Rocky Mountain Tool & Machine Co. v. Tecon Corp.

371 F.2d 589
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 28, 1966
DocketNos. 8178-8180
StatusPublished
Cited by18 cases

This text of 371 F.2d 589 (Rocky Mountain Tool & Machine Co. v. Tecon Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rocky Mountain Tool & Machine Co. v. Tecon Corp., 371 F.2d 589 (10th Cir. 1966).

Opinion

DAVID T. LEWIS, Circuit Judge.

This action was brought under the Miller Act, 40 U.S.C. §§ 270a, 270b, by the United States for the use and benefit of Rocky Mountain Tool & Machine Co., Inc. (Rocky Mountain) against Tecon Corporation (Tecon) and involves a complex of claims resulting from the construction of a Bureau of Reclamation project designated as the “Blue Mesa Dam and Power Plant” and located near Gunnison, Colorado. Rocky Mountain’s first claim asserts a sum in excess of $346,000 to be recoverable from Tecon as the prime contractor on the project through Rocky Mountain’s second tier sub-contract with Dearborn Machinery Movers Company, Inc. (Dearborn), a first tier subcontractor of Tecon’s. Rocky Mountain also sought damages for materials furnished and labor performed under a second contract made directly with Tecon and further damages for the wrongful termination of that contract. Rocky Mountain’s total claims approximate $2,000,000. Tecon counterclaimed against Rocky Mountain and its surety, Hartford Accident & Indemnity Co. (Hartford), for breach of contract, claiming damages of $500,000. Hartford asserted an independent defense on its bond. Jurisdiction of the expanded claims, where the Miller Act is not applicable, is based upon diversity of citizenship, 28 U.S.C. § 1332.1

The case was tried to a jury and resulted in verdicts denying recovery to Rocky Mountain on the Miller Act claim and also on the claim for wrongful termination of Rocky Mountain’s direct contract with Tecon but awarding to Rocky Mountain damages in the sum of $47,-884 for labor and materials furnished to Tecon between December 1, 1962 and January 10,1963. The jury also returned verdicts granting Tecon damages of $225,000 against Rocky Mountain for breach of contract and against Hartford in the sum of $150,000. The trial court directed the entry of judgment on the verdicts including interest on the monetary award from the date of the filing of the claim by the party obtaining a verdict. After consideration of various post-trial motions, final amended judgment was entered which raised the judgment against Hartford from $150,000 to $177,116, the latter sum being equal to the net recovery found against Rocky Mountain, Hartford’s principal. Interest on the monetary awards was allowed only from and after the date of the verdicts. By way of appeal and cross appeal, the parties now assert error in every portion of the judgment that is adverse to their respective interests.

A consideration of the precise appellate issues seems to dictate a somewhat detailed narrative of the factual development of the parties’ controversy. In April 1962, the Bureau of Reclamation awarded to Tecon the prime contract for the construction of the Blue Mesa Dam. Tecon awarded a sub-contract to Dear-born covering the portion of the project that included construction and installation of a steel overflow pipe and pen-stock manifold which would carry water from the reservoir to the power plant at the base of the dam. Dearborn in turn, with Tecon’s approval, awarded a second tier sub-contract to Rocky Mountain for the fabrication and partial installation of the structures contemplated by the first tier sub-contract between Tecon and Dearborn. Rocky Mountain provided Dearborn a performance bond in the amount of $825,000, issued by Hartford as surety on the work to be performed under the Dearborn-Rocky Mountain subcontract.

In June 1962, Rocky Mountain submitted to Dearborn a schedule of pay estimates which was accepted by Dearborn and was satisfactory to Tecon as a contractually binding payment and progress schedule. Rocky Mountain later disputed the binding nature of the schedule, but there is evidence in the record to support the conclusion that Rocky Mountain [593]*593did in fact consider itself so bound for at least the period in which the second tier sub-contract with Dearborn was in effect.

