Robey v. Parnell

CourtNew Mexico Court of Appeals
DecidedJanuary 10, 2017
Docket33,852
StatusPublished

This text of Robey v. Parnell (Robey v. Parnell) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robey v. Parnell, (N.M. Ct. App. 2017).

Opinion

1 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

2 Opinion Number: _______________

3 Filing Date: January 10, 2017

4 NO. 33,852

5 KENNETH M. ROBEY

6 Plaintiff-Appellee/Cross-Appellant,

7 v.

8 LLOYD G. PARNELL,

9 Defendant-Appellant/Cross-Appellee.

10 APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY 11 Denise Barela Shepherd, District Judge

12 Yntema Law Firm P.A. 13 Hessel E. Yntema, III 14 Albuquerque, NM

15 for Appellee/Cross Appellant

16 Lakins Law Firm, P.C. 17 Charles N. Lakins 18 Albuquerque, NM

19 for Appellant/Cross Appellee 1 OPINION

2 HANISEE, Judge.

3 {1} The district court entered a judgment in favor of Plaintiff, Kenneth M. Robey,

4 in his action for breach of contract against Defendant, Lloyd G. Parnell, after a bench

5 trial. Defendant appeals, raising six issues. Plaintiff cross-appeals the district court’s

6 dismissal of his claims for unfair and unconscionable trade practices. We reject the

7 arguments of both parties, except as to the district court’s award of consequential

8 damages to Plaintiff in the amount of $2,500. We reverse as to that amount of

9 damages only and affirm the judgment in all other respects.

10 BACKGROUND

11 {2} Plaintiff owns a farm in Lemitar, New Mexico. After nearly fifty years of use,

12 the irrigation well on Plaintiff’s property stopped producing water and he contacted

13 Defendant about designing and constructing a replacement well. Defendant provided

14 Plaintiff with two estimates: an initial written estimate and, after some discussion, a

15 final written estimate. The latter estimate indicated the well would be 120 feet deep,

16 and would include, among other things, an annular seal installed to protect the well

17 from biofouling1 and other contaminants. The replacement well was anticipated to

18 1 The term “biofouling” is defined as “the gradual accumulation of waterborne 19 organisms (as bacteria and protozoa) on the surfaces of engineering structures in 20 water that contributes to corrosion of the structures and to a decrease in the efficiency 1 cost $37,876.64. Prior to construction, Plaintiff asked Defendant for a written

2 contract, but Defendant told Plaintiff that “he didn’t do business that way,” and they

3 could proceed based on the estimate, their verbal agreement, and a handshake.

4 Plaintiff agreed. Plaintiff’s understanding of the agreement, as told to him by

5 Defendant, was that Defendant would construct a well that would be fully adequate

6 for Plaintiff’s irrigation purposes, that it would be capable of producing 2,500 to

7 3,000 gallons of water per minute, and that it would last at least as long as Plaintiff’s

8 prior well, approximately fifty years.

9 {3} In September 2007 Defendant completed work on the well. The final invoice

10 Defendant submitted to Plaintiff totaled $37,334.04. The invoice indicated the well

11 was not 120 but 115 feet deep, and included an added item—a concrete pad— but did

12 not include an annular seal. Defendant told Plaintiff that the shallower depth would

13 “not make any difference[,]” and that the concrete pad was required by the state and

14 would serve the function of an annular seal, which was unnecessary. The absence of

15 an annular seal was contrary to Defendant’s verbal representation regarding the well

16 Plaintiff understood would be constructed.

17 of moving parts.” Merriam–Webster Dictionary, http://www.merriam-webster.com 18 /dictionary/biofouling (last visited on Nov. 11, 2016).

2 1 {4} Plaintiff was initially satisfied with the well, but by March 2011, three-and-a-

2 half years after its completion, the well failed to produce anything but a surge of

3 sediment-filled water before it began sucking air. Plaintiff contacted Defendant about

4 the well’s failure and Defendant recommended the well be cleaned out. But in order

5 for the well to be cleaned out, the concrete pad first had to be removed. Plaintiff again

6 discussed the annular seal with Defendant, who told Plaintiff that an annular seal was

7 not required when Plaintiff’s well was constructed but that he could add one,

8 although it really was not necessary. Following the well’s clean-out, its performance

9 did not improve.

