Ronald B. "Bud" Forman, Arbors Development, LLC, and the Rosebud Development, Ltd. v. Classic Century Homes, LTD.

Court of Appeals of Texas·Decided December 9, 2014·No. 02-12-00362-CV·Published

Opinion

COURT OF APPEALS

SECOND DISTRICT OF TEXAS

FORT WORTH

NO. 02-12-00362-CV

RONALD B. "BUD" FORMAN, ARBORS APPELLANTS DEVELOPMENT, LLC, AND THE ROSEBUD DEVELOPMENT, LTD.

V.

CLASSIC CENTURY HOMES, LTD. APPELLEE

------------

FROM THE 67TH DISTRICT COURT OF TARRANT COUNTY TRIAL COURT NO. 67-233602-08

----------

MEMORANDUM OPINION1

----------

I. Introduction

In three issues, Appellants Ronald B. “Bud” Forman; Arbors Development, LLC; and The Rosebud Development, Ltd. (collectively, the Developers) appeal

1 See Tex. R. App. P. 47.4.

the trial court’s Modified Final Judgment. We will affirm in part and reverse and remand in part.

II. Procedural Background and Statement of Facts The Developers entered into two contracts, Phase I and Phase II, with Appellee Classic Century Homes, Inc. (Classic) regarding residential lots located within the Rosebud Development. The Phase I contract was signed August 16, 2002, and required Classic to purchase sixty-four single-family lots according to a set schedule, referred to as a “Takedown Schedule.” The Phase II contract was signed August 31, 2005, and required Classic to purchase forty-three additional lots as set forth in a second Takedown Schedule. The Phase II contract also required Classic to pay interest as set forth in the contract and all ad valorem taxes, prorated from the date of the initial “Closing” to each respective purchase date.2 Instead of purchasing forty-three lots by the required date of May 27, 2007, under the Phase II Takedown Schedule, Classic purchased only twenty lots and did not pay the interest or ad valorem taxes on the remaining unpurchased twenty-three lots.

In addition, at closing, the Phase II contract required Classic to “reimburse”

the Developers $1,915.00 per lot for prepaid water taps or a “capital improvement fee.” Therefore, for each of the Phase II lots purchased by Classic,

2 The contract stipulated that “the purchase and sale of the Lots shall be closed in separate transactions . . . .”

it paid the capital improvement fee to the Developers.3 However, in mid-2008 Classic learned that the Developers had not paid all the Phase II capital improvement fees. In response, the Developers explained that (1) it was the general course of business of the Developers to pay the fees when Classic was ready to begin construction, (2) it was against the water district’s policy to allow a developer to reserve a water meter for each specific lot, and (3) the district limited the number of meters that could be reserved at one time based on availability. The record does not contain an explanation of why then there was a “prepaid” provision in the contract.

In connection with borrowing money from the bank to purchase each lot under Phase I and Phase II, which included the capital improvement fee, a HUD- 1 Settlement Statement was furnished to the bank. In each Settlement Statement, the Developers asserted that the capital improvement fee had been paid. However, in what the Developers asserted was their general course of business, it did not pay a fee for each lot but instead paid for a group of lots and then applied the fee to individual lots as builders began construction. According to Classic, the Developers did not disclose this methodology. Consequently, twenty-five of the lots’ capital improvement fees had not been paid and as a result, those fees would have to be paid “again” in order for Classic to begin building.

3 Classic paid a total of $19,150 for the prepaid water meters under the Phase II contract.

As a result of its paying capital improvement fees that had in fact not been paid, Classic sued the Developers on October 28, 2008,4 asserting breach of contract and fraud, among other causes of action. The Developers counterclaimed for Classic’s failure to purchase all of the lots agreed to pursuant to the Takedown Schedules. After a trial to the bench, with findings of fact and conclusions of law made, the trial court awarded compensatory and exemplary damages to Classic and a take nothing judgment as to the Developers’ counterclaim. This appeal resulted.

III. Trial to the Bench and Evidentiary Sufficiency Challenges A trial court’s findings of fact have the same force and dignity as a jury’s answers to jury questions and are reviewable for legal and factual sufficiency of the evidence to support them by the same standards. Catalina v. Blasdel, 881 S.W.2d 295, 297 (Tex. 1994); Anderson v. City of Seven Points, 806 S.W.2d 791, 794 (Tex. 1991); see also MBM Fin. Corp. v. Woodlands Operating Co., 292 S.W.3d 660, 663 n.3 (Tex. 2009).