In August 1962, after Rocky Mountain had expended considerable sums of money in preparation of a fabrication site, Dearborn became involved in bankruptcy proceedings in Detroit, Michigan. Being apprehensive of the effect that these proceedings might have upon Dear-born’s respective contractual obligations, Tecon and Rocky Mountain entered into an agreement whereby Rocky Mountain or its assignee would receive payments directly from Tecon for work performed under the Dearborn-Rocky Mountain subcontract. It was also agreed that in the event the trustee in bankruptcy should terminate the Tecon-Dearborn sub-contract Rocky Mountain would complete its work on the project under a direct subcontract with Tecon. The prospective Tecon-Rocky Mountain sub-contract provided :

“Sub-contractor [Rocky Mountain] shall perform its work in such manner as to meet the applicable portions of the attached payment and progress schedule.”

Attached was the Tecon-Dearborn payment and progress schedule that had been based partially upon the schedule of pay estimates submitted by Rocky Mountain to Dearborn. Also in the prospective sub-contract was a paragraph which provided :

“In the event the Sub-Contractor fails, neglects, or refuses to prosecute the work or any separable part thereof in accordance with the requirements, specifications and regulations provided under the said Prime Contract, or in the event the Sub-Contractor fails to maintain a progress schedule, which, in the opinion of the Contractor will assure completion of Sub-Contractor’s work, or any part thereof at its option, within the time required by said Contractor, then the Contractor may, by written notice to the Sub-Contractor, terminate his right to proceed with the work, or such part thereof as is not being performed as required. In such event, the Contractor shall have full power and authority, without process of law and without violating this agreement, to , take the prosecution of work out of the hands of the Sub-Contractor and complete it with its own forces, or contract with other parties for its completion, or use other measures as in the Contractor’s opinion are necessary for its completion, including the use of equipment, plant and other property of the Sub-Contractor on the work, as hereinafter provided. Should the expense incurred by the Contractor in taking over and completing the work be less than the sum that would have become payable under this agreement if said work had been completed by the Sub-Contractor, then the Sub-Contractor shall be entitled to the difference, and should such expense exceed the said sum, then the Sub-Contractor and Sub-Contractor’s surety shall be liable to the Contractor for the amount of such excess.”

Rocky Mountain continued its operations under the second tier sub-contract with Dearborn until the end of November 1962 when the trustee in bankruptcy terminated the first tier sub-contract between Dearborn and Tecon. During that period there were numerous communications between the parties concerning the quality and quantity of Rocky Mountain’s work. Rocky Mountain expressly recognized that its work was behind schedule but promised to use the winter months when no work was planned as a time for catching up.

On December 3, 1962, Tecon advised Rocky Mountain that by virtue of the trustee’s action the Tecon-Rocky Mountain sub-contract of August 1962 had come into effect subject to the condition that Rocky Mountain furnish a performance bond in the amount of $500,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ClearOne Communications, Inc. v. Biamp Systems
653 F.3d 1163 (Tenth Circuit, 2011)
Cashner v. Freedom Stores, Inc.
98 F.3d 572 (Tenth Circuit, 1996)
Stuckey v. Northern Propane Gas Co.
874 F.2d 1563 (Eleventh Circuit, 1989)
Bjurstrom v. Campbell
618 P.2d 533 (Court of Appeals of Washington, 1980)
Bowman v. Pamida, Inc.
261 N.W.2d 594 (Supreme Court of Minnesota, 1977)
Davis Cattle Co., Inc. v. Great Western Sugar Company
393 F. Supp. 1165 (D. Colorado, 1975)
Sorensen v. Robert N. Ewing, General Contractor
448 P.2d 110 (Court of Appeals of Arizona, 1968)
Kulm Credit Union v. Harter
157 N.W.2d 700 (North Dakota Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
371 F.2d 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rocky-mountain-tool-machine-co-v-tecon-corp-ca10-1966.