B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Denio
608 A.2d 1166 (Supreme Court of Vermont, 1992)
In Re Hawk Mountain Corp.
542 A.2d 261 (Supreme Court of Vermont, 1988)
Everett v. Town of Bristol
674 A.2d 1275 (Supreme Court of Vermont, 1996)
Village of Woodstock v. Bahramian
631 A.2d 1129 (Supreme Court of Vermont, 1993)
In Re Appeals of Garen
807 A.2d 448 (Supreme Court of Vermont, 2002)
In Re Crushed Rock, Inc.
557 A.2d 84 (Supreme Court of Vermont, 1988)
In Re Taft Corners Associates, Inc.
632 A.2d 649 (Supreme Court of Vermont, 1993)
Levy v. Town of St. Albans Zoning Board of Adjustment
564 A.2d 1361 (Supreme Court of Vermont, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Route 103 Quarry, Counsel Stack Legal Research, https://law.counselstack.com/opinion/route-103-quarry-vtsuperct-2006.