Roskam Baking Co. v. Lanham MacHinery Co., Inc.

71 F. Supp. 2d 736, 1999 U.S. Dist. LEXIS 17220, 1999 WL 1005206
CourtDistrict Court, W.D. Michigan
DecidedJuly 15, 1999
Docket5:97-cv-00213
StatusPublished
Cited by7 cases

This text of 71 F. Supp. 2d 736 (Roskam Baking Co. v. Lanham MacHinery Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roskam Baking Co. v. Lanham MacHinery Co., Inc., 71 F. Supp. 2d 736, 1999 U.S. Dist. LEXIS 17220, 1999 WL 1005206 (W.D. Mich. 1999).

Opinion

OPINION

QUIST, District Judge.

Plaintiff, Roskam Baking Company (“Roskam”), has sued Defendants, Lanham Machinery Company, Inc., APV Consolidated, Inc., and APV Baker Company, Inc. (collectively “APV” or “Defendants”), alleging breach of contract and negligence. This Court has diversity jurisdiction over Plaintiffs claims pursuant to 28 U.S.C. § 1332. This matter is before the Court on Defendants’ Motion for Summary Judgment re Breach of Contract and Negligence, Defendants’ Motion for Summary Judgment re Consequential Damages, and Defendants’ Motion for Summary Judgment re Spoliation of Evidence.

Facts

A. Purchase and installation of the oven

On July 21, 1987, Roskam entered into a. written contract with APV for the purchase of an oven for its Butterworth commercial baking facility in Grand Rapids, Michigan, to replace an older model APV oven at the facility. (See 7/15/87 Proposal, Defs.’ Br.Supp.Mot.Summ.J. re Breach of Contract & Negligence Ex. A (hereinafter the “Oven Contract”).) The oven was a large “continuous feed” oven designed to produce approximately 15,000 pounds of bread per hour and was designed to operate at approximately 500F. The bread was fed into the oven on a conveyor which entered through a 42 inch opening at the *739 top front of the oven, which was covered on three sides by a stainless steel draft hood. The bread was fed through the oven on the conveyor and, after baking, exited a similar opening at the bottom of the oven. The new oven was 18 inches taller than the older model, but otherwise had the same dimensions and was installed at the same place in the plant. (9/23/98 Bledsoe Dep. at 132, 134, Pl.’s Resp. Mot.Summ.J. re Breach of Contract & Negligence Ex. A.)

The parties disagree about whether Roskam or APV was responsible for the installation of the new oven, particularly as installation related to the distance between the top of the oven and the ceiling at the Butterworth facility. The Oven Contract provides that Roskam would pay APV $36,204.00 for APV to supervise installation of the oven, but that Roskam was not paying for APV to provide labor, electrical wiring, plumbing; or freight in regards to installation. (See Oven Contract at 3.) The contract goes on to state that “Oven Installation requires beam and or truss modifications in oven area to allow for an additional 18" HT. in oven enclosure and adequate clearances for duct-work and blowers.” (Id.) A handwritten note next to this provision reads “In-house change — Roskam.” (Id.) This section also provides that “[a]ll relocation of existing equipment and or building modifications are not included and will be by [Roskam].” (Id.)

A separate section of the contract, entitled “Work by Buyer,” provides that “[a]ll necessary openings or building alterations or modifications and relocation of equipment as required are by Buyer.” (Id. at 6, ¶ 2.) This section also states that “[i]t is the Buyer’s responsibility to comply with insurance and local safety codes pertaining to building construction, fire, electrical, and steam requirements.” (Id. ¶ 5.) Finally, this section states that “[APV] is not responsible for installation or supervision of any of the above.” (Id. ¶ 9.)

Finally, the Oven Contract states that APV’s liability is limited to repair or replacement of the oven in a case of a defect occurring within the first 2,000 operating hours or the first year from the date of shipment, whichever comes first. (See id. at 7.) The contract also states that APV assumes no “responsibility for the loss of time, downtime, products or equipment damage occasioned by failure of the equipment, whatever the cause.” (Id.)

