ROBERT E. HARDY, II v. BERNARD H. BRONNER

CourtCourt of Appeals of Georgia
DecidedMay 18, 2026
DocketA26A0680
StatusPublished

This text of ROBERT E. HARDY, II v. BERNARD H. BRONNER (ROBERT E. HARDY, II v. BERNARD H. BRONNER) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ROBERT E. HARDY, II v. BERNARD H. BRONNER, (Ga. Ct. App. 2026).

Opinion

FOURTH DIVISION MCFADDEN, P. J., WATKINS and PADGETT, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.gov/rules

May 18, 2026

In the Court of Appeals of Georgia

A26A0679, A26A0680. BRONNER et al. v. HARDY et al.; and vice versa.

WATKINS, Judge.

This appeal concerns a dispute between business partners Robert Hardy and

William Packer on the one hand (collectively, the “defendants,”) and Bernard Bronner

on the other. All three are shareholders in Rainforest Production Holdings, Inc. For the

reasons discussed below, we conclude that neither Bronner, in his appeal from the final

judgment and subsequent denial of his motion for judgment notwithstanding the

verdict, nor the defendants, in their cross-appeal from a pretrial order denying their

motion to enforce a settlement agreement, have established that the trial court

committed reversible error. Consequently, we affirm. Viewed in the light most favorable to the verdict,1 the record shows that

Rainforest, a film production company, was founded in 1996 by Hardy and Packer.

Bronner became involved several years later when he invested in the company. Over

time, disputes arose regarding repayment of Bronner’s and other investors’ funds. In

2010, the parties executed a “Reconciliation Agreement” to address those concerns.

Rainforest was dissolved four years later, in 2014, at which point Bronner owned 30.8

percent of the company’s shares, Hardy owned 32.1 percent, Packer owned 31.5

percent, and 14 others owned the remaining shares. Bronner later filed suit against

Hardy, Packer, and, nominally, Rainforest itself, raising direct and derivative claims

as a shareholder of the company.

One of Bronner’s claims was a shareholder derivative claim for breach of

contract based on Section 2.3 of the Reconciliation Agreement, which described how

Rainforest would be compensated when Hardy and Packer worked on projects for

outside entities.2 As relevant to this appeal, Bronner alleged that Packer’s work on

1 See Fassnacht v. Moler, 358 Ga. App. 463 (855 SE2d 692) (2021). 2 Section 2.3 provides: Compensation for Single Contractor Core Business Projects. With respect to any Core Business Project with a third party for which (1) the personal services of only one of Hardy or Packer are contracted on an 2 three movies — Think Like a Man, Ride Along, and About Last Night — fit within the

individual basis (as opposed to the services of Rainforest Films or another Rainforest Productions operating entity per se) for the project (such contracted individual referred to herein as the “Contractor”), (2) the other individual is not so contracted or is engaged and paid on a separate basis for personal services that are not part of the Core Business of Rainforest Productions, and (3) the name or assets of Rainforest Films or another Rainforest Productions operating entity are nonetheless to be used in the project (each such project, a “Single Contractor Project”), any compensation in connection with such Single Contractor Project shall be allocated and paid in the following manner: (a) Any compensation that is a “front-end payment” with respect to such project, regardless of the time the payment is actually delivered, shall be allocated such that fifty percent (50%) is paid directly to Rainforest Films, and fifty percent (50%) is paid directly to the Contractor or his personal holding company or other designee; and (b) Any compensation that is a “back-end payment” with respect to such project, regardless of the time such payment is actually delivered, shall be allocated such that ninety percent (90%) is paid directly to Rainforest Films, and ten percent (10%) is paid directly to the Contractor or his personal holding company or other designee. (c) If any compensation is paid or delivered as an initial matter in a manner that is inconsistent with the requirements of this Section 2.3, the recipient of such initial payment shall promptly (and in any event, within fourteen (14) days following its receipt of such payment) cause the appropriate amount thereof to be delivered to the ultimate recipient as specified in this Section 2.3. (Emphasis added).

