Robison v. Madsen

516 N.W.2d 594, 246 Neb. 22, 1994 Neb. LEXIS 129
CourtNebraska Supreme Court
DecidedMay 27, 1994
DocketS-92-948
StatusPublished
Cited by97 cases

This text of 516 N.W.2d 594 (Robison v. Madsen) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robison v. Madsen, 516 N.W.2d 594, 246 Neb. 22, 1994 Neb. LEXIS 129 (Neb. 1994).

Opinion

Per Curiam.

After Richard Robison, doing business as Robison Construction, presented evidence and rested in his residential construction lien foreclosure action, the trial court, on motion of the residence’s owners, dismissed Robison’s case because he had failed to prove the amount of his lien.

We affirm the dismissal by the district court for Lancaster County.

ASSIGNMENTS OF ERROR

Robison claims that the trial court erred in (1) sustaining the *24 owners’ motion to dismiss on grounds of insufficient evidence of the actual cost of constructing a residence for its owners and (2) overruling Robison’s motion for new trial.

STANDARD OF REVIEW

An action to foreclose a construction lien is one grounded in equity. Lange Indus. v. Hallam Grain Co., 244 Neb. 465, 507 N.W.2d 465 (1993). In an appeal of an equity action, an appellate court tries factual questions de novo on the record and reaches a conclusion independent of the findings of the trial court, provided, where credible evidence is in conflict on a material issue of fact, the appellate court considers and may give weight to the fact that the trial judge heard and observed the witnesses and accepted one version of the facts rather than another. Id.

When a defendant in an equity action moves to dismiss the plaintiff’s action at the close of the plaintiff’s evidence, the defendant, for the purposes of considering the defendant’s motion, admits the truth of the plaintiff’s evidence and testimony, together with every inference which may fairly and reasonably be drawn therefrom. The court must then determine, as a question of law, whether the plaintiff’s evidence has made a prima facie case. Schall v. Anderson’s Implement, 240 Neb. 658, 484 N.W.2d 86 (1992).

A district court’s denial of a motion for new trial will be affirmed when the court’s decision is neither erroneously prejudicial nor an abuse of discretion. See Goeke v. National Farms, Inc., 245 Neb. 262, 512 N.W.2d 626 (1994).

FACTS

On May 8, 1990, Roland Craig Madsen and Theresa Ann Madsen, by written contract, agreed to pay Robison the actual direct cost of the construction of a residence in the city of Lincoln’s subdivision of Williamsburg Village, plus 10 percent for overhead and profit. The contract set forth an estimated total cost of $191,966, but established the contract price as “the sum of actual direct construction cost plus ten percent for overhead and profit for the construction to be performed by Contractor [Robison].”

When the Madsens failed to pay the unpaid balance of what *25 Robison claimed was due him, Robison filed a construction lien and subsequently filed this action in the district court for Lancaster County.

The contract defined direct construction cost as “all costs to complete the Project in accordance with the plans and specifications.” Attached to the contract was an 11-page, detailed list of specifications, which both Robison and Roland Madsen signed. Also entered into evidence were copies of plans for the construction of the Madsens’ residence, which Robison testified were the plans referred to in the contract.

Robison began construction of the home in May 1990. As work progressed, Robison prepared and sent to the Madsens monthly statements showing his calculations of the construction costs incurred to the date of each statement. Robison testified that he based these calculations on invoices sent to him by subcontractors and the costs of labor performed by his own employees.

Robison testified that after the residence was substantially completed in late September 1990, he and Roland Madsen walked through the house and made a “punch list” of the items Madsen thought should be corrected. Robison testified that he corrected most of the items on that list in October.

Up to that time, the Madsens apparently had paid the monthly statements Robison sent them. Robison testified that in mid-October, Roland Madsen paid him $16,478 on the September bill but refused to pay the remaining balance. Robison testified that he then stopped working on the residence. He subsequently filed a construction lien against the property to secure the unpaid balance, which Robison claimed was $61,101.22 at that time. On March 5,1991, Robison filed a petition to foreclose the construction lien in the district court for Lancaster County.

