Laguna Royalty Company v. Clarence L. Marsh Et Ux.

350 F.2d 817
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 8, 1965
Docket21704_1
StatusPublished
Cited by44 cases

This text of 350 F.2d 817 (Laguna Royalty Company v. Clarence L. Marsh Et Ux.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laguna Royalty Company v. Clarence L. Marsh Et Ux., 350 F.2d 817 (5th Cir. 1965).

Opinion

JOHN R. BROWN,

Circuit Judge.

This appeal is by the working interest owners and holders of overriding royalties 1 of an oil and gas lease who lost 2 their lawsuit below against the landowner-lessor Marsh 3 who, as a matter of law, 4 unlawfully expelled the operator from the lease, and allegedly damaged their well beyond repair by having a bridge plug inserted above both producing sands. However, the jury by its “No” answer to interrogatory No. 1, in the light of the Court’s instruction, evidently believed either (a) that Rex Kelso, the operator of the well had by his own acts previously destroyed the well or (b) that the well was so depleted as to be no longer commercially productive regardless of who destroyed it. As to this judgment, a variety of errors are asserted. Also very much involved is the Trial Judge’s refusal to grant plaintiffs’ motion to vacate under F.R.Civ.P. 60(b) on the ground of newly discovered evidence. 5 We affirm on the main appeal and remand for further 60(b) proceedings.

Much of the history of the lease and the well is revealed by the facts found by the Texas State Court in an earlier proceeding between the same parties to determine the validity of the lease.

Landowner Marsh granted a lease on 340 acres in 1946. In 1948 a portion of it along with other acreage was unitized into the 320-acre “Marsh #1 unit” — the subject lease. Also in 1948, the “Marsh #1 well” was drilled and completed, and this well continued to produce gas, condensate and distillate in commercial quantities up to the time it was shut-in on April 1, 1961 on orders of the then operator, William A. Parker, a Bostonian who operated the well by mail and employing a local manager.

The well was then in need of repairs and reworking. Parker, on April 1,1961, for about $17,000 sold the well equipment in place to plaintiff Western Oil Corp. along with an option to buy the leases, which option was subsequently exercised on or about May 8, 1961. Western Oil thereby became the owner of the working interest and hence the operator of the well (and lease).

Not before the State Court apparently were the facts that Kelso was retained by Western to look over the well in anticipation either of salvaging the equipment or reworking and operating the well. The well was a dual completion gas well producing in what were known as the “A” sand at approximately 7170-80 feet and the “D” sand at approximately 7490-7500 feet. The A sand was a closed reservoir which produced by decreasing pressure, whereas the D sand was a field-wide blanket sand produced by water drive. The dual completion was accomplished by inserting tubing inside the casing. The A sand was tapped by perforating only the casing and allowing the gas to flow up the annulus (circular open space between the tubing and the casing). Then the D sand was produced by perforating both the casing and the *819 tubing. And with a “packer” set to seal ■off the annulus between the A and D sands, the D sand gas would flow up the tubing to the well head.

Production had declined to the point where Parker no longer considered it profitable to operate the well. Kelso then acting for Western Oil thought the well could be operated more cheaply— particularly since he could do much of the work himself, and also that a rework might restore the well to substantial productivity. Thus on about April 18, Kelso removed the packer separating the sands and also the tubing from the well to examine it. To prevent the higher pressure A sand gas from migrating down the casing and communicating with the D sand, which would destroy the A sand’s productivity, he filled the casing with a column of water. He apparently thought that salt water was used, but the Federal Court testimony of the well service people who did the work showed that actually fresh water from a canal was used. The well stood in this condition for about two months.

Shortly after this, Kelso acquired Western’s interest and became the operator. Former operator Parker had been plagued by unusually large overriding royalties, so that the working interest represented only 61% of production. Worse, some of these overrides had a conversion feature so that after a certain amount was paid, they would convert to working interest, thus further reducing Parker or his assigns’ interest to around 40%. Kelso, however, was successful in obtaining assignments of enough overrides to make further operation profitable in his opinion.

On May 30 Kelso was ready to begin reworking operations. Under the lease he had 60 days after cessation of production to redrill, or begin reworking. Otherwise, the lease would be forfeited unless he paid the appropriate shut-in royalty.

In the meantime, however, Marsh had decided to try to take over the well and operate it himself. Pursuant to this plan, he had entered a lease agreement with another company for the deeper sands ostensibly reserving to himself the A and D sands thereby avoiding an apparent slander of the Parker-Kelso lease title. The agreement also provided that he was to file suit to cancel the Parker-Kelso lease, which he subsequently did. The result, however, was adverse to Marsh since it culminated finally in the previously mentioned State Court judgment expressly declaring that Kelso’s lease was valid and subsisting. 6

While preparing to commence reworking operations on May 30, Kelso learned that a canal had been constructed be *820 tween the access road and the well site, and that the field had been watered so as to make the way impassable to heavy machinery. This was no act of God. A remarkable piece of self-help, it was the act of Marsh. But Kelso was tending his own fences for on May 31 he paid a shut-in royalty payment. On June 3 he received a letter from Marsh’s attorney asserting that the lease had terminated (June 1 apparently) and notifying him:

“ * * * that Mr. Marsh does and will consider you a trespasser in and upon his property * * * for all purposes excepting the removal of [certain salvage equipment], and that you will be held accountable for any and all damages resulting to the property of Mr. Marsh, including, the minerals underlying same by reason of any trespass * * .

On June 6 Kelso, reserving all rights and bowing only to this modern confrontation of force', replied that he was complying with the Marsh demand. He spelled out the details of his planned, but now frustrated, rework and the payment of the shut-in royalty. He sounded this note of caution:

“The rights of the overriding royalty owners should not be overlooked in this situation. If because of delay in recompletion of the well, they lose a certain amount of production therefrom, I do not wish to personally absorb any responsibility on account of this loss.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carla Frew v. Thomas Suehs
780 F.3d 320 (Fifth Circuit, 2015)
Albert Hill, III v. Tom Hunt
593 F. App'x 330 (Fifth Circuit, 2014)
Blau v. BILL HEARD CHEVROLET CORPORATION-ORLANDO
422 B.R. 293 (N.D. Alabama, 2009)
In Re Spears
352 B.R. 79 (N.D. Texas, 2006)
In re Linerboard Antitrust Litigation
223 F.R.D. 357 (E.D. Pennsylvania, 2004)
United States v. Enigwe
320 F. Supp. 2d 301 (E.D. Pennsylvania, 2004)
Ames v. Miller
184 F. Supp. 2d 566 (N.D. Texas, 2002)
In Re the Marriage of Thomas
825 P.2d 1163 (Court of Appeals of Kansas, 1992)
Hall v. Hall
587 So. 2d 1198 (Supreme Court of Alabama, 1991)
Shores v. Sklar
885 F.2d 760 (First Circuit, 1989)
Shores v. Sklar
885 F.2d 760 (Eleventh Circuit, 1989)
Pan Eastern Exploration Co. v. Hufo Oils
855 F.2d 1106 (Fifth Circuit, 1988)
Schauss v. Metals Depository Corp.
757 F.2d 649 (Fifth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
350 F.2d 817, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laguna-royalty-company-v-clarence-l-marsh-et-ux-ca5-1965.