Road Improvement Dist. No. 4 of Conway County v. Wilkerson

5 F.2d 416, 1925 U.S. App. LEXIS 2671
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 16, 1925
Docket6647
StatusPublished
Cited by11 cases

This text of 5 F.2d 416 (Road Improvement Dist. No. 4 of Conway County v. Wilkerson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Road Improvement Dist. No. 4 of Conway County v. Wilkerson, 5 F.2d 416, 1925 U.S. App. LEXIS 2671 (8th Cir. 1925).

Opinion

KENYON, .Circuit Judge.

This is an appeal from a judgment of the District Court of the United States for the Eastern District of Arkansas in. an action brought by ap-pellee, trustee for the P. J. Lewelling Construction Company, to recover a balance alleged to be due said company for work and material furnished in the construction of a certain road or roads for appellant. Appel-lee claims that the P. J. Lewelling Construction Company entered into a contract with appellant to construct the roadbed of the proposed highway in accordance with the plans and specifications, and under the direction of the district engineer, and that the amount actually due for said work was $443,-102.20; that monthly estimates had been furnished by the engineers of materials and work done, amounting to $392,590, and that there is a balance due and unpaid of $50,-743.20. The original complaint asked for profits, which claim, however, has been abandoned. The claim at the time of suit was the property of E. M. Wilkerson, trustee for the P. J. Lewelling Construction Company.

Appellant contended in the trial court, and contends here, that, some controversy having arisen between the parties, a demand was made upon it by the Construction Company for a final estimate and release of its contract, and .that such final estimate was made, which was accepted as a final settlement; said final estimate being known as “No. 27.” This showed an amount due to the construction company of $13,634.54. Three cheeks were given therefor, in the respective sums of $5,210, $2,114.54, and $6,310. In two of these cheeks were these words: “In payment of final estimate due the Lewelling' Const. Co.” In the other cheek was this phrase: “Final estimate consummates contract.” The final estimate was dated June 13,1921. The cheeks above referred to were dated June 21, 1921. Mr. Dudley, who was treasurer and bookkeeper of the construction company, indorsed them in blank in the name of the construction company, by himself as treasurer, as appears on the cheeks, and delivered them to the Bank of Morrillton, which held an assignment of the estimates and retained percentages. Afterwards two competent engineers went over the work which had been done by the Lewelling Construction Company, and testified to shortages in the final estimates, making a difference in favor of the construction company in the amount of $50,624.84.

By consent of the parties the ease was referred by the court to a master, with instructions to make findings and submit the same to the court. The master, after hearing the testimony of witnesses, reported to *418 the court that the account, as stated by the engineer of the district, was short, as shown by a table inserted in'the master’s report, in the sum of $50,624.84, less 32 cents admitted over allowance, and found that the claim of the trustee of the construction company for judgment in the sum of $50,624.52 was 'supported by a preponderance of the evidence. The court approved the findings of the master, and entered judgment for said amount and costs on the 25th day of May, 1923.

The ease being referred by the court to the master at the request of both parties, and the findings being concurred in and confirmed by the trial court, they must be accepted as presumptively correct, “and unless some obvious error has intervened in the application of the law, or some serious or important mistake has been made in the consideration of the evidence, the decree should be permitted to stand.” Crawford v. Neal, 144 U. S. 585, 596, 12 S. Ct. 759, 36 L. Ed. 552; Tilghman v. Proctor, 125 U. S. 136, 8 S. Ct. 894, 31 L. Ed. 664; Kimberly v. Arms, 129 U. S. 512, 9 S. Ct. 355, 32 L. Ed. 764; Davis v. Schwartz, 155 U. S. 631, 15 S. Ct. 237, 39 L. Ed. 289; Furrer v. Ferris, 145 U. S. 132, 12 S. Ct. 821, 36 L. Ed. 649.

What were the findings of the master? They were: That there was gross error in the final estimate; that there was no testimony to show that Mr. Dudley had authority to bind the construction company to an accord and satisfaction by accepting the cheeks containing the statement that they were given “in payment of final estimate due the Lew-elling Const. Co., which consummates contract” ; that Mr. Lewelling had no reason to suspect that .the accounts kept by appellant’s agent were inaccurate; that he had the right to assume that the engineer was keeping accurate accounts; that the commissioners of the district proceeded on the same assumption, and-neither party had knowledge that the engineer’s accounts were materially inaccurate; that Mr. Lewelling agreed to settle on the basis of the final estimate; that the settlement was made under a mutual mistake as to material facts, and was not binding. The trial court entered decree in accordance with the master’s report.

The principal defense insisted on is that these cheeks, given for the amount of the final estimate, reciting "that they were in payment thereof and consummated the contract, amount to an accord and satisfaction. It is a general principle of law that, where there is a dispute concerning a claim and a check is given, or other remittance to the creditor, which recites that it is in full payment of the claim, and the same is accepted by the creditor, or if the creditor collects the check without objection, the transaction constitutes an accord and satisfaction. 1 R. C. L. § 32; Barham v. Bank of Delight, 94 Ark. 159, 126 S. W. 394, 27 L. R. A. (N. S.) 439; Bassick Gold Mine Co. v. Beardsley, 49 Colo. 275, 112 P. 770, 33 L. R. A. (N. S.) 852; Canton Union Coal Co. v. Parlin & Orendorff Co., 215 Ill. 244, 74 N. E. 143, 106 Am. St. Rep. 162.

Is this broad proposition applicable here? There is testimony, which is referred to by the master to the effect that Mr. Dudley, treasurer and bookkeeper of the Lewelling Construction Company, had no authority to bind the construction company by accepting checks containing the statements as to payment and consummation of the contract. There is also testimony that the company had no notice of the particular wording of the cheeks regarding payment until this suit was brought. The master makes no specific finding as to the authority of Dudley, but the evidence shows he had no authority to bind the construction company 'by an accord and satisfaction. We do not consider this question, however, of controlling importance, for, as we view if, the decisive point in the ease is the alleged' mutual mistake as to the final estimate. These cheeks were in payment of and based upon the final estimate. There is a dispute as to whether or not Lewelling, who was president and evidently the controlling spirit of .the construction company, knew of the estimate, and saw the same before the checks were given. The date of the estimate is June 13, 1921, and the date of the cheeks is June 21, 1921. He testifies he did not see the final estimate before the checks were given; that he did see a memorandum of the same made by one Nicholson. Other witnesses for appellant testified that they discussed the final estimate with him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
5 F.2d 416, 1925 U.S. App. LEXIS 2671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/road-improvement-dist-no-4-of-conway-county-v-wilkerson-ca8-1925.