Rochester Pure Waters District, a Municipal Authority of the State of New York v. Environmental Protection Agency

960 F.2d 180, 295 U.S. App. D.C. 121, 22 Envtl. L. Rep. (Envtl. Law Inst.) 21522, 34 ERC (BNA) 1851, 1992 U.S. App. LEXIS 5723
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 3, 1992
Docket90-5011, 90-5320
StatusPublished
Cited by28 cases

This text of 960 F.2d 180 (Rochester Pure Waters District, a Municipal Authority of the State of New York v. Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rochester Pure Waters District, a Municipal Authority of the State of New York v. Environmental Protection Agency, 960 F.2d 180, 295 U.S. App. D.C. 121, 22 Envtl. L. Rep. (Envtl. Law Inst.) 21522, 34 ERC (BNA) 1851, 1992 U.S. App. LEXIS 5723 (D.C. Cir. 1992).

Opinion

Opinion PER CURIAM.

PER CURIAM:

May a federal court order an executive agency to set aside funds from an appropriation that Congress has rescinded? In this case, the district court issued a temporary restraining order mandating that the Environmental Protection Agency retain approximately $4 million of the $47.7 million remaining in an appropriation for a grant program. Congress rescinded the entire $47.7 million after the court issued its order. Relying on case law dealing with the extension of lapsed budget authority, the court answered the question posed above in the affirmative by converting its temporary restraining order into a permanent injunction after the rescission. We are not persuaded by the analogy to a lapsed appropriation. A federal court cannot, consistent with the Constitution, overturn a rescission by Congress in order to preserve the positions of the parties in an ongoing dispute. To do so would allow the court to appropriate funds. That is the job of Congress. Therefore, we reverse.

I. Background

The Rochester Pure Waters District and the City of Rochester, New York (collectively “Rochester”), are embroiled in a long-standing dispute with the Environmental Protection Agency over funding for the construction of a sewage treatment plant. In 1968, the EPA awarded Rochester a $1,948,000 grant to help build a plant pursuant to section 8 of the Federal Water Pollution Control Act. That section established a program under which the Federal Government was authorized to provide up to thirty percent of the eligible costs of water pollution abatement projects. See 33 U.S.C. § 466e (1964), Pub.L. No. 89-753, § 203, 80 Stat. 1246, 1248-49 (1966). By June 1972, the EPA had increased Rochester’s grant to a total of $19,776,700, representing twenty-five percent of the total costs.

In October 1972, Congress enacted the Federal Water Pollution Control Act Amendments, which brought about significant changes in the law. In addition to creating the heart of the current federal water pollution programs, the Amendments greatly increased federal funding for quali *182 fied pollution abatement projects. The Amendments established a new program through which municipalities could recover up to seventy-five percent of construction costs. 33 U.S.C. § 1281 et seq. (1988). Congress also authorized additional reimbursements to section 8 grantees that had instituted approved projects between June 1966 and July 1973, up to a total of fifty-five percent of eligible construction costs. See id. § 1286(a) (“section 206(a)”). The Amendments required that applications for the upward adjustments be filed within a one-year window commencing on October 18, 1972. Applicants filing within this window were allowed to revise their claims “from time to time, as may be necessary.” Id. § 1286(c).

Congress appropriated $1.9 billion for the section 206(a) program in 1972. See Pub.L. No. 92-399, 86 Stat. 591 (1972). The next year, Congress extended the application deadline until January 31, 1974. See Pub.L. No. 93-207, 87 Stat. 906 (1973). In 1976 and 1977, a further $500 million was added to the section 206(a) appropriation.

Rochester filed a timely application for additional funds. The city and the district sought an increase to cover fifty-five percent of the project’s total cost of approximately $79 million, which the EPA granted. All together, the EPA provided Rochester with grants totalling $43,472,000.

