RNS Servicing, LLC v. Spirit Construction Services, Inc.

CourtDistrict Court, N.D. Illinois
DecidedMarch 25, 2020
Docket1:17-cv-00108
StatusUnknown

This text of RNS Servicing, LLC v. Spirit Construction Services, Inc. (RNS Servicing, LLC v. Spirit Construction Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RNS Servicing, LLC v. Spirit Construction Services, Inc., (N.D. Ill. 2020).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

RNS SERVICING, LLC, ) ) Plaintiff, ) No. 17-cv-00108 ) v. ) ) Judge Edmond E. Chang SPIRIT CONSTRUCTION SERVICES, ) INC., et al. ) ) Defendants. )

MEMORANDUM OPINION AND ORDER More than a decade ago, RNS Servicing’s predecessor-in-interest (IFC Credit Corporation) entered into a settlement agreement that was supposed to be worth $3.9 million but later turned out to be worth nothing. RNS now alleges that Defendants Spirit Construction, Steve Van Den Heuvel, and Sharad Tak fraudulently induced IFC to enter into the agreement. R. 31, Am. Compl.1 As Defendants point out, however, the alleged fraud occurred back in 2007, which they argue is way beyond the scope of any relevant statute of limitations that might govern this case. Naturally, the parties now dispute when exactly the claims against Defendants accrued and started the ticking of the limitations clock. Defendants argue that IFC should have known about the alleged fraud back in 2007 or 2008 at the latest, while RNS maintains that the limitations period did not start running until 2016.

1Citation to the docket is “R.” followed by the entry number and, when necessary, the relevant page or paragraph number. The statute of limitations issue was first raised at the pleading stage, but the Court held off on ruling until the parties were given an opportunity to engage in limited discovery on the issue. R. 51. Now that discovery on this issue is complete,

the parties have filed cross-motions for summary judgment on the limitations question only. R. 64; R. 76. For the reasons discussed below, RNS’s motion is denied, and the Defendants’ motion is granted: the case was untimely filed and is dismissed. I. Background The facts narrated below are undisputed unless otherwise noted.2 In 2005, IFC Credit Corporation, an equipment-lease finance company, entered into a series of lease agreements with a group of tissue-paper manufacturing companies. R. 65,

DSOF ¶¶ 10, 12. These tissue-paper manufacturing companies were all operated by an individual named Ron Van Den Heuvel. Id. ¶ 14. For the sake of convenience, the companies will collectively be referred to as the “Ron Companies.” Unfortunately, the Ron Companies soon defaulted on the leasing agreements; IFC sued the Ron Companies for breach of contract; and then IFC and Ron tried to work out various settlement agreements. DSOF ¶¶ 14-18. This initial settlement

process proved largely unsuccessful until Ron enlisted the help of his brother, Steve Van Den Heuvel. Long story short, IFC eventually agreed to settle its claims against the Ron Companies for a total of $23.9 million. Id. ¶¶ 23, 29-30. The bulk of the

2Citations to the parties’ Local Rule 56.1 Statements of Fact are identified as follows: “DSOF” for the Defendants’ Statement of Facts [R. 65]; “Pl.’s Resp. DSOF” for RNS’s response to the Defendants’ Statement of Facts [R. 75]; “PSOF” for RNS’s Statement of Additional Facts [R. 75]; and “Defs.’ Resp. PSOF” for the Defendants’ response to RNS’s Statement of Additional Facts [R. 85]. settlement would be paid upfront,3 while the remaining $3.9 million would be paid to IFC in monthly installments. Id. ¶¶ 23, 28. Here is where Steve comes in. Steve owned a construction company called

Spirit Construction. DSOF ¶ 2. And while all of this was going on, Spirit had entered into a construction deal with another company called ST Paper I, which was owned by an individual named Sharad Tak. Id. ¶¶ 3, 19. Pursuant to this deal, Steve and Tak had apparently executed four contracts for Spirit to perform engineering procurement and construction work for ST Paper I. Id. ¶ 19. These will be referred to as the EPC Contracts. The EPC Contracts were supposed to be lucrative; RNS alleges that each contract was represented to be worth at least $200 to $400 million. R. 75,

PSOF ¶ 6. The plan was for Spirit to hire the Ron Companies as subcontractors on the four EPC projects. DSOF ¶ 26. That meant the Ron Companies would work on the EPC projects in exchange for subcontractor payments, which could then be used by the Ron Companies to pay back IFC. Indeed, the Ron Companies explicitly assigned to IFC their right to receive the first $3.9 million in subcontractor payments under the EPC Contracts. Id. ¶ 28. According to Ron, the EPC Contracts would be

funded within a few weeks. R. 75, Pl.’s Resp. DSOF ¶ 37. What really cinched the deal was that Spirit and Steve also signed a separate agreement to make the EPC subcontractor payments directly to IFC until Ron’s $3.9

