Rose Electric, Inc. v. Cooler Erectors of Atlanta, Inc.

794 S.E.2d 382, 418 S.C. 424, 2016 S.C. App. LEXIS 119
CourtCourt of Appeals of South Carolina
DecidedSeptember 28, 2016
DocketAppellate Case No. 2014-001633; Opinion No. 5444
StatusPublished
Cited by2 cases

This text of 794 S.E.2d 382 (Rose Electric, Inc. v. Cooler Erectors of Atlanta, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rose Electric, Inc. v. Cooler Erectors of Atlanta, Inc., 794 S.E.2d 382, 418 S.C. 424, 2016 S.C. App. LEXIS 119 (S.C. Ct. App. 2016).

Opinion

LOCKEMY, C.J.:

In this dispute arising out of a construction project, Rose Electric, Inc. (Rose Electric) appeals the trial court’s order finding for Southern Produce, Inc. (Southern) and S2P, LLC, (S2P) (collectively Respondents) arguing the trial court erred in (1) finding an expressed contract barred its recovery under the theory of quantum meruit; (2) finding Rose Electric did not establish the elements of its quantum meruit claim; (3) and failing to award Rose Electric damages.

FACTS

Southern is in the business of processing produce for sale. In the fall of 2010, Southern leased a parcel of land from S2P in the new South Carolina Farmers Market in Lexington County. On October 27, 2010, Southern entered into a “flat fee, turnkey contract” with Cooler Erectors of Atlanta (Cooler Erectors) to construct a refrigerated processing center on the property.

[428]*428During the first week of November 2010, Morris Teasley, the president of Cooler Erectors, contacted Homer Rose, the owner of Rose Electric, about subcontracting the electrical work on the Southern project. Cooler Erectors and Rose Electric worked on three other projects at the new Farmers Market prior to working on the Southern project. Rose Electric agreed to complete the work; however, Rose Electric and Cooler Erectors did not discuss a price for the Southern project.

During the project Southern asked Rose Electric to modify . the plans and materials Rose Electric received from Cooler Erectors. Rose Electric agreed to make those changes.

Throughout the construction process, Southern paid Cooler Erectors $203,277.00 of the project’s $213,385.00 contract price. However, Cooler Erectors did not pay Rose Electric. Eventually, Rose Electric filed a mechanics’ lien on Southern’s property. The statement of account attached to the mechanics lien claimed Rose Electric was owed $54,339.13 for the “Total Contract Price” and $10,755.39 for “Change Orders.”

On May 20, 2011, Rose Electric filed its complaint alleging causes of action for foreclosure of its mechanics’ lien, breach of contract, unjust enrichment, and quantum meruit. During opening statements, Rose Electric notified the trial court it would only be pursuing its equitable cause of action for quantum meruit.

The trial court issued its order finding for Respondents on January 30, 2014. The trial court found an expressed contract existed between Rose Electric and Southern for the change orders and between Rose Electric and Cooler Erectors for the original scope of work. The trial court recognized Rose Electric elected not to proceed on its contract claims; therefore, the trial court found for Respondents. The trial court found the existence of an expressed contract precluded Rose Electric from recovery under quantum meruit. In the alternative, the trial court found Rose Electric failed to establish the elements of quantum meruit because Southern paid all but $10,108.00 of the contract price to Cooler Erectors and offered to pay Rose Electric for the change orders and a prorated share of the retainage.

[429]*429STANDARD OP REVIEW

Quantum meruit is an equitable doctrine to allow recovery for unjust enrichment. Columbia Wholesale Co., Inc. v. Scudder May N.V., 312 S.C. 259, 261, 440 S.E.2d 129, 130 (1994). “When reviewing an action in equity, an appellate court reviews the evidence to determine facts in accordance with its own view of the preponderance of the evidence.” Boykin Contracting, Inc. v. Kirby, 405 S.C. 631, 637, 748 S.E.2d 795, 798 (Ct. App. 2013).

LAW/ANALYSIS

a) Existence of a Contract

Rose Electric argues the trial court erred in finding an express contract between Rose Electric and Cooler Erectors for the scope of work under the original plans and between Rose Electric and Southern for the change orders because there was no assent to the price term of either agreement. We agree.

“A contract is an obligation which arises from actual agreement of the parties manifested by words, oral or written, or by conduct.” Stanley Smith & Sons v. Limestone College, 283 S.C. 430, 433, 322 S.E.2d 474, 477 (Ct. App. 1984). “If agreement is manifested by words, the contract is said to be express.” Id.; see also 13 Am. Jur. 2d Building & Constr. Contracts § 5 (2009) (“Where the parties to a building contract have orally agreed to the terms of performance and the price, there is an express contract.” (emphasis added)). “If [the contract] is manifested by conduct, it is said to be implied.” Stanley Smith & Sons, 283 S.C. at 434, 322 S.E.2d at 477.

“Certain terms, such as price, time and place, are considered indispensable and must be set out with reasonable certainty.” McPeters v. Yeargin Const. Co., Inc., 290 S.C. 327, 331, 350 S.E.2d 208, 211 (Ct. App. 1986); see also Stanley Smith & Sons, 283 S.C. at 434, 322 S.E.2d at 477 (noting price is an essential term in a construction contract). Even if the parties intend to be bound by an agreement, the absence of material terms renders the agreement unenforceable. Stevens [430]*430& Wilkinson of S.C., Inc. v. City of Columbia, 409 S.C. 568, 579, 762 S.E.2d 696, 701 (2014).

We find the trial court erred in finding an express contract between Rose Electric and Cooler Erectors and Rose Electric and Southern. The evidence presented showed each of the three parties intended to be bound to their agreements. Rose Electric began working prior to signing an agreement and Homer Rose testified, “We had previously done work for Cooler Erectors of Atlanta. We had completed three jobs, all of which we had been paid well. We had been paid on demand.” However, Rose acknowledged Rose Electric did not have a written contract with Cooler Erectors, nor had the two parties agreed to a contract price. Rather, Rose Electric sent Cooler Erectors invoices based on the time and cost of materials used. No evidence was presented to support the trial court’s finding that Rose Electric and Cooler Erectors manifested an agreement on the price of the electrical work required on the Southern project, which our courts require as an essential term in construction contracts. See Stanley Smith & Sons, 283 S.C. at 434, 322 S.E.2d at 477 (noting price is an essential term in a construction contract); McPeters, 290 S.C. at 331, 350 S.E.2d at 211 (“Certain terms, such as price, time and place, are considered indispensable and must be set out with reasonable certainty.”). Therefore, the trial court erred in finding an express contract between Cooler Erectors and Rose Electric.

We also find the trial court erred in finding an express contract between Rose Electric and Southern. At several points during the construction, Dan Stocker, the general manager of Southern, requested Rose Electric modify the electrical plans to better accommodate Southern’s anticipated uses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
794 S.E.2d 382, 418 S.C. 424, 2016 S.C. App. LEXIS 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rose-electric-inc-v-cooler-erectors-of-atlanta-inc-scctapp-2016.