Roemheld v. City of Chicago

131 Ill. App. 76, 1907 Ill. App. LEXIS 9
CourtAppellate Court of Illinois
DecidedJanuary 7, 1907
DocketGen. No. 12,932
StatusPublished
Cited by1 cases

This text of 131 Ill. App. 76 (Roemheld v. City of Chicago) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roemheld v. City of Chicago, 131 Ill. App. 76, 1907 Ill. App. LEXIS 9 (Ill. Ct. App. 1907).

Opinion

Mr. Justice Adams

delivered the opinion of the court.

Counsel for the city says, in his argument: “There is no dispute whatever about the facts in this case,” which is true. Therefore, the question to be decided is one of law.

The sole contention of the city, by its counsel, is that the changes in -the construction of the bridges were made by the plaintiffs without any written order therefor by the commissioner of public works. In support of this contention, counsel relies on section 1609 of the city ordinance, which is as follows:

Section 1609. “No payment shall be made on any work or job done by contract, for any extra work not specified in the contract, unless such extra work shall have been done by the written order of the commissioner of public works, to be annexed' to such contract, directing the same, and stating that such work is not included in the contract; Provided, that any order given under this section shall state what the extras are, and that such extras are necessary for the proper completion of, or for the security of the work previously done, and the reasons therefor.”

The contract also provides for a written order, but this is not mentioned by counsel for the city.

In City of Elgin v. Joslyn, 36 Ill. App. 301, the suit was by Joslyn, a contractor, against the city, for extra work and material not included in his written contract with the city. The contract was for the construction of certain buildings connected with the water works of the city. There was a clause in the specifications for the work, providing: “No extra work will be paid for or allowed unless the same was done upon the written order of the engineer. * * * All claims for extra work must be made to the engineer in writing, before the payment of the next succeeding estimate, after the work shall have been performed, and, failing to do this, the contractor shall be considered to have abandoned his claim.” The suit was defended on the ground, among others, that the work claimed as extra was done without the written order of the engineer. In respect to this the court say: “The provisions of the clause are mutual. The proof is, in this case, that the engineer of the city and the city officers, the water commissioners, had charge and supervision of this work, and were constantly proposing and requiring changes and departures from the original plans, and that many of these changes were of a material and important character, involving more . expense than the original plans. One witness, at least, swears that the finished work could hardly be recognized by looking at the original plans. Under the provision in question, if the engineer and the city, which he represented, intended to enforce that provision against the contractor, and avail themselves of its benefits, then it was their duty also to obey it; and it was the duty of the engineer, or the commissioners, when they ordered extra work, to put it in writing themselves. By the strict letter of this clause, no extra work is allowed to be done, except it is ordered by the. engineer in writing. He is to make the order, and must put it in writing, and his omission to do his duty, and comply with the contract, cannot be invoked to aid the defendant; nor can the defendant omit to comply with its part of the requirements of that clause and, at the same time, insist on a strict compliance with it on the part of the appellee. The neglect of the defendant to keep its part of that clause must be held to be a waiver of the right to insist on the plaintiff keeping his part of it.” The judgment of the Appellate Court was affirmed by the Supreme Court. City of Elgin v. Joslyn, 136 Ill. 525.

The contract in this case expressly provides that all of the work contracted for shall be done “under the immediate direction and superintendence of the commissioner of public works of the city of Chicago, and to his entire satisfaction, approval and acceptance,” and that “all material used, and all labor performed shall be subject to the inspection and approval or rejection of said commissioner.” The presumption of law being, that, in the absence of evidence to the contrary, an officer has performed his duty, it must be presumed that the commissioner of public works superintended the construction of the bridges, as provided by the contract, and, therefore, must have known of the changes which were being made. He must also have accepted the bridges, including the changes, because otherwise the original contract prices would not have been paid, as he alone could issue vouchers or estimates for the work.

The contract also contains the following clause:

“Should the commissioner of public works deem it proper or necessary, in the execution of the work, to make any alterations which shall increase or diminish the expense, such alterations shall not vitiate or annul the contract or agreement hereby entered into, but the said commissioner shall determine the value of the work so added or omitted, such value to be added to or to be deducted from the contract price, as the case may be.”

This clause authorized the commissioner to order alterations which might increase the cost of the work.

In Cincinnati v. Cameron, 33 Ohio St. 336, Cameron, by his contract, agreed not to make any alterations or modifications in the 'work, or make any claim for such, unless ordered in writing so to do. This agreement was required to be included in all contracts made by the city, by an act of the legislature. The court held that the provision was intended for the benefit of the city and might be waived, and was waived by the city. Ib. 360 et sequens. In that case the board in charge of the work had adopted the practice of giving oral orders, deeming written ones unnecessary, and the court held this an abandonment of written orders. Ib. 372.

Wood v. Fort Wayne, 119 U. S. 319, was a suit by the plaintiffs, Wood et al., in part to recover for work and materials, extra to a contract between plaintiffs and the city of Fort Wayne, for the construction of water works in the city. The contract contained the following paragraphs:

“And it is hereby agreed that no claim for extra work shall be made of entertained, unless such extra work shall have been done in obedience to a written order of the engineer and trustees, and a stipulated price for same agreed upon, whenever such stipulation may be practicable. When otherwise, such claims to be made to the trustees in writing within ten days after the completion of such extra work, or before the payment of the next succeeding monthly estimate after such work is done, failing to do which all rights of the contractor to such extra pay shall be forfeited.
“The said trustees shall have the right to make any alterations in the extent, dimensions, form, or plan of the work contemplated by this contract, either before or after the commencement of construction. If such alterations diminish the quantity of work, the price paid shall be proportionately diminished, and no anticipated profits allowed for the work omitted. If they increase the work, such actual increase to be paid for at contract rate for work of its class.”

In respect to these paragraphs the court say:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cassidy v. Kirkpatrick
211 Ill. App. 196 (Appellate Court of Illinois, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
131 Ill. App. 76, 1907 Ill. App. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roemheld-v-city-of-chicago-illappct-1907.