Rodgers v. IBEC Housing Co.

12 V.I. 166, 20 Fed. R. Serv. 2d 1179, 1975 U.S. Dist. LEXIS 15996
CourtDistrict Court, Virgin Islands
DecidedSeptember 26, 1975
DocketCivil No. 1975-329
StatusPublished
Cited by9 cases

This text of 12 V.I. 166 (Rodgers v. IBEC Housing Co.) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rodgers v. IBEC Housing Co., 12 V.I. 166, 20 Fed. R. Serv. 2d 1179, 1975 U.S. Dist. LEXIS 15996 (vid 1975).

Opinion

YOUNG, District Judge

MEMORANDUM OPINION AND ORDER

The original complaint was filed in this matter on April 22, 1975. The plaintiff, Leonard Rodgers, now seeks leave of Court to amend his complaint. Defendant, IBEC Housing Company, V.I., Inc. (hereinafter “IBEC”), has brought a motion to dismiss the proceedings pursuant to Rule 12(b) of the Federal Rules of Civil Procedure, asserting that the statute of limitations has expired on plaintiff’s claim. The Government of the Virgin Islands, also defendants herein, have moved the Court to dismiss this action for lack of jurisdiction by the Court over the subject matter of the plaintiff’s claim.

I

FACTS

The plaintiff is the owner of a plot of land which is adjacent to and contiguous with the Sion Farm Housing Project. In the past the plaintiff had used this land for the grazing and raising of livestock. His complaint alleges the further intention to subdivide and sell his property.

The defendant, IBEC, was at all times relevant to this action the owner and/or developer of the tract of land which is now the Sion Farm Housing Project. The complaint alleges that while in the process of developing the site, IBEC paved the land which is now the Sion Farm [169]*169Housing Project so that waters cannot soak into the ground and failed to provide adequate drainage facilities, all to the plaintiff’s detriment. It is further alleged that IBEC altered the natural elevation of the land causing the surface waters which occur during rainy periods to flow and discharge on plaintiff’s land.

An engineer’s report on his investigation of the drainage situation of plaintiff’s land explains further that a drainage swale, a manmade waterway, was cut through the plaintiff’s property to “solve” the problems of an inadequate storm water disposal system at the Sion Farm development. This swale, the report concludes, along with a drainage path from a nearby laundry, contributes substantially to the runoff problems on plaintiff’s land.

The Government’s position as a defendant in this action results from its allegedly negligent approval and issuance of construction permits for the grading, filling and concreting of the Sion Farm project.

The plaintiff alleges that he has been damaged by the defendants’ actions because a swamp and marsh have developed on the property rendering it unfit for the raising of livestock, and that because of the formation of the swamp and marsh he cannot sell the property either.

II

PLAINTIFF’S MOTION TO AMEND THE COMPLAINT

I shall first consider the plaintiff’s motion to amend his complaint, since my resolution of this motion will have a bearing on the discussion of the defendants’ motions. The original complaint alleges essentially the facts stated above. As a basis for relief the complaint alleges that by pursuing the course of conduct which they did, the defendants acted with willful, wanton and gross negli[170]*170gence, such that the plaintiff has suffered and will continue to suffer serious damage.

The plaintiff now seeks the Court’s permission to amend the complaint, relying upon Rule 15 of the Federal Rules of Civil Procedure. The original complaint is retained as Count I of the amended complaint. Count II of the amended complaint realleges the same facts and states that the acts complained of constitute a nuisance which the defendants have neglected and refused to abate. The third count of the amended complaint alleges that the defendants’ conduct constitutes a continuing trespass on plaintiff’s land. In addition to the $500,000.00 of damages prayed for in the initial complaint, the plaintiff seeks a mandatory injunction compelling the defendants to abate the nuisance and to construct a proper drainage system, and an order restraining the defendants from the continuing trespass.

Rule 15 permits a party to amend his complaint once as a matter of course before a responsive pleading is served. The term “responsive pleading” should be interpreted by reference to Rule 7(a). 3 Moore’s Federal Practice ¶[15.07[2], at 851 (2d. ed. 1948). Thus, the Third Circuit has held in Kelly v. Delaware River Joint Commission, 187 F.2d 93 (1951), that a motion to dismiss the complaint is not a “responsive pleading” within the meaning of Rule 15. Under this interpretation the plaintiff would be entitled to amend his complaint once as a matter of right.

Even assuming that the plaintiff must seek the leave of Court to amend his complaint, Rule 15 provides that such leave “shall be freely given when justice so requires.” There is no indication that the plaintiff is acting in bad faith or for the purposes of delay in seeking to amend the complaint. Nor does the Court feel that the defendants will be unduly prejudiced by granting the motion to amend. Leave of court is frequently granted so that a plaintiff may [171]*171change the form or nature of the claim stated. See, e.g., Heay v. Phillips, 201 F.2d 220 (9th Cir. 1952).

I conclude, therefore, that whether as a matter of right or within the discretionary power of this Court, the plaintiff’s motion to amend the complaint should be granted.

Ill

IBEC’S MOTION TO DISMISS

Defendant IBEC now brings a motion to dismiss the complaint pursuant to Rule 12 (b) of the Federal Rules of Civil Procedure. IBEC argues that the plaintiff’s action is barred by the two-year statute of limitations found in 5 V.I.C. § 31(5). The defendant’s theory, simply stated, is that all construction was completed by mid-1970, and that five years had passed between the completion of the work and the bringing of the action. Moreover, the defendant notes that heavy rains occurred in the Virgin Islands in May 1969 and November 1970, asserting that the plaintiff should have known whether or not the development of the housing project would cause damage to his property.

The Court’s task in this regard is not made easier by the lack of specific dates in the various submissions of the parties. It appears from the affidavits that the grading, filling, concreting and paving of the Sion Farm Housing Project and any approval therefore occurred prior to July 1970. The difficulty arises with respect to when the plaintiff became aware or should have become aware of the damage to his land. The plaintiff was made aware that a drainage swale was cut through his property in the fall of 1971. The only reference to time in the complaint states:

“. . . that on several occasions during periods of heavy rains in the past year said waters have been discharged in such great quantity on plaintiff’s land that it was flooded to a depth of many inches for many days at a time.” (Keeping in mind that the complaint was filed on April 22,1975.)

[172]*172The only other indication with respect to time comes from the plaintiff’s response to the defendants’ motion to dismiss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Government of the Virgin Islands v. American Federation of Teachers, Local 1826
48 V.I. 30 (Superior Court of The Virgin Islands, 2006)
Hodge v. Bluebeard's Castle, Inc.
44 V.I. 242 (Supreme Court of The Virgin Islands, 2002)
In Re Tutu Wells Contamination Litigation
846 F. Supp. 1243 (Virgin Islands, 1993)
Harthman v. Texaco, Inc.
846 F. Supp. 1243 (Virgin Islands, 1993)
Van Putten v. Alexis
19 V.I. 265 (Virgin Islands, 1982)
Mercer v. Government of the Virgin Islands
18 V.I. 171 (Supreme Court of The Virgin Islands, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
12 V.I. 166, 20 Fed. R. Serv. 2d 1179, 1975 U.S. Dist. LEXIS 15996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rodgers-v-ibec-housing-co-vid-1975.