Robinson v. Wilson

173 P. 331, 102 Wash. 528, 1918 Wash. LEXIS 968
CourtWashington Supreme Court
DecidedJune 6, 1918
DocketNo. 14826
StatusPublished
Cited by4 cases

This text of 173 P. 331 (Robinson v. Wilson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robinson v. Wilson, 173 P. 331, 102 Wash. 528, 1918 Wash. LEXIS 968 (Wash. 1918).

Opinion

Chadwick, J.

On June 20, 1914, appellants and respondents Samuel A. Agnew and O. E. Wilson entered into a contract of lease whereby appellants leased to respondents certain property in the city of Centralia. A building was in course of construction thereon. The parts of the lease material to this inquiry are as follows:

“For the term of five (5) years the said term to commence upon lessors giving to lessees notice in writing of the completion of the building now under course of construction on said premises, the said building to be three stories high and in accordance with the plans and specifications, except as to the first floor which is to be subdivided in accordance with the wishes of lessees, and said building to be completed on or about October 1st, 1914, and the said five years ’ term to commence five days after the giving of such notice, at the monthly rent or sum of four hundred ($400) dollars per month for the first twelve months of said lease, and the sum of four hundred and twenty-five ($425) dollars per month for the succeeding forty-eight months of said term, the said rentals to be paid monthly in advance, the first month’s payment to be paid on the execution hereof, and the other monthly rentals to be paid monthly in advance as of the time as set for the commencing as this lease by the notice as aforementioned, during the full term hereof.”

The building was completed in November, 1914, and on the 9th day of that month defendants went into possession and paid their rent up to and including the 15th day of February, 1916. On February 24,1916, defendants notified plaintiffs that they would refuse thereafter to pay rent because of the neglect and refusal of appellants to put the building in a tenantable condition, in that they had failed to provide sufficient heating facilities, and that, as a result thereof, respondents [530]*530had been compelled to turn away guests; that, when the back rooms were properly heated, the front rooms were too cold for comfort, and when the front rooms were properly heated, the back rooms were uninhabitable because of the heat. A further delinquency was alleged in that appellants had failed to provide proper sample rooms. It seems that the sample rooms were in the basement and that water seeped through the walls and floor during the rainy seasons. In their notice of refusal to pay additional rent, respondents claimed damages for the expired term of $3,000, and for the future term of $12,000, and “you are therefore advised, as before stated in this letter, that the Wilson Hotel Company will no longer pay rent upon said premises until such conditions are eradicated, or satisfactory arrangement made for the settlement of these demands.” On the 13th day of March, appellant gave respondents notice to pay rent, and on the 16th brought this action to recover the rent due in March and April, or $850.

Respondents answered, admitting the lease, and alleged affirmatively that the building was built to be used as a hotel and that it had not been constructed according to plans and specifications, in that the heating plant had not as much radiation as called for and that the valves were improperly installed, and that the building was not constructed of the best materials, and that the workmanship was not of the “best manner” employed by skilled mechanics. They alleged that the rental value was not to exceed $200 per month, and prayed for the difference between that sum and the sum of $400 and $425 per month which had been paid under the lease, and for damages for the remainder of the term in a like sum.

They also prayed for damages in the sum of $500 on account of the careless and negligent manner in [531]*531which appellants had attempted to repair the building. This item was in no way sustained. Appellants replied, denying generally. The testimony going to the condition of the heating plant and its workings is in sharp conflict. That there was a seepage through the walls and floor of the basement and to some extent through the south wall was established.

The court found that the building had not been built according to the plans and specifications in the particulars mentioned; that respondents had suffered a damage to the extent of $100 per month; figured the reasonable rental value at $325 per month; allowed respondents $2,000 less $850, the unpaid rent, and entered a judgment for the difference, being $1,150 with costs.

"Without taking issue with the theory of the law entertained by the trial judge in the assessment of damages, and granting that the heating plant did not meet the requirements of the business and that water seeped into the basement and through the south walls, we are unable to follow him in his findings of fact.

The right of respondents to recover rests primarily in contract, and they are under a burden to show a breach of contract. The lease was executed long before the building was occupied and was drawn with reference to certain plans and specifications. If the plans were then inadequate, the infirmity would fall equally upon the contracting parties and there could.be no recovery. For it is known of all men that “plans and specifications ’ ’ do not insure habitable buildings. Some architects are artists, some have constructive genius, and some can draw “plans and specifications.”

Likewise, if the building was not completed according to the plans and specifications, it was a fact susceptible of proof, and of which the proof of the inadequacy of the heating plant and the seepage in the walls [532]*532would not be evidence—certainly not when standing alone and unsupported by any testimony which would tend in the slightest degree to prove that the plans and specifications had been departed from. The only testimony found in the record in which plans and specifications are mentioned is that of a witness who says:

“The basement could have been constructed water tight, and if the mixtures called for in the plans and specifications had been properly placed the basement would not have leaked. The same is true of the south wall of the building. If this had been properly constructed it would not leak . . . The walls of the basement are not of the best possible construction as called for in the plans and specifications.”

But he does not assume to say what the plans and specifications required.

Witnesses testified that the rental value of a building used for hotel purposes and heated as this one was and with seepage in the basement and through the south wall would be from $100 to $250 per month, but it is not shown that the hotel was not as adequately patronized as a hotel in a community the size of Centraba would have been patronized if conditions had been otherwise. It is true that one of the respondents testified that a number of traveling men had quit the hotel, but how many or for how long or whether it resulted in a money loss is not made clear. Many traveling men testified to their satisfaction with the hotel, two of them saying it was a favorite resort of traveling men, and one of them that it was often full to overflowing.

Both the contractor and the heating contractor testified that the building was built and the heat installed strictly in accord with the plans and specifications, and their testimony is not challenged. The building was accepted by the architect in charge, which is some evi[533]*533dence that it was completed in accordance with the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Publishers Building Co. v. Miller
172 P.2d 489 (Washington Supreme Court, 1946)
Tailored Ready Co. v. Fourth & Pike Street Corp.
35 P.2d 508 (Washington Supreme Court, 1934)
Arnold-Evans Company v. Hardung
232 P. 290 (Washington Supreme Court, 1925)
Robinson v. Wilson
176 P. 331 (Washington Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
173 P. 331, 102 Wash. 528, 1918 Wash. LEXIS 968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robinson-v-wilson-wash-1918.