Blount, Inc. v. United States

15 Cl. Ct. 146, 1988 U.S. Claims LEXIS 124, 1988 WL 72120
CourtUnited States Court of Claims
DecidedJuly 13, 1988
DocketNo. 203-88C
StatusPublished
Cited by2 cases

This text of 15 Cl. Ct. 146 (Blount, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount, Inc. v. United States, 15 Cl. Ct. 146, 1988 U.S. Claims LEXIS 124, 1988 WL 72120 (cc 1988).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

Subject complaint was filed in this court on March 29,1988, by Blount, Inc. (Blount), the successor to Blount Brothers Corporation. Damages in the amount of $415,464 are prayed for pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 601, et seq. (CDA).

Instead of filing an answer to said complaint, on June 13, 1988, there was filed in this court Defendant’s Motion to Transfer and Defendant’s Motion to Suspend Proceedings pending resolution of the transfer motion. The gravamen of defendant’s threshold motion is that subject case should be transferred to the General Services Board of Contract Appeals (GSBCA) pursuant to 41 U.S.C. § 609(d), i.e., the CDA, in the “interest of justice.” After a careful review of the pleadings by the parties, with particular reference to the evidence supportive of the operative criteria bearing on the motion to transfer, this court finds that sound discretion compels that defendant’s motion to transfer should be granted, in the interest of justice. Therefore, said motion to transfer, by this opinion, will be allowed, and defendant’s motion to suspend is, as a consequence, moot.

Facts

Plaintiff, Blount, Inc., is a Delaware corporation which has its principal place of business in Montgomery, Alabama. The General Services Administration (GSA) awarded to Blount Brothers Corporation, [147]*147the predecessor to plaintiff, a lump sum contract for the construction of the Federal Building East project in Portland, Oregon. This agreement, in the amount of $35.5 million, was executed pursuant to Project # NOR26500, and Contract # GS-10P-02633. Various change orders modified said contract, increasing the amount thereof to approximately $40.3 million, of which approximately $39.9 million has been paid to date. Thus, as previously stated, by this action plaintiff seeks to recover, inter alia, $415,464. The basis for said demand stems from the following circumstances: (i) plaintiff sub contracted the access flooring, the integrated ceiling system, and the acoustical ceiling to Washington Acoustical Company, Inc. (WACO); (ii) WACO, in turn, subcontracted with C-Tec, Inc., to provide the raised or “computer” flooring; (iii) in November 1984 and February 1985 plaintiffs predecessor made submissions # 25 and # 122 for payment, which were rejected in August 1985 by GSA; (iv) in January 1986 plaintiff, as a consequence of said rejection, filed certified claim #BB-953 with the contracting officer (CO) in the amount of $415,464 on behalf of WACO; (v) a final decision denying same was issued by the CO on March 31, 1987; and (vi) short of one year thereafter, i.e., March 29, 1988, subject complaint was filed in this court on behalf of the subcontractor.

Prior to filing said complaint in this court, in March 1988, plaintiff’s predecessor also had filed three separate cases with the GSBCA on its behalf as follows: GSBCA #8665 on September 16, 1986; GSBCA #8898 on March 17, 1987; and GSBCA # 8969 on May 5, 1987. One case involved the contractor’s shoring and underpinning system, while the remaining two cases related to the apportionment of the compensable delay claims and disruption of work sequence. These claims before the GSBCA are being handled by the in-house counsel of GSA, whereas subject claim(s) in this court are being defended by the Department of Justice.

Additional claims (other than those pending in this court and before the GSBCA) have been submitted to the CO within GSA by plaintiff, the prime contractor, in the approximate amount of $10 million. Such claims are presently pending. Moreover, WACO, the sub contractor who is actually prosecuting the present claims in this court through plaintiff, also has additional claims presently pending before the CO within GSA.

Discussion

Supportive of its entitlement to the grant of its motion to transfer, defendant relies on the plain and unambiguous language of the Contract Disputes Act, 41 U.S.C. § 609(d), which provides as follows:

If two or more suits arising from one contract are filed in the United States Claims Court and one or more agency boards, for the convenience of parties or witnesses or in the interest of justice, the United States Claims Court may order the consolidation of such suits in that court or transfer any suits to or among the agency boards involved.

(emphasis added). We read the operative provisions of the statute to provide that there are three separate circumstances under which this court “may,” in its discretion, order the transfer of any suit to an agency board. The court may do so if it is—

(i)for the convenience of the parties, or
(ii)for the convenience of witnesses, or
(iii)in the interest of justice.

Given the fact that the disjunctive “or” is used transitionally on two occasions, supra, it is clear, beyond cavil, that the existence of all three criteria is not a prerequisite to the sound exercise of the court’s discretion. To the contrary, the clarity of the foregoing pertinent provisions of the Act leaves no basis for doubt that it is only necessary for the movant to establish the existence of only one of the aforementioned criteria to be entitled to the favorable exercise of the court’s discretion.

Moreover, it is axiomatic that the grant of a party’s motion to transfer and consolidate is subject to the sound discretion of the court. E.D.S. Federal Corp. v. [148]*148United States, 1 Cl.Ct. 212, 214 (1983). In that connection, Warwick Construction, Inc. v. United States, 225 Ct.Cl. 567, 650 F.2d 289 (1980), teaches that a 41 U.S.C. § 609(d) transfer and consolidation may also be effected sua sponte.

Because a motion to transfer and consolidate is often made, as here, by the defendant, and against the wishes of the plaintiff who initiated the action in this court, it is helpful to explicate the legislative history of the CDA and the underlying philosophical bases of said statutory provision. We do so inasmuch as it confirms the court’s perception of the proper construction thereof. The threshold observation is that the court is counseled that—

... when reviewing the decision to consolidate, [or transfer, it] should not arbitrarily take away the contractor’s right to his day in court by consolidating two suits in the agency boards, and thus force one suit out of the court. It is the intent of the section to make available the opportunity to consolidate like suits in one jurisdiction, but this action should weigh the positions of the parties involved.

(emphasis added). S.Rep. No. 95-1118, 95th Cong., 2d Sess. 31, reprinted in 1978 U.S.Code Cong. & Ad.News 5235, 5265. Moreover, we are specifically counseled to not be unmindful

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
45 Fed. Cl. 134 (Federal Claims, 1999)
Giuliani Contracting Co. v. United States
36 Cont. Cas. Fed. 75,882 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
15 Cl. Ct. 146, 1988 U.S. Claims LEXIS 124, 1988 WL 72120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-inc-v-united-states-cc-1988.