In their answer, the Madsens admitted that they had entered into the contract dated May 8, 1990. They also asserted as affirmative defenses that they had been induced to enter into the contract by fraudulent misrepresentations and that Robison had failed to construct the house in a good and workmanlike manner.

At trial, Robison claimed that the Madsens owed him *26 $61,101.22, plus subsequent finance charges for a total of $71,756.21. At the close of Robison’s case, the district court granted the Madsens’ motion to dismiss Robison’s petition on grounds of insufficient evidence of the actual cost of constructing the Madsens’ residence. Robison then filed a motion for new trial, which the district court overruled. Robison appealed to the Nebraska Court of Appeals. Under our authority to regulate the caseloads of the appellate courts of this state, we removed the matter to this court.

ANALYSIS

To dispose of this appeal, we need only address Robison’s first assignment of error that the district court erred in dismissing Robison’s petition on the ground of insufficient evidence of the actual direct construction cost. In connection therewith, we must also address Robison’s claim that a statement contained in the Madsens’ answer was a judicial admission.

In their answer, the Madsens alleged for their first affirmative defense that Robison had quoted the Madsens various estimates of construction costs, that Robison had made material representations of fact that were false or made with reckless disregard for their truth or falsity, and that the Madsens had relied on these representations in entering into the contract. As part of this allegation, the Madsens also stated:

[T]he amount set forth in the April 30, 1990 estimate was in the amount of $186,798 and the contracted amount was in the amount of $191,966', and the variance between said sums arose because of the failure of the Plaintiff to include certain items in preparing said amount and the Defendants were aware of this variance and asserted [sic] to the variance by executing the contract.

(Emphasis supplied.)

Robison claimed, at the hearing on his motion for new trial and on appeal, that by making this assertion in their answer, the Madsens made a judicial admission that the contract established a minimum price of $191,966.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Estate of Adelung
306 Neb. 646 (Nebraska Supreme Court, 2020)
Goes v. Vogler
304 Neb. 848 (Nebraska Supreme Court, 2020)
Rosberg v. Rosberg
Nebraska Court of Appeals, 2019
Wisner v. Vandelay Invs., L.L.C.
300 Neb. 825 (Nebraska Supreme Court, 2018)
Wisner v. Vandelay Investments
300 Neb. 825 (Nebraska Supreme Court, 2018)
State v. Burke
Nebraska Court of Appeals, 2016
Linda N. v. William N.
289 Neb. 607 (Nebraska Supreme Court, 2014)
Cervantes v. Omaha Steel Castings Co.
831 N.W.2d 709 (Nebraska Court of Appeals, 2013)
Connelly v. City of Omaha
769 N.W.2d 394 (Nebraska Supreme Court, 2009)
Malchow v. Doyle
748 N.W.2d 28 (Nebraska Supreme Court, 2008)
City of Ashland v. Ashland Salvage, Inc.
711 N.W.2d 861 (Nebraska Supreme Court, 2006)
Gohl v. Gohl
700 N.W.2d 625 (Nebraska Court of Appeals, 2005)
Gernstein v. Allen
630 N.W.2d 672 (Nebraska Court of Appeals, 2001)
McLain v. Ortmeier
612 N.W.2d 217 (Nebraska Supreme Court, 2000)
Elstun v. Elstun
589 N.W.2d 334 (Nebraska Court of Appeals, 1999)
Hall v. Progress Pig, Inc.
575 N.W.2d 369 (Nebraska Supreme Court, 1998)
US West Communications, Inc. v. Taborski
572 N.W.2d 81 (Nebraska Supreme Court, 1998)
Jessen v. DeFord
536 N.W.2d 68 (Nebraska Court of Appeals, 1995)
Garrett v. Garrett
527 N.W.2d 213 (Nebraska Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
516 N.W.2d 594, 246 Neb. 22, 1994 Neb. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robison-v-madsen-neb-1994.