Roderick v. Bugge

584 F. Supp. 626, 1984 U.S. Dist. LEXIS 18045
CourtDistrict Court, D. Massachusetts
DecidedMarch 30, 1984
DocketCiv. A. 74-1969-N
StatusPublished
Cited by4 cases

This text of 584 F. Supp. 626 (Roderick v. Bugge) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roderick v. Bugge, 584 F. Supp. 626, 1984 U.S. Dist. LEXIS 18045 (D. Mass. 1984).

Opinion

MEMORANDUM AND ORDER

DAVID S. NELSON, District Judge.

Patrick Roderick, a longshoreman employed by the stevedoring company J.J. Orr & Sons, Inc. (Orr), was injured when a steel I-beam, which had been hoisted by crane from a ship and lowered onto wooden bolsters on shore, toppled onto his foot as he attempted to release the crane’s hook. Roderick brought suit under section 5(b) of the Longshoremen’s and Harbor Workers’ Compensation Act (LHWCA), 33 U.S.C. § 905(b), against the corporate shipowner *627 Iver Bugge (Bugge). The shipowner in turn cross-claimed against B.T. Equipment Co. (BT), an equipment rental company which had leased to Orr a crane with an operator to help unload the ship. The primary action between Roderick and Bugge was settled for $40,000 prior to trial. What remain at issue are Bugge’s alternative claims against BT for indemnity and contribution. In support of the indemnity claim Bugge argues that, notwithstanding its own arguably negligent conduct, BT’s breach of its implied warranty of workmanlike performance entitles the shipowner to full reimbursement for the $40,000 settlement plus all costs incurred in the primary action. Alternatively, it contends that BT’s negligence “substantially exceeded” any of its own and that BT should therefore shoulder the lion’s share of the damages. In a four-part response, BT argues that it is immune from liability since the crane operator was a “borrowed servant” of the stevedore Orr; that indemnity is foreclosed by the 1972 amendments to the LHWCA; that the crane operator was free of negligence; and that in any event the crane involved in the mishap was never identified as that belonging to BT. On the basis of the evidence adduced at a two-day trial, the court concludes that neither indemnity nor contribution is warranted.

Preliminary Findings of Fact

On the morning of April 27, 1974, the freighter M/V Saga Sword was berthed at the Municipal Pier in Providence, Rhode Island, loaded with a cargo of steel products. Bugge had earlier retained Orr, the stevedore, to conduct the unloading. While Orr owned several cranes which it planned to use on this job, it had determined that an additional crane would be necessary. Accordingly, Orr had leased a crane with operator from BT, a company in the business of leasing cranes and other heavy equipment. This crane was delivered and erected by BT personnel on April 24 and was used in discharging the Saga Sword on April 27. David Shannon, a Rhode Island licensed crane engineer and a BT employee, was at the controls.

Each of the several cranes involved in the unloading process serviced a different hatch, lifting bundles of steel from the ship’s hold and lowering them onto wooden bolsters on the pier from which they were then removed by forklift. Inside each hatch, a crew of four longshoremen moved the successive steel bundles into position and connected them to the crane’s hook by means of attached wire slings. The crews worked under the direction of an Orr supervisor, who in turn reported to the ship officer employed by Bugge. In maneuvering a crane inside a hatch — an area beyond his field of vision — each operator was guided by standard hand signals made by an Orr “signal man” perched on deck. Once a load was free of the hatch, the operator swung it over to the pier and lowered it to a designated spot within his field of vision, again with the guidance of hand signals received from one of two “landers” on the deck. The landers, also Orr employees, then disconnected the slings from the crane’s hook.

Plaintiff Roderick, together with Lewis Paiva, comprised one such team of landers during the unloading of the Saga Sword, with Paiva also serving as the dockside signal man. The morning hours were devoted to discharging steel rolls. Following lunch break, during which their crane was moved to another hatch, they commenced unloading steel I-beams which measured some twenty feet long, twelve inches wide and eight inches high. The I-beams were taken out individually during the first half-hour, without incident. Then Bugge’s ship officer, in an attempt to complete the job by five o’clock, directed the Orr employees to unload two I-beams at a time. On the very first such load, the two I-beams, each of which was connected to the crane’s hook by a pair of slings, became crisscrossed, with one resting'at least in part on top of the other. Despite this configuration, Paiva gave the signal to lower the load onto the pallets and release the tension on the slings. As Roderick reached over to disconnect the hook, the upper I-beam top *628 pled off and pinned his foot to the ground, causing his injuries. 1

The Borrowed Servant Defense

Since the early stages of this suit, BT has contended that its crane operator Shannon constituted a borrowed servant of Orr for the duration of the Saga Sword job, thereby rendering Orr rather than BT responsible under, respondeat superior for any negligence or breach of warranty on Shannon’s part. In the face of potént arguments on each side, the court rejects BT’s position. The two traditional tests governing this “extraordinarily troublesome” area, Wilson v. Nooter Corp., 475 F.2d 497, 500 (1st Cir.), cert. denied, 414 U.S. 865, 94 S.Ct. 116, 38 L.Ed.2d 85 (1973) —“whose is the work and whose is the power of control,” Standard Oil Co. v. Anderson, 212 U.S. 215, 225, 29 S.Ct. 252, 255, 53 L.Ed. 480 (1909) — yield inconclusive answers. Certainly in one sense Shannon was advancing the work of Orr by participating in the unloading of the Saga Sword; the use of cranes, which Orr often supplied itself, constituted an integral part of a job that had been specifically assigned to the stevedore and was within its normal province. At the same time, Shannon “was furthering his own employer’s sole business, which consists of renting, for profit, cranes and operators to construction contractors” and others. Ciejek v. Crane Service Co., 351 F.2d 788, 791 (D.C.Cir.1965); see also Poole v. Clagett, 196 F.2d 775 (D.C.Cir.1952) (crane and operator leased for profit “in regular course of appellee’s business”); Haw v. Liberty Mutual Ins. Co., 180 F.2d 18 (D.C.Cir.1950) (same as to lease of bulldozer with operator).

The issue of control similarly pulls in both directions. 2 On the one hand, BT continued to pay Shannon’s wages and withhold his taxes, and it retained the right both to fire him and to replace him on the job with another operator. The crane was of considerable value and complexity, raising the inference that BT expected Shannon to protect its interests whenever they conflicted with Orr’s.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boston Ship Repair, LLC v. Starr Indemnity & Liability Co.
997 F. Supp. 2d 118 (D. Massachusetts, 2014)
Hastings v. JEFCO Equipment Company, Inc.
2013 IL App (1st) 121568 (Appellate Court of Illinois, 2013)
Canty v. A. Bottacchi, S.A. de Navegacion
849 F. Supp. 1552 (S.D. Florida, 1994)
Krzywicki v. Tidewater Equipment Co., Inc.
600 F. Supp. 629 (D. Maryland, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
584 F. Supp. 626, 1984 U.S. Dist. LEXIS 18045, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roderick-v-bugge-mad-1984.