Roberts v. United States

531 F. Supp. 372, 1981 U.S. Dist. LEXIS 17164
CourtDistrict Court, D. Vermont
DecidedDecember 30, 1981
DocketCiv. A. 79-49
StatusPublished

This text of 531 F. Supp. 372 (Roberts v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roberts v. United States, 531 F. Supp. 372, 1981 U.S. Dist. LEXIS 17164 (D. Vt. 1981).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

HOLDEN, Chief Judge.

The plaintiff, Ronald Roberts, brought this action under the Federal Tort Claims Act (FTCA), 28 U.S.C. §§ 1346(b), 2674 (1976), seeking to recover for losses he suffered when a slate quarry which he owned, located in South Poultney, Vermont, was destroyed. Roberts alleges that on June 1, 1978 John Rouba, a federal mine inspector, negligently and unlawfully ordered Roberts to use explosives to remove an “overburden” of rock and clay from one of the quarry walls. According to Roberts, he followed Rouba’s orders, which included specific instructions about how and where to blast. The ensuing blast, conducted on June 7, 1978, destroyed the quarry. Rob *374 erts claims Rouba’s actions constituted tortious conduct for which Roberts may recover under the FTCA. The United States disputes both Roberts’ factual allegations and his legal basis for recovery. On September 14-16, 1981, the court held a trial without a jury on the issue of liability only. 1 The court’s findings and conclusions are entered following the final submission by the parties on December 15, 1981.

FINDINGS OF FACT

In 1975 Ronald Roberts purchased a slate quarry located in South Poultney, Vermont. Until its destruction in June, 1978, Roberts operated this quarry (the “South Poultney quarry”) and other quarries in Middle Gran-ville, New York. At the South Poultney quarry, Roberts also operated a mill which processed and finished the slate removed from his quarries. The quarries and mill produced slate tile and flagstone.

During the entire relevant period, Roberts’ South Poultney quarry was subject to the provisions of the Federal Mine Safety and Health Act of 1977, 30 U.S.C.A. § 801 et seq. (West Supp.1981), or its predecessor, the Federal Metal and Nonmetalic Safety Act. This brought the quarry within the regulatory jurisdiction of the Mine Safety and Health Administration (MSHA), or its predecessor, the Mining Enforcement and Safety Administration.

On May 30 and June 1,1978, federal mine inspector John Rouba conducted an inspection of Roberts’ South Poultney quarry and mill. Rouba spent May 30th inspecting the mill operation. On June 1st he inspected the quarry.

The South Poultney quarry was an open-pit quarry which measured 400 feet long from north to south and 150 feet wide from east to west. The eastern side of the quarry, referred to as the “east butt,” consisted of a vertical rock wall approximately 125 feet high. The western side, referred to as the “west slant,” consisted of a 30-40 foot wall which sloped downward toward the bottom of the quarry pit at a 60-70 degree angle. Apparently, the merchantable slate was removed from the west slant side of the quarry.

During his June 1st inspection of the quarry, Rouba noticed an “overburden” on the west slant. An overburden is a formation of rock, clay, and surface debris that hangs over the wall of the quarry. At the time of Rouba’s inspection, quarrying underneath the surface of the ground proceeded in a westerly direction. The quarry operation left undisturbed a “collar” of slate at the top of the west wall. Over the collar was clay soil. The collar would not collapse unless it became detached from the main body of slate stone that supported the collar. As the quarry operation advanced to the west the overburden became more dangerous and eventually would fracture from the main body of stone and collapse with the clay soil above it and slide into the pit. The overhang, created by the collar and the clay above it, constituted a highly dangerous condition that threatened the safety of men working below the collar in the quarry pit. When Rouba inspected the quarry he regarded the presence of the overhang of slate and clay to be a violation of federal mine safety regulations, which require that

Loose, unconsolidated material shall be stripped for a safe distance, but in no case less than 10 feet, from the top of pit or quarry walls, and the loose, unconsolidated material shall be sloped to the angle of repose.

30 C.F.R. § 56.3-2 (1981). Rouba apparently first observed this overburden while he was in the east side of the quarry pit.

Upon observing the overburden, Rouba went to the top of the east butt of the quarry, where he met with Roberts and informed him of the safety violation. The content of the ensuing conversation between Roberts and Rouba was sharply disputed at trial. Roberts claims that Rouba verbally ordered Roberts to remove the overburden by blasting it away with explosive charges. Roberts testified that he first *375 disagreed with Rouba about the existence of the overburden. Then Roberts stated he asked Rouba if he could use heavy equipment, such as bucketloaders or scrapers, to remove the condition, explaining to Rouba that such methods would take three to four weeks to complete. According to Roberts, Rouba said he could use a dragline method, but Roberts replied that this method would not work. Roberts also stated that Rouba knelt down and sketched directions for blasting on a piece of loose slate (Plaintiff’s Exhibit 7). 2 Roberts testified that Rouba informed him that the quarry would be closed if the overburden was not removed. Roberts further testified that he expressed concern to Rouba that a blast would “bring ... the whole meadow [into] the quarry pit.” On redirect examination Roberts testified that Rouba also suggested the use of a backhoe to remove the overburden, but Roberts replied that this would not work either, because the equipment would sink into the clay behind the quarry wall.

Rouba confirmed that he suggested the use of heavy equipment to remove the overburden, but Roberts said the equipment would sink. According to Rouba, Roberts suggested the use of explosives as a method of removing the overburden. Rouba maintained that he issued no orders to Roberts; he merely informed Roberts that he would close the quarry in the event, on reinspection, he found men working underneath the overburden. Rouba did not recall ever making any sketches on pieces of slate during this conversation. Rouba testified that he issued no written citation to Roberts for the alleged safety violation.

In summary, there was no conflict in the evidence that the slate collar and the clay soil it held constituted a danger to the workers in the pit. All were agreed that the peril had to be removed in the interest of safety. The discussion between Roberts and the mine inspector Rouba centered on how the removal could best be accomplished.

From these conflicting accounts of the conversation, the court finds that Rouba observed an overburden which he believed constituted a safety violation. Rouba informed Roberts that his quarry would be ordered closed until the overburden was removed if he found employees working in the pit. The two men discussed the alternative methods of removing the overburden, but Rouba did not expressly order Roberts to use explosives. Indeed, Rouba suggested at least two other methods for removing the overburden, which Roberts concluded would not work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
531 F. Supp. 372, 1981 U.S. Dist. LEXIS 17164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roberts-v-united-states-vtd-1981.