Romans v. Shannon

1921 OK 37, 195 P. 298, 80 Okla. 199, 1921 Okla. LEXIS 31
CourtSupreme Court of Oklahoma
DecidedFebruary 1, 1921
Docket9805
StatusPublished
Cited by17 cases

This text of 1921 OK 37 (Romans v. Shannon) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Romans v. Shannon, 1921 OK 37, 195 P. 298, 80 Okla. 199, 1921 Okla. LEXIS 31 (Okla. 1921).

Opinion

PITCHFORD, J.

This is an appeal from the judgment of the district court of Creek county, in which judgment was rendered for the defendant. The cause was by an agreement tried to the court without jury.

The plaintiff contracted with the defendant 'to do certain work and labor in the construction of certain miles or road in Creek county. The material portion of the contract is as follows:

“First. The party of the second part agrees to move dirt for twenty (20c) per yard; loose rock for fifty cents (50c) per yard; solid rock for eighty (80c) per yard, and one and one-half cents for overhaul; twenty-five ($25.00) per acre for clearing right-of-way.”

On the trial, plaintiff introduced Mr. Whittlesey, city engineer of Sapulpa, Okla^ homa. On cross-examination of this witness, it developed that, in computing the amount of earth moved, plaintiff was given credit for the earth moved out of the excavation and credit for the same dirt when built up into an embankment. That is, if the plaintiff moved 100 yards out of an excavation and *200 moved it and loaded up a grade, or built up a grade, lie would be credited with 100 yards of dirt moved out of an excavation and 100 moved into embankment, and would be entitled to a credit for moving 200 yards of dirt — in other words, pay for two ways.

The witness admitted that, if moving earth as contemplated by the contract in question meant that the plaintiff was to be credited with moving earth once where he took it out of an excavation and put it in a fill, his figures would not be correct; that is, if the contract called for a one-way haul instead of a two-way haul, and if the contract should be construed to contemplate a one-way haul the witness was not prepared to say that the estimate of the defendant was wrong.

At this point the court indicated that in his judgment this method of computing the work done by the plaintiff was not warranted by the contract, and that the plaintiff should be credited with moving the earth only once.

Whereupon the following colloquy occurred between the court and plaintiff’s attorney:

“Mr. Lytle: I believe, if your Honor please, that it is a question that the court should be informed upon unless the court feels competent himself. The Court: You don’t offer to plead any custom with reference to the construction of this contract. Mr. Lytle: We are not asking to prove a custom, we are not pleading a custom, and we are not talking about a custom, but the question is whether the words rised have a technical and distinct meaning in the line of civil engineering. The Court. Do you plead it? Mr. Lytle: No; we don’t need to plead it. The Court: Gentlemen, I take the view from this contract that the witness’ theory and interpretation of it is erroneous. I take the view that the contract is unambiguous so far as appears upon its face; that the words of the contract are to be given their plain and ordinary meaning. An agreement that one must remove dirt at twenty cents a yard means he must only get twenty cents for handling the dirt; and in that part of the contract which provides that if he hauls the dirt over a certain distance he is to get a cent and a half per cubic yard, there is no ambiguity. It does not occur to me that reasonable minds could differ over the plain, common meaning of these words; and I am rather of the opinion that the objection or motion should be sustained as to the testimony of the witness on moving earth.”

To which ruling the plaintiff excepted and asked leave to amend his petition and to make proof by the witness Whittlesey, as follows:

“By alleging that the expression contained in the contract, ‘move dirt for twenty cents per yard,’ meant and means according to the custom in this vicinity of engineers and of, contractors engaged in the building and construction of roads and highways that a person so agreeing to move dirt is entitled under such custom to the amount of compensation per yard for the earth excavated, and is also entitled to the same compensation for the various fills made by him; and in connection with this request to amend our petition, we offer to prove at this time, by this witness, who is city engineer of Sa-pulpa, that he is familiar and has been for a long while, while the construction of roads and highways and of railroads and of the contracts in connection therewith, and that the term ‘move dirt,’ when so employed and not modified in any respect, means that the person agreeing to move said dirt shall receive the compensation fixed in the contract for excavating and shall also receive the same compensation for the construction of the fills in the highway.”