Garry Bledsoe, one of the APV employees involved in supervising the installation of the oven, discussed with Roskam personnel whether the cross members that connected the ceiling trusses could be raised or removed, as required in the Oven Contract, such that the new oven, which was 18 inches taller than the older model, could be placed in the same location. (See 9/23/98 Bledsoe Dep. at 131; 5/7/98 Bled-soe Dep. at 33, Pl.’s Resp. to Mot. Summ J. re Breach of Contract & Negligence Ex. B.) Although Bledsoe thought that the oven could have been installed in a different area where the trusses were already removed, he did not suggest to Roskam the possibility of installing the oven in a different location, as the existing location already had a conveyor and a concrete pad to use as a foundation for the oven and Roskam requested that the new oven be installed in the same area. (See 9/23/98 Bledsoe Dep. at 133-34.) The trusses were then removed by Roskam. (See 5/7/98 Bledsoe Dep. at 58.)

APV also decided that the draft hood, which extended 26 inches above the top of the oven, would be attached to the wood roof by either metal chains or threaded metal rods. (See Black Dep. at 59-61, PL’s Resp. to Mot.Summ.J. re Breach of Contract & Negligence Ex. C.) APV was aware at the time it installed the oven of the possibility that hot air could come out of the top of the oven during operation due to a phenomenon called “chimney effect.” (See Stephen Smith Dep. at 25-29, PL’s Resp. to MotSumm.J. re Breach of Contract & Negligence Ex. H.) However, *740 Bledsoe testified that he was only concerned about the clearance of the oven concerning the cross structures between the trusses, and that the issue of the clearance between the top of the oven and the ceiling “was not a relevant factor there.” (5/7/98 Bledsoe Dep. at 58.) Bledsoe testified that the modifications that Roskam made in accordance with APV’s suggestions were satisfactorily completed. (See 5/7/98 Bledsoe Dep. at 111.)

B. OSHA inspection

On September 3, 1994, pursuant to a separate written agreement between APV and Roskam, APV conducted an OSHA inspection of the oven. (See 9/3/94 OSHA Inspection Procedure, Defs.’ Br.Supp.Mot. Summ J. re Breach of Contract & Negligence Ex. F (hereinafter the “OSHA Inspection Contract”).) The OSHA Inspection Contract states that the inspection was to be conducted pursuant to OSHA regulations, under which “APV has undertaken to inspect all safety devices on the Equipment.” (Id. at ¶ 2.) The OSHA Inspection Contract defines “safety device” as a feature designed to shut down part or all of the equipment “due to a dangerous condition of an abnormal function in the equipment.” (Id.) The OSHA Inspection Contract also states that:

APV has not undertaken to advise customer as to other safety features, safeguards ir procedures which might be utilized by Customer to improve the safety features or other characteristics of the Equipment, and Customer has not requested that APV do so. Therefore APV does not warrant or represent that the Equipment.is “safe” or employs all safety features which are necessary or desirable in equipment of this type.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robertet Flavors, Inc. v. Tri-Form Construction Inc.
1 A.3d 658 (Supreme Court of New Jersey, 2010)
United Medical Supply Co. v. United States
77 Fed. Cl. 257 (Federal Claims, 2007)
Agri-Mark, Inc. v. Niro, Inc.
233 F. Supp. 2d 200 (D. Massachusetts, 2002)
Busch v. Dyno Nobel, Inc.
40 F. App'x 947 (Sixth Circuit, 2002)
Dominguez v. LANHAM MACHINERY CO., INC.
122 F. Supp. 2d 852 (W.D. Michigan, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
71 F. Supp. 2d 736, 1999 U.S. Dist. LEXIS 17220, 1999 WL 1005206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roskam-baking-co-v-lanham-machinery-co-inc-miwd-1999.