Robert J. Barnabei Contracting, LLC v. Greater Hartford Jewish Community Center, Inc.

14 A.3d 461, 127 Conn. App. 507, 2011 Conn. App. LEXIS 144
CourtConnecticut Appellate Court
DecidedMarch 29, 2011
DocketAC 31679
StatusPublished
Cited by7 cases

This text of 14 A.3d 461 (Robert J. Barnabei Contracting, LLC v. Greater Hartford Jewish Community Center, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robert J. Barnabei Contracting, LLC v. Greater Hartford Jewish Community Center, Inc., 14 A.3d 461, 127 Conn. App. 507, 2011 Conn. App. LEXIS 144 (Colo. Ct. App. 2011).

Opinions

Opinion

GRUENDEL, J.

The plaintiff, Robert J. Bamabei Contracting, LLC, appeals from the judgment of the trial court rendered in accordance with a report filed by an attorney fact finder (fact finder). The court rendered judgment awarding the plaintiff $292 in compensatory damages pursuant to a subcontract agreement (agreement) with the defendant Aspinet Constmction Company.1 On appeal, the plaintiff claims that the court improperly overmled its objection to acceptance of the fact finder’s report because the report lacks factual justification and is otherwise incomplete. The plaintiff further claims, for the first time on appeal, that the defendant failed to comply with § 7 (f) of the agreement. We affirm the judgment of the trial court.

The following facts and procedural history are relevant to the resolution of this appeal. In early 2004, the Greater Hartford Jewish Community Center, Inc. (community center), retained the defendant as the general contractor for a renovation project (project) at the community center’s West Hartford location. On March 19, 2004, the plaintiff and the defendant executed the agreement, whereby the plaintiff was to perform subsurface constmction services for the project for a total price of $37,960. The dispositive provisions of the agreement are as follows:

[510]*510“Section 4. ... If at any time there shall be evidence of any hen or claim for which, if established, [the defendant] or the [community center] might be or become hable and which is chargeable to [the plaintiff], [the defendant] shah have the right to retain out of any payment due or to become due by [the defendant] to [the plaintiff] an amount sufficient to indemnify [the defendant] and [the community center] against such hen or claim ....
* * *
“Section 7. The following conditions are hereby made a part of this [agreement . . .
“(d) The [plaintiff] agrees ... to comply with ah [fjederal, [s]tate, [m]unicipal and local laws, ordinances, codes and regulations governing and to pay ah costs and expenses required thereby ....
* H= *
“Section 8. (a) [The plaintiff] shah submit in writing to [the defendant] ah claims for adjustment in the [agreement] price ... for like claims by [the defendant] against [the community center — namely, through a written change order]. . . . [The defendant’s] liability to [the plaintiff] for such claims is limited to any adjustment which shah be made by [the community center] to [the defendant’s] contract on account of [the plaintiffs] claim.”

On the same day that the parties executed the agreement, the defendant approached a third party, George Toreho Engineers, P.C. (Toreho), to perform engineering services in connection with the project, as such services were beyond the plaintiffs expertise. The defendant retained Toreho to ensure that the plaintiffs work complied with apphcable specifications of the West Hartford building code (building code), including, specifically, § 1816.13. After the plaintiff commenced [511]*511work on the project, the defendant submitted a written change order on May 17, 2004, by which the agreement price was increased from $37,960 to $41,275. On June 11, 2004, the plaintiff submitted an invoice to the defendant in the amount of $51,200, although it is undisputed that the plaintiff failed to submit a written change order pursuant to § 8 (a) of the agreement. Despite the plaintiffs noncompliance with § 8 (a), the defendant submitted the plaintiffs invoice to the community center for approval, which the community center eventually declined to pay due to the lack of supporting documentation. On August 3, 2004, the defendant submitted a second written change order backcharging the agreement price by $16,435.50, the cost of Torello’s services on the project, pursuant to § 7 (d), thereby reducing the plaintiffs total compensation to $24,839.50. The defendant then refused to pay the plaintiff $9925, the difference between the agreement price of $41,275 and the plaintiffs invoice of $51,200, claiming that it was not liable for this amount pursuant to § 8 (a) of the agreement. Additionally, the defendant maintained that the plaintiff was responsible for the expenses associated with Torello’s work pursuant to § 7 (d) of the agreement, as those services were required by the building code.

On July 11, 2005, the plaintiff commenced this action claiming, inter alia, breach of contract by the defendant. In support of its claim, the plaintiff alleged that the defendant was responsible for the full invoice amount of $51,200 and further that the defendant incorrectly backcharged the agreement price by the cost of Tor-ello’s services. In response, the defendant countered that the plaintiff was not entitled to the invoice amount of $51,200 because the community center never approved this adjustment to the agreement price. The defendant also argued that because the plaintiff already had been paid $24,547.50, and because the agreement [512]*512price of $41,275 was properly reduced by $16,435.50, the cost of Torello’s services, the plaintiff was entitled only to $292. The matter was tried before the fact finder on June 18, 2007, and a report was submitted by the fact finder on November 13, 2007. In his report, the fact finder specifically found that the defendant was not contractually hable for the invoice amount of $51,200, as the community center had not approved this upward adjustment in the agreement price as required by § 8 (a). As to the plaintiffs claim regarding the back-charge for Torello’s services, the fact finder found that “[§] 7 (d) of the [agreement] makes [the] plaintiff hable for the costs of code compliance . . . .” Thus, the fact finder recommended that the plaintiff be awarded $292, or the amount of the agreement price ($41,275), less the cost of Torello’s services ($16,435.50) and the amount that the plaintiff had already been paid by the defendant ($24,547.50). Subsequently, the plaintiff filed an objection to acceptance of the fact finder’s report and recommendations, arguing that the report was “incomplete and omits facts essential to a just disposition of this matter.” On October 19, 2009, the court overruled the plaintiffs objection and rendered judgment in accordance with the fact finder’s report. This appeal fohowed.

The plaintiff claims that the court improperly overruled its objection to acceptance of the fact finder’s report and recommendations. Specifically, the plaintiff argues that the fact finder incorrectly concluded that the $51,200 invoice amount in effect constituted a claim for $9925 in extra compensation, rather than a legitimate adjustment to the agreement price of $41,275.2 Additionally, the plaintiff claims that the fact finder [513]*513incorrectly found that the cost of Torello’s services was appropriately backcharged under the agreement.

Before addressing the merits of the plaintiffs claims, we begin with the applicable legal principles and standard of review governing our analysis. “A reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court ... or the Superior Court reviewing the findings of . . . attorney trial fact finders. . . . This court has articulated that attorney trial fact finders and [fact finders] share the same function . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guzman v. Yeroz
143 A.3d 661 (Connecticut Appellate Court, 2016)
CHFA–Small Properties, Inc. v. Elazazy
Connecticut Appellate Court, 2015
Ray Weiner, LLC v. Bridgeport
Connecticut Appellate Court, 2014
Tomick v. United Parcel Service, Inc.
43 A.3d 722 (Connecticut Appellate Court, 2012)
Cadle Co. v. D'ADDARIO
26 A.3d 682 (Connecticut Appellate Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
14 A.3d 461, 127 Conn. App. 507, 2011 Conn. App. LEXIS 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-j-barnabei-contracting-llc-v-greater-hartford-jewish-community-connappct-2011.