Robinson v. Hagenkamp

53 N.W. 813, 52 Minn. 101, 1892 Minn. LEXIS 479
Supreme Court of Minnesota·Decided December 27, 1892·Published·Cited by 5 cases

Opinion

Dickinson, J.

The plaintiff entered into a contract with one Hagenkamp whereby the latter agreed to supply’all necessary material for, and to erect, a block of five buildings for her and upon her land, in accordance with a plan and specifications which constituted a part of the contract. The buildings were to be fully completed by the middle of November, 1890; and if not completed by that date the contractor agreed to pay to the plaintiff, as liquidated damages, the sum of $15 for each day that should elapse before completion. The plaintiff agreed to pay to the contractor the sum of $23,800, payments to be made at intervals of two weeks of such proportion of that sum as the work done and materials furnished should bear to the whole, less fifteen per cent, thereof to be withheld by the plaintiff until the contract should be fully performed. The amounts thus to be paid were to be determined by the estimates of Traphagen and Fitzpatrick, the supervising architects.

In accordance with a provision of this contract, Hagenkamp, the contractor, as principal, and these appellants (defendants) as his sureties, executed to the plaintiff their bond in the sum of $8,000, the condition of which was that Hagenkamp should faithfully perform the contract on his part, and save the plaintiff harmless from all claims of subcontractors, workmen, and material men for work or material employed in the erection of the buildings.

Hagenkamp entered upon the performance of the contract, but about the 1st of November he abandoned it, and absconded; the buildings being then only partially constructed. The plaintiff’s agent, one Mendenhall, then notified the appellants that plaintiff held them to responsibility as sureties, and called upon them to take action in the matter. Thereupon, they, on the 7th day of November, employed one Mueller to complete the buildings in accordance with the terms of the contract. He went on with the construction, but did not complete the buildings until about the 20th of April of the following year.

[105]*105In the course of the prosecution of the work by the original contractor, Hagenkamp, some extra work was done by direction of the owner, not provided for in the contract, and there were some departures from the specifications, by direction of the plaintiff. No notice of this was communicated by the plaintiff to the defendants, when they, being notified of Hagenkamp’s default, employed Mueller to complete the buildings. There was conflicting evidence as to whether they then knew that such changes had been made.

After Mueller undertook the work, and during its progress, there was other extra work done, and changes were made, by direction of the plaintiff.

During the progress of the work, both while Hagenkamp was carrying it on and also after it was undertaken by Mueller, lien claims arose for labor done and material furnished to them, respectively, and after the buildings were completed lien claims were filed against the property, amounting in all to more than $10,000.

The liens thus imposed while Mueller was carrying on the work amounted to $3,500. One of the lien claimants commenced an action against the plaintiff to enforce his lien; all other lien claimants being also made parties, pursuant to the lien law of 1889, ch. 200. The plaintiff notified these appellants of the pendency of such action, and called upon them to defend the same. Upon petition of some of such lien claimants, who claimed that these appellants were personally liable to them, they were made parties defendant. They interposed an answer joining issue upon the claims asserted to have arisen under Hagenkamp, as well as to those subsequently arising, and they participated in the trial as to such matters. Judgment wras rendered, charging the plaintiff’s estate with the aggregate amount of such liens, including the $3,500 above mentioned, for which the court found these appellants to be personally liable; but the rendering of a personal judgment against them was stayed pending a motion for a new trial. The premises were decreed to be sold to satisfy such liens.

This action was afterwards commenced to recover the amount of such liens, and also the liquidated damages specified in the original contract for the noncompletion of the buildings by the time there [106]*106designated. The plaintiff recovered a verdict for $8,0.31.91. The defendants appealed from an order refusing a new trial.

When, upon the default of Hagenkamp, the appellants, his sureties, took upon themselves the performance-of the contract, as they did do when they employed Mueller to complete the construction of the buildings, they assumed the relation of principal obligors, and not merely that of sureties, at least as respects the work thereafter done. Having been theretofore obligated merely as sureties for the performance of the work by Hagenkamp, they then, with the consent of the plaintiff, stepped into his place, and undertook to do the work themselves, employing Mueller as their agent, with whom (Mueller) the plaintiff sustained no contract relation. They evidently authorized Mueller to receive payment from the plaintiff as the work progressed in accordance with the original contract, and payments were so made. The result was the same as if the defendants had themselves received the money. They were directly responsible as for their own' neglect, and not merely as sureties, on account of liens imposed on the property for material purchased and labor employed by their agent, Mueller, in the prosecution of the work. They need not have undertaken the performance of the contract, but having done so, and having stepped into the place of the contractor, appropriating the benefits of the contract so far as to receive the contract price for doing the work, they were reciprocally bound, to themselves pay for material purchased by them and for labor employed in their undertaking; and if by their default the plaintiff’s property was charged therefor, they were directly responsible to her.

It is said that the defendants should not be held to liability under this assumption of the work of construction, because the previous changes in the performance of the contract had legally discharged them from tbeir obligation as sureties, and that the failure of the plaintiff to communicate such facts to them when they were called upon as sureties to take such action as Hagenkamp’s default rendered necessary constituted a fraud upon them.

It will be unnecessary to consider whether such changes had been made in, or rather such departures from, the contract, as might have avoided the contract of suretyship, although we will say in passing [107]*107that the doing of extra work,-for which the plaintiff would have been required to pay according to its reasonable worth in addition to the contract price, would not have had such an effect. Assuming that such changes had been made as might have discharged the defendants, they are in no position to avail themselves of that defense. By their own conduct they are precluded from doing so. They voluntarily sought to and did avail themselves of the benefits of the original contract by stepping into the shoes of their principal and receiving payment, not only for the work done by themselves, but, what is more to the point, by receiving payment for what had been done by Hagenkamp up to the time of his default. Up to that time fifteen per cent, of the proper proportion of the contract price for work done and material furnished had been withheld, pursuant to the contract; that percentage not being payable until the work should be completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Robinson v. Hagenkamp, 53 N.W. 813, 52 Minn. 101, 1892 Minn. LEXIS 479 (Mich. 1892).

53 N.W. 813 (Robinson v. Hagenkamp) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Howard v. Fisher
283 P. 1042 (Supreme Court of Colorado, 1929)
Martin v. Fee
226 N.W. 203 (Supreme Court of Minnesota, 1929)
Fort Dodge, Des Moines & Southern Railroad v. Burns
177 Iowa 51 (Supreme Court of Iowa, 1916)
Stephens v. Elver
77 N.W. 737 (Wisconsin Supreme Court, 1898)
McHenry v. Brown
68 N.W. 847 (Supreme Court of Minnesota, 1896)