10 {5} After some further unproductive communications with Defendant, Plaintiff

11 filed suit in August 2011. At the bench trial, Plaintiff testified that instead of being

12 120 feet deep as described in the estimate, or 115 feet deep as described in the

13 invoice, the well was less than 105 feet deep. Additionally, Plaintiff testified that he

14 discovered that the concrete pad was not required by the state, and that it was his

15 belief that the pad was actually used to conceal the fact that an annular seal had not

16 been installed as promised. Plaintiff’s expert testified to numerous issues with the

17 well, including Defendant’s failure to install the annular seal described in the

18 estimate, a component Plaintiff’s expert explained was required by state regulation.

19 Plaintiff’s expert further testified that the well was not constructed to a workmanlike

3 1 standard, and ultimately concluded that the failure of the well was caused by a

2 number of factors, including Defendant’s negligent design and construction and

3 biofouling attributable to Defendant’s failure to install the annular seal or sanitize his

4 tools and materials. Defendant’s expert disputed the cause of the biofouling and the

5 failure of the well. In Defendant’s expert’s view, the biofouling of the well was

6 caused by naturally occurring bacteria, and could have been prevented through

7 routine maintenance, which was the responsibility of the well owner.

8 {6} After a three-day bench trial, the district court entered its findings of fact and

9 conclusions of law. Crediting Plaintiff’s testimony, the district court found that

10 Defendant told Plaintiff the new well would last at least as long as the old one, or for

11 about fifty years, and concluded that, as a matter of law, this statement amounted to

12 an express warranty. The district court further concluded, based on the Plaintiff’s

13 expert’s testimony, that Defendant failed to design and construct the well in a

14 workmanlike manner with the ordinary skill of those who undertake such work.

15 Additionally, based on the estimate provided by Defendant, Plaintiff’s testimony, and

16 Plaintiff’s expert’s testimony, the district court concluded Defendant failed to perform

17 all contracted-for obligations and breached his contract with the Plaintiff. The district

18 court also found that Defendant negligently made numerous false or misleading

19 material representations to Plaintiff regarding the well’s specifications and

4 1 capabilities and the state’s requirements for the well, and determined that Defendant

2 negligently represented, by omission, “reductions in quantity and changes in quality

3 of the materials provided,” as compared to what was originally specified in the

4 estimate.

5 {7} The district court entered judgment for Defendant on Plaintiff’s claims for

6 unfair and unconscionable trade practices, finding that Plaintiff failed to demonstrate

7 that Defendant knowingly made false or misleading statements and that Defendant’s

8 acts and practices constituted an unconscionable trade practice. The district court also

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lenscrafters, Inc. v. Kehoe
2012 NMSC 20 (New Mexico Supreme Court, 2012)
Bank of New York v. Romero
2011 NMCA 110 (New Mexico Court of Appeals, 2011)
Chan v. Montoya
2011 NMCA 072 (New Mexico Court of Appeals, 2011)
Stevenson v. Louis Dreyfus Corp.
811 P.2d 1308 (New Mexico Supreme Court, 1991)
H. T. Coker Construction Co. v. Whitfield Transportation, Inc.
518 P.2d 782 (New Mexico Court of Appeals, 1974)
G.E.W. Mechanical Contractors, Inc. v. Johnston Co.
858 P.2d 103 (New Mexico Court of Appeals, 1993)
Thompson v. H. B. Zachry Co.
410 P.2d 740 (New Mexico Supreme Court, 1966)
Gallegos v. State Board of Education
1997 NMCA 040 (New Mexico Court of Appeals, 1997)
Hood v. Fulkerson
699 P.2d 608 (New Mexico Supreme Court, 1985)
ITT Educational Services, Inc. v. Taxation & Revenue Department
1998 NMCA 078 (New Mexico Court of Appeals, 1998)
Lovington Cattle Feeders, Inc. v. Abbott Laboratories
642 P.2d 167 (New Mexico Supreme Court, 1982)
Key v. Chrysler Motors Corp.
918 P.2d 350 (New Mexico Supreme Court, 1996)
Torres v. Plastech Corp.
1997 NMSC 053 (New Mexico Supreme Court, 1997)
Scott v. Brown
416 P.2d 516 (New Mexico Supreme Court, 1966)
Western States Mechanical Contractors, Inc. v. Sandia Corp.
798 P.2d 1062 (New Mexico Court of Appeals, 1990)
FIRST NAT. BANK IN ALBUQUERQUE v. Sanchez
815 P.2d 613 (New Mexico Supreme Court, 1991)
Galvan v. Miller
445 P.2d 961 (New Mexico Supreme Court, 1968)
Woolwine v. Furr's, Inc.
745 P.2d 717 (New Mexico Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Robey v. Parnell, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robey-v-parnell-nmctapp-2017.