The court refused the amendment and offer of testimony, and this presents the whole proposition presented on this appeal: •That is, was the court correct in refusing the amendment and the testimony offered in support thereof?

It is a principle of law, universally accepted, that, in the absence of fraud, accident. or mistake, parol evidence is not admissible to vary or contradict the expressed terms of a written contract. The language used is to govern its interpretation, if the language is clearly explicit and does not involve an uncertainty, and the words used are to be understood in their ordinary and proper sense, and ordinarily where there is no uncertainty, and when the language is plain and unambiguous, extrinsic evidence as to its meaning is not admissible.

The purpose of the law is to try to ascertain the intentions of the parties concerned; however, when the language used is ambiguous, or when the words are used in a local or technical sense, peculiar to certain trades or occupations, parol testimony of usage or custom may be resorted to, but this exception is only allowed to explain what is ambiguous, and where the words used are plain, uncertain, parol evidence should not be permitted on the theory that custom would give an entirely different meaning.

The rule of construction stated by Elliott on Contracts, vol. 8, 1913-1918 Supplement, sec." 1506, is as follows:

“A plain and unambiguous contract leaves no room for construction. The courts will try to. give a contract such construction as will make it certain, hut cannot change its terms or make a new contract.”

In Strange et al. v. Hicks et al., 78 Okla. 1, 188 Pac. 347, it is said as follows:

*201 “The paramount rule for the construction of a contract is to ascertain the intent of the parties at the time the contract was entered into and to give effect to same if it can he done consistent with legal principles. If the language of a contract is such as to clearly show the intent of piarties, Vthen there is no need to apply any technical rules of construction, for where there is no doubt, there is no room for construction.”

In Wolf et al. v. Blackwell Oil & Gas Co. et al., 77 Okla. 81, 186 Pac. 484, the court says:

“The language of a contract is to govern its interpretation, if the language is clear and explicit and does not involve an absurdity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Pickering
541 P.2d 1361 (Court of Civil Appeals of Oklahoma, 1975)
Dooley v. Hall Cordes
1967 OK 203 (Supreme Court of Oklahoma, 1967)
Commerce Acceptance Co. v. Campbell
1962 OK 18 (Supreme Court of Oklahoma, 1962)
Cities Service Oil Co. v. Geolograph Co., Inc.
1953 OK 69 (Supreme Court of Oklahoma, 1953)
Owens v. Cohlman
1938 OK 180 (Supreme Court of Oklahoma, 1938)
Cooke v. Kinkead
1936 OK 744 (Supreme Court of Oklahoma, 1936)
Higby v. Martin
1933 OK 360 (Supreme Court of Oklahoma, 1933)
First National Bank of Ft. Smith v. Dunklin
1930 OK 534 (Supreme Court of Oklahoma, 1930)
Rogers v. Kinney
1926 OK 769 (Supreme Court of Oklahoma, 1926)
Green v. Cox MacHinery Co.
1926 OK 43 (Supreme Court of Oklahoma, 1926)
Horse Shoe Mining Co. v. Red Rose Lead & Zinc Mining Co.
1924 OK 466 (Supreme Court of Oklahoma, 1924)
Outcault Advertising Co. v. Waurika Nat. Bank
1924 OK 298 (Supreme Court of Oklahoma, 1924)
Virginia-California Gasoline Co. v. Jordan
1924 OK 230 (Supreme Court of Oklahoma, 1924)
Smart v. Bassler
1924 OK 155 (Supreme Court of Oklahoma, 1924)
Union Nat. Bank v. Lavacota Oil & Gas Co.
1923 OK 64 (Supreme Court of Oklahoma, 1923)
Sternwear Tire & Tube Co. v. Marion Tire & Rubber Co.
1923 OK 31 (Supreme Court of Oklahoma, 1923)
Delk v. City Nat. Bank of Duncan
1922 OK 97 (Supreme Court of Oklahoma, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
1921 OK 37, 195 P. 298, 80 Okla. 199, 1921 Okla. LEXIS 31, Counsel Stack Legal Research, https://law.counselstack.com/opinion/romans-v-shannon-okla-1921.