Rose Construction v. Raintree Dev.

CourtCourt of Appeals of Tennessee
DecidedJanuary 23, 2001
DocketW2000-01388-COA-R3-CV
StatusPublished

This text of Rose Construction v. Raintree Dev. (Rose Construction v. Raintree Dev.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rose Construction v. Raintree Dev., (Tenn. Ct. App. 2001).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON January 23, 2001 Session

ROSE CONSTRUCTION, INC. v. RAINTREE DEVELOPMENT COMPANY, LLC

An Appeal from the Chancery Court for Shelby County No. 110162-1 Walter L. Evans, Chancellor

No. W2000-01388-COA-R3-CV - December 31, 2001

This is an arbitration case. The plaintiff construction company agreed to construct the defendant developer’s planned development project. When disputes arose out of the parties’ performance, they terminated the contract. The parties then entered into arbitration. The arbitration panel found in favor of the plaintiff for $974,068.00 plus interest, including a $250,000 award for attorney’s fees. The plaintiff filed an action in the chancery court, seeking confirmation of the award. The defendant asked the chancery court to vacate the arbitration award. The trial court vacated the entire award, finding that the arbitration panel exceeded its authority in awarding attorney’s fees. The plaintiff construction company appeals. We reverse, finding that the award of attorney’s fees is authorized under the parties’ contract, and remand the case for confirmation of the arbitration award in toto.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court is Reversed and Remanded.

HOLLY K. LILLARD , J., delivered the opinion of the court, in which ALAN E. HIGHERS , J., and DAVID R. FARMER , J., joined.

Christopher M. Caputo, Michael I. Less, and Clifton M. Lipman, Memphis, Tennessee, for the appellant, Rose Construction, Inc.

Larry E. Parrish, Memphis, Tennessee, for the appellee, Raintree Development, LLC.

OPINION

This is an appeal from the trial court’s order vacating an arbitration award. On January 29, 1996, Rose Construction, Inc. (“Rose”), and Raintree Development Company, LLC (“Raintree”), entered into a construction agreement under which Rose agreed to construct the Raintree Planned Development Project (“the project”) in Collierville, Tennessee. In Section 4.5.1 of the construction agreement, the parties agreed to arbitrate all controversies arising out of the contract “in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association” (“Arbitration Rules”). Rule L-6 of the Arbitration Rules provides that any award resulting from such arbitration may include “an award of attorneys’ fees if all parties have requested such an award or it is authorized by law or their arbitration agreement.” The parties agree that Rule L-6 is incorporated into the contract by reference.

After work on the project was substantially completed, disputes arose between the parties regarding change orders, the quality of the workmanship, and payments due. On October 9, 1997, Raintree terminated the contract. On October 15, 1997, Rose notifed Raintree that Rose had terminated the contract on September 30, 1997 because of Raintree’s failure to pay.

On October 29, 1997, Rose filed a demand for arbitration. On November 7, 1997, Rose filed suit against Raintree in the Shelby County Chancery Court to enforce a mechanic’s lien it had previously filed. On November 26, 1997, Rose filed a motion to stay the litigation pending resolution of the previously filed arbitration demand. On August 11, 1998, despite Raintree’s persistent attempts to resist arbitration, the trial court entered an order staying the litigation pending resolution of the arbitration proceedings.

On March 15, 1999, by certified letter, Rose notified Raintree that it intended to seek an award of attorney’s fees under the Tennessee Prompt Pay Act. See Tenn. Code Ann. § 66-34-101, et seq. (1993 & Supp. 2001) (“The Act”). From March 29 to April 19, 1999, the arbitration panel1 conducted the arbitration proceedings. At the arbitration hearing, Rose argued that it was entitled to attorney’s fees under the Act because of Raintree’s bad faith. On April 6, 1999, the arbitration panel entered an order permitting Rose to introduce evidence on that issue.

On June 21, 1999, the arbitration panel issued an award in favor of Rose. The panel ordered Raintree to pay Rose the following: (1) $789,068 for construction costs, (2) $60,000 for a pass- through claim of a Rose subcontractor, (3) $250,000 in attorney’s fees under the Prompt Pay Act, and (4) pre-award and post-award interest at a rate of ten percent (10%). The arbitration panel also determined that Raintree was entitled to a credit of $125,000 for work remaining on the project, making the total amount awarded to Rose $974,068.00 plus interest.

On June 25, 1999, Rose filed a motion in chancery court for summary judgment and to confirm the award of the arbitration panel. On August 11, 1999, Raintree filed its own motion for summary judgment, arguing that the award should not be confirmed. On November 30, 1999, Raintree filed a memorandum with the chancery court arguing, inter alia, that the arbitration award should be vacated in its entirety because the arbitration panel exceeded its authority in awarding attorney’s fees.

On the same date, November 30, 1999, the trial court conducted a hearing on whether to confirm or vacate the award of the arbitration panel. At the hearing, the trial judge stated that “this court in reading [Arnold v. Morgan Keegan & Co., 914 S.W.2d 445 (Tenn. 1996),] is satisfied that

1 The p anel m embers w ere Lew is H. Con ner, Jr., David K. Taylor, and Edw in Rod gers.

-2- the court cannot vacate an award due to an error of law or error of fact or because it disagrees with the arbitrators.” The trial court then expressed its intent to “on its own motion modify the award to exclude the award of attorney’s fees. And the Court will confirm all the other aspects of the award.” However, no order was entered as a result of that hearing.

Thereafter, the trial court sent counsel for the parties its proposed findings of fact and conclusions of law. On March 3, 2001, the trial court conducted a hearing to address the comments and concerns of the parties on the proposed findings. Subsequently, on March 30, the trial court issued an Order and a detailed Memorandum of Law, changing its original position and vacating the entire arbitration award. In its Memorandum, the trial court found that the parties had entered into a valid arbitration agreement, but that “[t]here is no basis or foundation in the enumerated language of the contract which allows for the award of attorney fees in the event of arbitration.” The trial court therefore held that the award of attorney’s fees to Rose “goes outside and beyond the arbitration agreement” itself. With respect to Rose’s assertion that the Prompt Payment Act authorized such relief, the trial court found that the Act applied “only in a ‘chancery court’ lawsuit,” and that the Act was “clearly not applicable” in arbitration proceedings. (Emphasis in original). Moreover, the trial court held that Tennessee Code Annotated § 29-5-31 prohibits the award of attorney’s fees in arbitration proceedings unless such relief is provided for in the arbitration agreement. Finally, the trial court held that Raintree’s due process rights were violated because Raintree was not given sufficient notice of Rose’s intent to seek attorney’s fees, and because the arbitration panel failed to issue a ruling before the commencement of the hearing that Rose was entitled to seek attorney’s fees. The trial court then vacated the entire arbitration award because “[t]he award of attorney fees under the Prompt Pay Act by the arbitrators constituted more than just a mere error in construing the prevailing law, but was a complete failure to apply the law or the contract.” From this order, Rose now appeals.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Wilson v. Moore
929 S.W.2d 367 (Court of Appeals of Tennessee, 1996)
Arnold v. Morgan Keegan & Co., Inc.
914 S.W.2d 445 (Tennessee Supreme Court, 1996)
D & E Construction Co. v. Robert J. Denley Co.
38 S.W.3d 513 (Tennessee Supreme Court, 2001)
Gabel v. Lerma
812 S.W.2d 580 (Court of Appeals of Tennessee, 1990)
Williams v. McMinn County
352 S.W.2d 430 (Tennessee Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
Rose Construction v. Raintree Dev., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rose-construction-v-raintree-dev-tennctapp-2001.