Roubin & Janeiro, Inc.

652 F.2d 70, 28 Cont. Cas. Fed. 81,191, 227 Ct. Cl. 580, 1981 U.S. Ct. Cl. LEXIS 144
CourtUnited States Court of Claims
DecidedMarch 13, 1981
DocketNo. 396-80C
StatusPublished
Cited by10 cases

This text of 652 F.2d 70 (Roubin & Janeiro, Inc.) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roubin & Janeiro, Inc., 652 F.2d 70, 28 Cont. Cas. Fed. 81,191, 227 Ct. Cl. 580, 1981 U.S. Ct. Cl. LEXIS 144 (cc 1981).

Opinion

The government has moved to transfer this government contract case to the General Services Administration Board of Contract Appeals (Board) pursuant to section 10(d) of the Contract Disputes Act of 1978 (Act), 41 U.S.C. § 609(d) (Supp. II 1978), because four other cases arising out of the same contract have been filed with the Board. Plaintiff opposes this motion and has moved to stay proceedings in this court until the Board proceedings have been completed. We grant the government’s motion and deny plaintiffs motion, and transfer this action to the Board.

[581]*581HH

The plaintiff, a construction company, was awarded a fixed-price contract to perform stonework and masonry work in conjunction with the construction of a new federal office building in New Haven, Connecticut. Plaintiff filed with the contracting officer six claims for additional compensation. Each claim was denied. Four were decided by the contracting officer prior to the effective date of the Act and have been appealed to the Board. The remaining two, decided after the effective date of the Act, are consolidated in this direct access proceeding before us under 41 U.S.C. § 609(a). See Warwick Construction, Inc. v. United States, 225 Ct.Cl. 567 (1980).

A general description of each claim follows:

A. GSBA No. 4991 (Foamglass Insulation). Plaintiff sought an equitable adjustment because it was required to use steel studs in installing 4-inch glass insulation to masonry walls. Plaintiff contended that the specifications did not indicate that steel studs should be used. The Board, in a decision entered September 30, 1980, denied the claim and remanded to the contracting officer to determine a downward equitable adjustment due to the government because of plaintiffs "failure to stick up the 4-inch foam-glass insulation blocks with mastic.”

B. GSBA No. 4992 (Storage Space). Plaintiff sought an equitable adjustment because of the unavailability of a proposed storage area which, plaintiff alleged, the site plans indicated was available. Plaintiff contended that this situation caused delivery and construction delays. The Board, in a decision entered October 28, 1980, denied the claim.

C. GSBA No. 5010 (Limestone Coping). Plaintiff sought an equitable adjustment for being required to install coping stone with a return lip, which it asserts was contrary to contract drawings. The Board, in a decision entered January 30, 1981, denied the claim for the increased cost of providing coping stones with a lip, the additonal effort involved, and any delays encountered. The Board, however, upheld plaintiffs claim for the "additional effort required to cut the lip . . . from the coping stones for the balconies” [582]*582and remanded to the contracting officer to determine damages.

D. GSBA No. 5090 (Spandrel Beams). Plaintiff sought an equitable adjustment due to the misalignment of the spandrel beams. The Board has not yet held a hearing on this claim and has suspended further proceedings on it pending the outcome of the litigation presently before us.

E. Ct. Cl. No. 396-80C (Omnibus Claim). This case, presently before us, consists of two counts or claims. Count I challenges the contracting officer’s decision of July 31, 1979, denying plaintiffs impact and delay claim for 234 calendar days of extended time and additional compensation of $565,341. Count II challenges the contracting officer’s decision of June 6, 1980, refusing to release to plaintiff the final contract balance of $56,750.

n.