Over ten years after the expiration of the filing deadline, Rochester applied to the EPA for an additional $3,986,884 to cover the costs of settling lawsuits with the project’s prime contractor and a subcontractor. The New York Department of Environmental Conservation, the EPA's delegated agent for the section 206(a) program, denied the request in December 1984, holding that an applicant could not receive more than the amount claimed prior to the statutory deadline of January 31, 1974. See Rochester Pure Waters Dist. v. EPA, 724 F.Supp. 1038, 1041 (D.D.C.1989) {“Rochester"). After this denial, Rochester diligently pursued its administrative remedies with the state agency and the EPA. In September 1989, Rochester also filed a Deviation Request with the EPA, pursuant to 40 C.F.R. Part 30, in which it sought a departure from the agency’s regulations. Id. at 1041-42.

In the meantime, while these administrative appeals were pending, Rochester became concerned that while it might win the administrative battles, the EPA might lose the funds with which to satisfy the additional claim. By 1989, only $47.7 million of the $2.4 billion appropriated for section 206(a) remained unobligated. In June 1989, the staff of the House Committee on Appropriations contacted the EPA and asked for data and comments regarding the possible rescission of the $47.7 million. The EPA replied shortly thereafter that it believed no one would be adversely affected by the proposed step. Id. at 1042. On July 20, 1989, the House of Representatives passed a bill appropriating funds for a variety of agencies, including the EPA, for fiscal year 1990. That legislation included the rescission of the full $47.7 million in section 206(a) funds. The committee report accompanying the bill stated that the EPA “indicate[d] that this rescission will cause no adverse impacts.” H.R.Rep. 101-150, 101st Cong., 1st Sess. 49 (1989).

In early September 1989, the EPA’s Acting Deputy Assistant Administrator of Water was informed of Rochester’s claim. See Quigley Affidavit If 7, reprinted in Joint Appendix (“J.A.”) at Tab 5. As a consequence, the agency advised the Senate Appropriations Committee staff on September 11 that “EPA had some difficulties with the proposed rescission because there was a pending administrative claim for section 206(a) funds.” Brozen Affidavit II 5, reprinted in J.A. at Tab 4. Senate committee staff members acknowledged that they were aware of the claim. Id. Nevertheless, the Senate subsequently passed its version of the fiscal year 1990 appropriations bill, which included the identical rescission proviso.

On October 13, 1989, Rochester filed this action in the district court to require the EPA to preserve and set aside the nearly $4 million needed to cover its claim and requested a temporary restraining order (“TRO”). The court granted the order the *183 same day and directed the agency to preserve the monies until November 15. Rochester, 724 F.Supp. at 1040. It appears that EPA staff immediately informed the House Appropriations Committee staff of the lawsuit and of the likelihood that a restraining order would be entered that day. Agency officials indicated that they had no objection to reducing the rescission by $4 million to cover the claim. On October 18, 1989, a conference committee reported a bill that included the full rescission. The Senate passed the legislation on October 27, and the House gave its assent four days later.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. McDonough
71 F.4th 909 (Federal Circuit, 2023)
United States v. Stone
District of Columbia, 2019
Atlas Brew Works, LLC v. Barr
391 F. Supp. 3d 6 (D.C. Circuit, 2019)
Atlas Brew Work, LLC v. Whitaker
District of Columbia, 2019
Sierra Club v. Trump
379 F. Supp. 3d 883 (N.D. California, 2019)
Nat'l Ass'n v. Bureau of the Census
382 F. Supp. 3d 349 (D. Maryland, 2019)
California v. Trump
267 F. Supp. 3d 1119 (N.D. California, 2017)
United States House of Representatives v. Burwell
130 F. Supp. 3d 53 (District of Columbia, 2015)
Figueroa v. United States
66 Fed. Cl. 139 (Federal Claims, 2005)
Nevada v. Department of Energy
400 F.3d 9 (D.C. Circuit, 2005)
St NV v. DOE
400 F.3d 9 (D.C. Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
960 F.2d 180, 295 U.S. App. D.C. 121, 22 Envtl. L. Rep. (Envtl. Law Inst.) 21522, 34 ERC (BNA) 1851, 1992 U.S. App. LEXIS 5723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rochester-pure-waters-district-a-municipal-authority-of-the-state-of-new-cadc-1992.