Rought v. Price Chopper Operating Co.
This text of 73 A.D.3d 1414 (Rought v. Price Chopper Operating Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
Appeal from an order of the Supreme Court (Ledina, J.), entered April 1, 2009 in Sullivan County, which partially denied defendants’ motion for summary judgment dismissing the complaint.
Plaintiff was employed as an electrician by Demco New York Corporation, a subcontractor for defendant Konover Construction Corporation, the general contractor, at a construction site owned by defendants Price Chopper Operating Company, Inc. and Golub Corporation (hereinafter collectively referred to as the owners). Demco’s supervisor jerry-rigged a system to move heavy commercial wire into place by using a forklift as a power source to pull a rope over two pulleys and through a conduit mounted on the walls of the electrical room of the building under construction. The conduit included turns as it ran up to the ceiling, across the ceiling and then down on the other side of the room. The wires were initially pulled by two men from a large spool on the floor up to the electrical room more than 10 feet above. A bundle of wrapped wires was then lifted or pushed by plaintiff into the beginning of the conduit, which initially ran four feet straight up to the ceiling. The rope pulled up on the wires from inside the conduit as plaintiff stood under the conduit and pushed the bundle of wires up. When the wires reached the first turn in the conduit above plaintiffs head, the rope broke, resulting in the bundle of wires recoiling and falling back onto plaintiff, allegedly causing him to twist, fall and sustain injuries. He commenced this action against defendants alleging negligence and violations of Labor Law §§ 200, 240 (1) and § 241 (6). When defendants moved for summary judgment, Supreme Court partially granted the motion by dismissing the Labor Law § 240 (1) cause of action, but denied it as to the other causes of action. Only defendants appeal.
We turn first to defendants’ contention that they should have been granted summary judgment dismissing plaintiff s Labor Law § 241 (6) cause of action. “[T]he proponent of a summary judgment motion must make a prima facie showing of entitlement to judgment as a matter of law, tendering sufficient evidence to demonstrate the absence of any material issues of fact,” and “[t]he evidence produced by the movant must be viewed in the light most favorable to the nonmovant, affording the nonmovant every favorable inference” (Walton v Albany Community Dev. Agency, 279 AD2d 93, 94-95 [2001] [internal quota[1415]*1415tion marks and citations omitted]; see Sainato v City of Albany, 285 AD2d 708, 710 [2001]; Baker v International Paper Co., 226 AD2d 1007, 1008 [1996]). The pertinent provisions of the Labor Law are liberally construed to ensure safety at construction sites (see Bland v Manocherian, 66 NY2d 452, 459 [1985]). An allegation of a violation of a specific safety regulation can give rise to a viable cause of action under Labor Law § 241 (6) (see Misicki v Caradonna, 12 NY3d 511, 515 [2009]; Morris v Pavarini Constr., 9 NY3d 47, 51 [2007]; Hotaling v Corning Inc., 12 AD3d 1064, 1065 [2004]).
The allegations regarding the condition of the rope—which had broken several times prior to the accident and was repaired with knots—are adequate to implicate a regulation that sets forth sufficient specificity to give rise to a viable Labor Law § 241 (6) cause of action (see 12 NYCRR 23-6.2 [a] [1], [2]; see generally Morris v Pavarini Constr., 9 NY3d at 50).
The location of the wires directly above plaintiff, together with the configuration of the pulley system and the initial vertical pull of four feet, constituted adequate assertions that the wires were being hoisted when the accident occurred (see Hayden v 845 UN Ltd. Partnership, 304 AD2d 499, 500 [2003]). Since the forklift was being used as a substitute power source for hoisting and pulling materials with a rope (and not for its [1416]*1416intended use at a job site), the general exception for forklifts (see 12 NYCRR 23-6.1 [a])—which are governed by other regulations (see 12 NYCRR 23-9.8)—does not, as urged by defendants, lead to the conclusion that the hoisting regulations are totally inapplicable (cf. St. Louis v Town of N. Elba, 70 AD3d 1250, 1251 [2010]). Defendants failed to establish that they were entitled to summary judgment on the Labor Law § 241 (6) cause of action and, thus, we agree with Supreme Court’s decision not to dismiss that cause of action (see Picchione v Sweet Constr. Corp., 60 AD3d 510, 512 [2009]; Giordano v Forest City Ratner Cos., 43 AD3d 1106, 1108 [2007]).
Next, we consider defendants’ argument that plaintiff’s Labor Law § 200 and common-law negligence causes of action should have been dismissed. In order to prevail on these claims, plaintiff “must establish that the owner or contractor both exercised supervisory control over the operation and had actual or constructive knowledge of the unsafe manner in which the work was being performed” (Lyon v Kuhn, 279 AD2d 760, 761 [2001]; see Biance v Columbia Washington Ventures, LLC, 12 AD3d 926, 927 [2004]). Here, Konover’s project superintendent testified that he had been on site on the day of plaintiffs accident and he had the authority to stop the work if, in his opinion, it was not being performed in a safe manner. There also is evidence that Konover provided the forklift and pulleys being used by Demco, and that Konover’s project superintendent directed Demco’s workers to replace a barricade and reposition the pulleys during the operation. This evidence creates a question of fact as to whether Konover exercised the requisite supervisory control over plaintiff’s work (see Rizzuto v L.A. Wenger Contr. Co., 91 NY2d 343, 352-353 [1998]; Detraglia v Blue Circle Cement Co., 7 AD3d 872, 874 [2004]). As for the owners, however, there is no evidence that they exercised any supervision or control over the work activity that brought about plaintiffs injury and, accordingly, the common-law negligence and Labor Law § 200 claims against them must be dismissed (see Comes v New York State Elec. & Gas Corp., 82 NY2d 876, 877-878 [1993]; Fassett v Wegmans Food Mkts., Inc., 66 AD3d 1274, 1276 [2009]).
The remaining arguments have been considered and found to be unavailing.
Mercure, J.E, and Spain, J., concur.
In Narrow v Crane-Hogan Structural Sys. (202 AD2d 841, 842 [1994]), the plaintiffs failed to allege any regulations in their complaint or bill of particulars and, in response to the defendants’ summary judgment motion, they asserted a broad allegation to all of 12 NYCRR subpart 23-6. Since that subpart contains within its sections many provisions, some setting forth general safety standards (see e.g. Schwab v A.J. Martini, Inc., 288 AD2d 654, 656 [2001], lv denied
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
73 A.D.3d 1414, 901 N.Y.S.2d 418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rought-v-price-chopper-operating-co-nyappdiv-2010.