When multiple suits arise under the same contract, section 10(d) of the Act permits us, "in the interest of justice” to "transfer any suits to or among the agency boards involved.” 41 U.S.C. 609(d). The legislative history admonishes us to "be sensitive to the reasons why the suits have been split [between this court and the Board], and. . . not consolidate only for the sake of consolidation.” S. Rep. No. 95-1118, 95th Cong., 2d Sess. 31, reprinted in [1978] U.S. Code Cong. & Ad. News 5235, 5265.1 The Senate Report continues:

The Court of Claims, when reviewing the decision to consolidate, should not arbitrarily take away the contractor’s right to his day in court by consolidating two suits in the agency boards, and thus forcing one suit out of the court. It is the intent of this section to make available the opportunity to consolidate like suits in one jurisdiction, [583]*583but this action should weigh the position of the parties involved.

Thus, we must balance the plaintiffs reasons for splitting the suits against the government’s interest in consolidating the cases before the Board.

A. The petition in the case before this court overlaps with the four claims before the Board.2

Count I of the petition before this court apparently is an omnibus claim intended to encompass all impact and delay claims arising under the contract. As such, it also covers the claims contained in GSBA 4991 (Foamglass Insulation),3 4992 (Storage Space),4 5010 (Limestone Coping),5 and 5090 (Spandrel Beams).6 The petition, however, goes much further, and includes many additional factors contributing to the delay. Count II involves the same underlying factual issues since it is based upon the government’s retention of [584]*584money due under the contract for "unsatisfactory job progress and deficiencies.”

Plaintiff contends that this case is similar to the example given in note 1, supra, of a situation where Congress believed that consolidation would be inappropriate. It states that the claims before the Board are all "small” and are being handled under the accelerated procedures of Board Rule 12 for claims involving $25,000 or less. On the basis of the papers before us, we cannot decide whether these claims are small and being handled under accelerated procedures.

In a letter to the Board’s Administrative Judge dated November 30,1979, plaintiff indicated that the parties had decided at a pretrial conference that the hearing would be limited to

the issues of liability alone, on each of four appeals. Further, in view of the consolidation of the cases and the aggregation of amounts, the appellant believes that it would not be appropriate to apply Rule 12 accelerated procedures to the consolidated proceedings. Accordingly, appellant withdraws it’s [sic] request for accelerated processing under Rule 12.

The Administrative Judge, in a letter dated December 5, 1979, allowed plaintiffs request. However, only three cases were actually consolidated and, in each, the Administrative Judge stated that plaintiff proceeded "under the optional accelerated procedure provided by our Rule 12.” The government contends that this statement was erroneous.

Furthermore, we are unable to determine the comparative size and substantiality of the Board claims as against the omnibus claim here.

B. In a recent case involving section 10(d) of the Act, we decided, sua sponte,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
45 Fed. Cl. 134 (Federal Claims, 1999)
Giuliani Contracting Co. v. United States
36 Cont. Cas. Fed. 75,882 (Court of Claims, 1990)
Blount, Inc. v. United States
15 Cl. Ct. 146 (Court of Claims, 1988)
Glendale Joint Venture v. United States
34 Cont. Cas. Fed. 75,375 (Court of Claims, 1987)
Multi-Roof Systems Co. v. United States
32 Cont. Cas. Fed. 72,530 (Court of Claims, 1984)
Skip Kirchdorfer, Inc. v. United States
31 Cont. Cas. Fed. 72,231 (Court of Claims, 1984)
E.D.S. Federal Corp. v. United States
30 Cont. Cas. Fed. 70,659 (Court of Claims, 1983)
Santa Fe Engineers, Inc. v. United States
29 Cont. Cas. Fed. 82,635 (Court of Claims, 1982)
Dravo-Groves v. United States
30 Cont. Cas. Fed. 70,186 (Court of Claims, 1982)
Bianchi v. United States
231 Ct. Cl. 729 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
652 F.2d 70, 28 Cont. Cas. Fed. 81,191, 227 Ct. Cl. 580, 1981 U.S. Ct. Cl. LEXIS 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roubin-janeiro-inc-cc-1981.