Roberts & Schaefer v. Hardaway Co.

152 F.3d 1283
CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 31, 1998
Docket97-2664
StatusPublished

This text of 152 F.3d 1283 (Roberts & Schaefer v. Hardaway Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roberts & Schaefer v. Hardaway Co., 152 F.3d 1283 (11th Cir. 1998).

Opinion

[PUBLISH]

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT

________________________ FILED U.S. COURT OF APPEALS No. 97-2664 ELEVENTH CIRCUIT ________________________ 08/31/98 D. C. Docket Nos. 95-590-CIV-T-17E THOMAS K. KAHN 95-623-CIV-T-25B CLERK

ROBERTS & SCHAEFER CO.,

Plaintiff-Counter-Defendant-Appellee, Cross-Appellant,

versus

HARDAWAY CO., a Georgia corporation,

Defendant-Counter-Claimant, Appellant-Cross-Appellee.

HARDAWAY CO., a foreign corporation,

Plaintiff-Appellant, Cross-Appellee,

ROBERTS & SCHAEFER COMPANY, a foreign corporation,

Defendant-Appellee, Cross-Appellant.

________________________

Appeals from the United States District Court for the Middle District of Florida _________________________ (August 31, 1998) Before DUBINA and MARCUS, Circuit Judges, and CLARK, Senior Circuit Judge.

MARCUS, Circuit Judge:

This diversity case arises out of three contracts between Roberts & Schaefer Company

(“R & S”), a general contractor, and The Hardaway Company (“Hardaway”), a

subcontractor, concerning construction of a phosphate beneficiation plant for Mobil Mining

& Minerals Co. (“Mobil”). Following a jury trial before the magistrate judge, the court

entered judgment for Hardaway on two of the contracts, and judgment for R & S on the third.

On appeal, Hardaway contends that the magistrate judge erred in permitting R & S to take

advantage of the unilateral mistake doctrine with respect to one of the contracts and further

asserts that the trial court incorrectly applied the doctrine in this case. R & S, meanwhile,

cross-appeals and challenges the damages awarded to Hardaway on one of the other

contracts. We find that the magistrate judge acted within his discretion when he applied the

unilateral mistake doctrine in this case. We also conclude that the damages award to

Hardaway is not in error. Accordingly, we affirm the judgment.

I.

A.

A detailed review of the facts is necessary to understand our holding. Mobil engaged

R & S to design and build a phosphate beneficiation plant for an initial lump sum of

approximately $44,300,000. In accordance with Mobil’s arrangement with R & S,

construction was to proceed on a “fast track.” In the construction business, this means that

construction commences under a schedule of simultaneous design, building, and

-2- construction. In other words, in this case, R & S was to begin construction before it

completed the design and finalized a set of fully coordinated plans.

Consistent with fast-track construction, prior to finishing the design of the plant, R &

S awarded three subcontracts to Hardaway. Specifically, and in the order of award, R & S

and Hardaway entered into subcontracts for (1) structural steel/mechanical erection (“703

Contract”), (2) underground piping (“707 Contract”), and (3) above-ground piping (“712

Contract”). Although only the 712 and 703 Contracts are at issue on appeal, we review

formation of all three contracts to establish the parties’ pattern of doing business.

Each of the three Contracts awarded contained engineering plans and specifications

comprising hundreds of pages. The substance of the agreement between the parties,

however, was contained within the Construction Agreement, which was nearly identical in

all three Contracts. Among other relevant provisions, the Construction Agreements provided

as follows:

ARTICLE II: PERFORMANCE OF THE WORK BY CONTRACTOR

***

2.3 Contractor shall employ sufficient labor and supervision to work as many shifts per week as necessary to complete the various components of the work by the interim completion dates specified in the agreed upon Schedule. . . .

ARTICLE V: WORK SCHEDULE

-3- 5.1 Contractor shall submit to Company a proposed Work Schedule for the Work set out in a form in conformance with the Specifications.

5.2 After review and approval of the proposed Work Schedule by Company, the Schedule shall be binding on both parties, and shall be changed only in conformance with the provisions of this Agreement.

5.3 It is further agreed that time is of the essence of each and every portion of this Agreement and of the Specifications wherein a definite and certain length of time is fixed for the performance of any act whatsoever; and, where an additional time is allowed for the completion of any Work, the new time limit fixed by such extension shall be of the essence of this Agreement. If Contractor fails to meet any deadline set forth in the Contract Documents, Contractor shall be liable to Company for any excess costs incurred which are attributed to Contractor’s failure.

