Rouse Construction Co. v. Interstate Steel Corp.

CourtCourt of Appeals of Tennessee
DecidedAugust 29, 2001
DocketE2001-00242-COA-R3-CV
StatusPublished

This text of Rouse Construction Co. v. Interstate Steel Corp. (Rouse Construction Co. v. Interstate Steel Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rouse Construction Co. v. Interstate Steel Corp., (Tenn. Ct. App. 2001).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE August 29, 2001 Session

ROUSE CONSTRUCTION COMPANY v. INTERSTATE STEEL CORPORATION

Appeal from the Chancery Court for Knox County No. 137689-3 Sharon Bell, Chancellor

FILED JANUARY 15, 2002

No. E2001-00242-COA-R3-CV

This is a case wherein the Plaintiff/Appellant, Rouse Construction Company, seeks damages for breach of contract from the Defendant/Appellee, Interstate Steel Corporation. The Chancellor found that there was no meeting of minds between the parties as to essential contract terms and, therefore, ordered that Rouse's claim be denied. The Chancellor further determined that Interstate should be allowed a judgment in the amount of $19,090.00 for materials and plans delivered to Rouse. We concur in the determination of the Chancellor and affirm.

Tenn.R.App.P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Cause Remanded

HOUSTON M. GODDARD , P.J., delivered the opinion of the court, in which HERSCHEL P. FRANKS and CHARLES D. SUSANO, JR., JJ., joined.

D. Scott Hurley, Knoxville, Tennessee, for the Plaintiff/Appellant, Rouse Construction Company

Wanda Graham Sobieski and Nanette J. Landen, Knoxville, Tennessee, for the Defendant/Appellee, Interstate Steel Corporation

OPINION

In this appeal from the Knox County Chancery Court the Plaintiff/Appellant, Rouse Construction Company (hereinafter Rouse), contests the ruling of the Knox County Chancery Court in favor of the Defendant/Appellee, Interstate Steel Corporation (hereinafter Interstate) and raises the following issues which we restate:

1. Did the Chancellor err in her determination that there was no meeting of the minds between the parties with respect to essential terms of a construction subcontract which Rouse asserts existed between itself and Interstate? 2. Did the Chancellor err in granting Interstate a judgment for materials and construction plans which Interstate provided to Rouse in connection with a construction project for which Rouse was employed as general contractor?

In August of 1997, Interstate submitted a bid to Rouse to be employed as a subcontractor to provide steel fabrication and erection for a construction project for Grace Baptist Church in Knoxville. Rouse relied on this bid in calculating its own bid to be employed as general contractor on the project.

In late September of 1997, Grace Baptist Church advised Rouse that it had been chosen to serve as general contractor and on or around that same date Rouse notified Interstate that it planned to use Interstate for structural steel fabrication and erection based on Interstate's apparent low bid to perform those services. Shortly thereafter, Interstate began providing some services to the project, transmitting a few framing plans and bolts to the construction site on October 3, 1997, and some erection drawings, nuts, bolts and washers on October 7, 1997.

On October 15, 1997, Dwight Campbell, Rouse's project expediter, sent a fax to Interstate's president, John Goodwin, setting forth a proposed schedule of tentative start dates for steel work by Interstate. However, at a meeting on October 17, 1997, between Mr. Goodwin and Rouse officials, Mr. Goodwin announced that Interstate would not be able to comply with this schedule and presented Rouse with an alternative schedule. Rouse officials testify that the schedule presented by Mr. Goodwin was not separated into construction phases and was rejected. Mr. Goodwin was asked by Rouse to submit a phased schedule with a bar graph showing how each phase of construction would be implemented in relation to the building. It is undisputed that, at the time of the meeting on October 17 there was still no signed contract between the parties.

On October 20, 1997, Joel Perfetto, vice president of Rouse, received a bar graph schedule from Interstate along with a cover memorandum from Mr. Goodwin describing the attached schedule as 'tentative' and noting that, although the attached schedule breaks framing into two sequences, a three unit break would, in his opinion, make the project easier. Mr. Perfetto testifies that he contacted Mr. Goodwin upon receipt of this proposed schedule and memorandum and requested that Mr. Goodwin submit a three phase schedule but that Mr. Goodwin never did so. Mr. Goodwin testifies that Rouse did not respond to the schedule submitted by him on October 20.

The next meeting between Rouse and Interstate took place on November 14, 1997. Mr. Goodwin testifies that at this meeting Mr. Perfetto presented him with yet another schedule which Mr. Goodwin rejected and he describes the dates set forth in that schedule as "somewhat similar, if not tighter, than the one that Dwight Campbell told me was their tentative start up dates. It did not reflect the schedule I gave them on the 20th of October." Mr. Goodwin further testifies that at this meeting he was advised by Rouse that a contract was still being worked on but that it would be finalized by the next week. Pending readiness of the contract, Rouse provided Mr. Goodwin with a sample form contract for his review.

-2- On November 18, 1997, Mr. Goodwin sent a letter to Doug Donohue, president of Rouse, which Mr. Goodwin testifies was prompted by a phone call from Mr. Donohue the previous day wherein Mr. Donohue indicated that Interstate was behind schedule in submission of shop drawings. Mr. Goodwin begins this letter by stating as follows:

In view of the circumstances and your schedule demands, I do not believe we can help you in this project.

We have gone over all aspects of this matter very carefully, and still must contend that the very best we can do, as far as schedule is concerned, does not meet your needs.

The letter also describes the best that Interstate is able to do with respect to scheduling, setting forth those factors upon which such scheduling would be contingent. In closing the letter, Mr. Goodwin states:

If this project schedule becomes more realistic, perhaps we can work with you to the extent as stated above.

Please advise me as soon as possible as we are continuing our efforts and progress on the framing plan portion of this project.

On the day after he received this letter Mr. Donohue called Mr. Goodwin and, according to Mr. Goodwin, inquired as to when Interstate would be able to submit shop drawings for the project. Mr. Goodwin testifies that he advised Mr. Donohue that he would be able to submit the drawings as soon as certain problems were resolved on framing plans. Mr. Goodwin further testifies that this telephone call "eased Dave Donohue's mind in the fact that we were still working on our plans."

The record shows that Interstate continued working on the project during the months of November and December of 1997, specifically by preparing framing plans and shipping bolts, steel beams and steel columns to the construction site. The record also shows that the parties corresponded on various occasions during this time period regarding delivery of materials and other matters related to work being performed on the project by Interstate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swafford v. Harris
967 S.W.2d 319 (Tennessee Supreme Court, 1998)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Bowman v. Bowman
836 S.W.2d 563 (Court of Appeals of Tennessee, 1991)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Forest Inc. of Knoxville v. Guaranty Mortgage Co.
534 S.W.2d 853 (Court of Appeals of Tennessee, 1975)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Rouse Construction Co. v. Interstate Steel Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rouse-construction-co-v-interstate-steel-corp-tennctapp-2001.