In the “Recitals” section of the Agreement, Rainforest’s “Core Business” was described as “its feature film, television and other motion picture business activities[,]” while its “Core Business Projects” were described as including “all projects that are part of its Core Business[.]” 3 scope of Section 2.3 and that Packer failed to give Rainforest its share of payment for

those projects.

Both Bronner and Packer moved for summary judgment on the Section 2.3

claim, but the trial court concluded that genuine disputes of material fact prevented it

from granting either motion. Specifically, the trial court found that a jury had to

determine whether Rainforest’s name or assets were used in the projects such that

they came within the scope of Section 2.3.3

At trial, Packer defended against Bronner’s claim as to Think Like a Man by

presenting evidence that all proceeds for that project were paid to Rainforest. Packer

defended against Bronner’s claim as to Ride Along and About Last Night by arguing that

those projects did not fall within the scope of Section 2.3. In this vein, Packer testified

that none of Rainforest’s assets were used to make these films and that Rainforest’s

name was listed in these movies’ credits merely as a gratuitous “vanity credit.” He

3 The trial court observed that Section 2.3, by its terms, appears to apply only to projects for which there was an understanding at the beginning of the project that the project would be completed using Rainforest’s name and assets. The trial court further noted that, as to these three projects, there was evidence that Rainforest’s only involvement was being “gifted” a “vanity credit” after the projects were completed. 4 also presented expert testimony explaining that a “vanity credit” is given as a gift to

help the credited entity build its reputation.

After the close of evidence, Bronner moved for a directed verdict on several

claims, including liability and damages for the Section 2.3 claim. The trial court denied

the motion and ruled that the case had to be resolved by the jury.

The jury found in favor of Bronner on his Section 2.3 claim against Packer and

awarded him $375,000. The jury also awarded Bronner $4,500 on a breach of contract

claim relating to another provision of the Reconciliation Agreement. On all other

claims and counterclaims, including the parties’ competing claims for attorney fees,

the jury found against the respective claimants and determined that no award was

warranted.

The trial court entered a final judgment in accordance with the jury’s verdict,

and Bronner then filed a “Post-Trial Motion for Costs and Fees,” arguing that because

the jury returned a verdict in his favor on the Section 2.3 claim, he was entitled to

attorney fees under Section 3.4. Bronner also filed a motion for judgment

notwithstanding the verdict (“JNOV”), arguing that no reasonable jury could have

found a breach of the Reconciliation Agreement yet also denied an award of attorney

5 fees under Section 3.4 of that Agreement. The trial court denied the motions,

concluding that Bronner’s failure to include Section 3.4 attorney fees in his motion for

directed verdict precluded him from obtaining a JNOV on this issue. In its order

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. Proffitt
545 S.E.2d 623 (Court of Appeals of Georgia, 2001)
Goldstein v. Wells
673 S.E.2d 325 (Court of Appeals of Georgia, 2009)
James E. Warren, M.D., P.C. v. Weber & Warren Anesthesia Services, LLC
612 S.E.2d 17 (Court of Appeals of Georgia, 2005)
Brock v. King
629 S.E.2d 829 (Court of Appeals of Georgia, 2006)
Stephens v. McGarrity
660 S.E.2d 770 (Court of Appeals of Georgia, 2008)
Cawley v. Bennett
666 S.E.2d 438 (Court of Appeals of Georgia, 2008)
Southern Land Title, Inc. v. North Georgia Title, Inc.
606 S.E.2d 43 (Court of Appeals of Georgia, 2004)
Rm Kids, LLC v. Old Republic National Title Insurance Company
788 S.E.2d 542 (Court of Appeals of Georgia, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
ROBERT E. HARDY, II v. BERNARD H. BRONNER, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-e-hardy-ii-v-bernard-h-bronner-gactapp-2026.