ARTICLE VII: CHANGES, DELETIONS AND EXTRA WORK

7.1 Company may, at any time, make additions, deletions, or changes in the Work of either a major or a minor nature. All such modifications shall be authorized by written change orders.

7.9 If any dispute shall arise under this Agreement, Contractor shall continue to execute the work pending determination thereof unless requested by the Construction Manager or Company to suspend or terminate the Work or any portion thereof.

ARTICLE XII: TERMINATION ON CONTRACTOR’S DEFAULT

-4- 12.1 Company may, without limitation or exclusion of any other remedy, terminate Contractor’s right to perform the Work, if:

(a) Contractor shall fail to:

a. Make such progress with the Work as reasonably to conform with the Approved Work Schedule, or

(vii) Perform any other material obligation required by this Agreement,

12.5 If the Company terminates Contractor’s right to perform the Work asserting one of the grounds set out in Paragraph 12.1 and those grounds are subsequently determined to be inapplicable, Company’s action shall then be deemed to be a termination pursuant to Article XIII.

ARTICLE XIII – TERMINATION FOR COMPANY’S CONVENIENCE

13.1 Company may terminate this Agreement for its convenience on giving written notice to Contractor. Contractor shall stop all Work on the date specified in the notice, and Company shall pay Contractor for:

(a) All Work satisfactorily performed to date of termination, and

(b) All actual and reasonable costs incurred by Contractor as a consequence of the termination.

Company shall [] not be liable to pay any bonus, damage or other claim asserted by Contractor for its expected profit on the uncompleted portion of the Work.

1. The 703 Contract

-5- When R & S invited Hardaway to bid on the 703 Contract, Hardaway responded with

a written, signed bid and a form showing exceptions or clarifications to the bid drawings and

specifications. A post-bid/pre-award meeting occurred between R & S and Hardaway. On

March 9, 1994, R & S awarded the 703 Contract to Hardaway by signed letter accepting a

bid of $2,497,000, and stating that a formal contract would be signed later. Hardaway began

work on March 9. On April 6, 1994, it submitted a pay application seeking $152,550. The

parties signed a formal contract the same day, with an “effective” date of March 8, 1994,

corresponding to the date of oral notification of the award.

The 703 Contract was bid and accepted on a lump-sum basis. For a lump sum,

Hardaway was to employ all sufficient labor and supervision to work as many shifts as

necessary to complete the work by the interim completion dates. Hardaway agreed to submit

a critical path method (“CPM”) schedule. A CPM is a standard construction device used to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eskra v. Provident Life & Accident Insurance
125 F.3d 1406 (Eleventh Circuit, 1997)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
Schloesser v. Dill
383 So. 2d 1129 (District Court of Appeal of Florida, 1980)
McDevitt & Street Co. v. Dept. of Gen. Serv.
377 So. 2d 191 (District Court of Appeal of Florida, 1979)
State Board of Control v. Clutter Construction Corporation
139 So. 2d 153 (District Court of Appeal of Florida, 1962)
American Recycling Co., Inc. v. County of Manatee
963 F. Supp. 1572 (M.D. Florida, 1997)
Alberts v. Federal Home Loan Mortg. Corp.
673 So. 2d 158 (District Court of Appeal of Florida, 1996)
Florida Cranes, Inc. v. FLA. E. COAST PROP., INC.
324 So. 2d 721 (District Court of Appeal of Florida, 1976)
PA. NAT. MUT. CAS. INS. CO. v. Anderson
445 So. 2d 612 (District Court of Appeal of Florida, 1984)
Graham v. Clyde
61 So. 2d 656 (Supreme Court of Florida, 1952)
Langbein v. Comerford
215 So. 2d 630 (District Court of Appeal of Florida, 1968)
Williams v. Harbour Club Villas Condo. Ass'n
436 So. 2d 233 (District Court of Appeal of Florida, 1983)
Maryland Casualty Company v. Krasnek
174 So. 2d 541 (Supreme Court of Florida, 1965)
Bethlehem Steel Corp. v. Centex Homes Corp.
327 So. 2d 837 (District Court of Appeal of Florida, 1976)
Hyman v. Cohen
73 So. 2d 393 (Supreme Court of Florida, 1954)
Langley v. Irons Land & Development Co.
114 So. 769 (Supreme Court of Florida, 1927)
Block v. Drucker
212 So. 2d 890 (District Court of Appeal of Florida, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
152 F.3d 1283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roberts-schaefer-v-hardaway-co-ca11-1998.