We may sustain a legal sufficiency challenge only when (1) the record discloses a complete absence of evidence of a vital fact, (2) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact, (3) the evidence offered to prove a vital fact is no more than a mere scintilla, or (4) the evidence establishes conclusively the opposite of a vital

4 The Second Amended Petition was the live pleading at trial.

fact. Uniroyal Goodrich Tire Co. v. Martinez, 977 S.W.2d 328, 334 (Tex. 1998), cert. denied, 526 U.S. 1040 (1999); Robert W. Calvert, “No Evidence” and “Insufficient Evidence” Points of Error, 38 Tex. L. Rev. 361, 362–63 (1960). In determining whether there is legally sufficient evidence to support the finding under review, we must consider evidence favorable to the finding if a reasonable fact-finder could and disregard evidence contrary to the finding unless a reasonable fact-finder could not. Cent. Ready Mix Concrete Co. v. Islas, 228 S.W.3d 649, 651 (Tex. 2007); City of Keller v. Wilson, 168 S.W.3d 802, 807, 827 (Tex. 2005).

Any ultimate fact may be proved by circumstantial evidence. Russell v.

Russell, 865 S.W.2d 929, 933 (Tex. 1993). A fact is established by circumstantial evidence when the fact may be fairly and reasonably inferred from other facts proved in the case. Id. However, to withstand a legal sufficiency challenge, circumstantial evidence still must consist of more than a scintilla. Blount v. Bordens, Inc., 910 S.W.2d 931, 933 (Tex. 1995).

When reviewing an assertion that the evidence is factually insufficient to support a finding, we set aside the finding only if, after considering and weighing all of the evidence in the record pertinent to that finding, we determine that the credible evidence supporting the finding is so weak, or so contrary to the overwhelming weight of all the evidence, that the answer should be set aside and a new trial ordered. Pool v. Ford Motor Co., 715 S.W.2d 629, 635 (Tex. 1986)

(op. on reh’g); Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986); Garza v. Alviar, 395 S.W.2d 821, 823 (Tex. 1965).

IV. Laches

In its first issue, the Developers assert that Classic’s claims are barred by the doctrine of laches and by the contractual provision that all representations by either party only survive the contract by one year.

To prevail on the affirmative defense of laches in this case, the Developers had to show that (1) Classic had a legal or equitable right and unreasonably delayed in asserting that right, and (2) the Developers suffered harm as a result of the delay. Frequent Flyer Depot, Inc. v. Am. Airlines, Inc., 281 S.W.3d 215, 229 (Tex. App.—Fort Worth 2009, pet. denied) (citing Rogers v. Ricane Enterprises, Inc., 772 S.W.2d 76, 80 (Tex. 1989)); see also City of Fort Worth v. Johnson, 388 S.W.2d 400, 403 (Tex. 1964).

Free access — add to your briefcase to read the full text and ask questions with AI

Ronald B. "Bud" Forman, Arbors Development, LLC, and the Rosebud Development, Ltd. v. Classic Century Homes, LTD., (Tex. Ct. App. 2014).

Ronald B. "Bud" Forman, Arbors Development, LLC, and the Rosebud Development, Ltd. v. Classic Century Homes, LTD. (Ronald B. "Bud" Forman, Arbors Development, LLC, and the Rosebud Development, Ltd. v. Classic Century Homes, LTD.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Southwestern Bell Telephone Co. v. Garza
164 S.W.3d 607 (Texas Supreme Court, 2004)
Central Ready Mix Concrete Co. v. Islas
228 S.W.3d 649 (Texas Supreme Court, 2007)
Columbia Medical Center of Las Colinas, Inc. v. Hogue
271 S.W.3d 238 (Texas Supreme Court, 2008)
In Re J.O.A.
283 S.W.3d 336 (Texas Supreme Court, 2009)
Aquaplex, Inc. v. Rancho La Valencia, Inc.
297 S.W.3d 768 (Texas Supreme Court, 2009)
Swain v. Wiley College
74 S.W.3d 143 (Court of Appeals of Texas, 2002)
Harris v. Archer
134 S.W.3d 411 (Court of Appeals of Texas, 2004)
McLaughlin, Inc. v. Northstar Drilling Technologies, Inc.
138 S.W.3d 24 (Court of Appeals of Texas, 2004)
Williams v. Glash
789 S.W.2d 261 (Texas Supreme Court, 1990)
AR Clark Investment Company v. Green
375 S.W.2d 425 (Texas Supreme Court, 1964)
In the Interest of G. M.
596 S.W.2d 846 (Texas Supreme Court, 1980)
State v. Addington
588 S.W.2d 569 (Texas Supreme Court, 1979)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Alamo National Bank v. Kraus
616 S.W.2d 908 (Texas Supreme Court, 1981)
Rogers v. Ricane Enterprises, Inc.
772 S.W.2d 76 (Texas Supreme Court, 1989)
Valsangiacomo v. Americana Juice Import, Inc.
35 S.W.3d 201 (Court of Appeals of Texas, 2000)
Frequent Flyer Depot, Inc. v. American Airlines, Inc.
281 S.W.3d 215 (Court of Appeals of Texas, 2009)