3This upfront portion of the settlement payment was technically split between two other lenders (Fortress and George Washington State Bank); it did not go to IFC. Pl.’s Resp. DSOF ¶ 33. IFC had previously transferred to Fortress and GWS Bank certain rights to lease payments from the Ron Companies, which is why Fortress and GWS Bank were part of the ultimate settlement agreement with Ron. DSOF ¶¶ 11, 14. million debt had been paid off. DSOF ¶ 30. So instead of Spirit paying Ron and then Ron paying IFC, Spirit would just directly pay IFC. Also, Spirit and Steve acknowledged in writing that the Ron Companies were indeed subcontractors in

connection with the EPC Contracts; they would receive more than $3.9 million in subcontractor payments; and the EPC Contracts were in full force and effect. Id. ¶¶ 26-30. Around this same time, IFC also received in-person assurances about the EPC Contracts from Tak. Specifically, Tak met with IFC’s CEO (Rudy Trebels) and CFO (Marc Langs) and confirmed that he and Steve had in fact executed the EPC Contracts; he fully intended to build the four projects contemplated by the four EPC Contracts; the EPC Contracts would be sufficiently financed; and finally, the Ron

Companies would be hired as subcontractors under the EPC Contracts. Id. ¶¶ 31-32. The parties dispute whether IFC ever reviewed the four EPC Contracts themselves before entering the settlement agreement. According to RNS, Defendants refused to allow IFC to access the EPC Contracts because of “regulatory and confidentiality concerns.” PSOF ¶¶ 8, 12. Defendants, on the other hand, maintain that IFC was given access to the contracts. R. 85, Defs.’ Resp. PSOF ¶ 12. In any

event, IFC apparently believed that the Ron Companies would have access to ample income via the EPC Contracts, which is why IFC agreed to formally settle its claims against the Ron Companies in March 2007. But the money did not start pouring in. By June 2007, Ron had still not yet made a single payment. DSOF ¶ 33; Pl.’s Resp. DSOF ¶ 33. So, in September 2007, IFC initiated its second lawsuit against Ron, this time for breaching the settlement agreement and misrepresenting the funding status of the EPC Contracts. Id. ¶ 34. In the complaint, IFC also named Spirit as a defendant, seeking a preliminary injunction prohibiting Spirit from making any direct payments to the Ron Companies

until IFC’s $3.9 million debt had first been paid off. Id. The second case eventually proceeded to discovery and then summary judgment. In support of summary judgment, Marc Langs (IFC’s CFO) signed an affidavit in which he stated that “IFC would not have agreed to allow [the Ron Companies] a ten-month payment schedule if we had known that the EPC Contracts were not going to be funded for many months (to our knowledge, the EPC Contracts are still not funded.) Nor would IFC have allowed [the Ron Companies] a ten-month

payment schedule if we knew that those companies were not going to receive ‘substantial payments’ under the EPC Contracts.” DSOF ¶ 37. In 2009, the judge presiding over the second case ultimately denied IFC’s motion for summary judgment on its injunctive-relief claim against Spirit and granted Spirit’s summary judgment motion against that same claim. PSOF ¶ 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Carmichael v. Village of Palatine, Ill.
605 F.3d 451 (Seventh Circuit, 2010)
Omnicare, Inc. v. Unitedhealth Group, Inc.
629 F.3d 697 (Seventh Circuit, 2011)
Wells v. Travis
672 N.E.2d 789 (Appellate Court of Illinois, 1996)
Gredell v. Wyeth Laboratories, Inc.
803 N.E.2d 541 (Appellate Court of Illinois, 2004)
Knox College v. Celotex Corp.
430 N.E.2d 976 (Illinois Supreme Court, 1981)
Orlak v. Loyola University Health System
885 N.E.2d 999 (Illinois Supreme Court, 2007)
American Family Mutual Insurance Company v. Plunkett
2014 IL App (1st) 131631 (Appellate Court of Illinois, 2014)
American Family Mutual Insurance Company v. Krop
2018 IL 122556 (Illinois Supreme Court, 2018)
Holland v. Florida
177 L. Ed. 2d 130 (Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
RNS Servicing, LLC v. Spirit Construction Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rns-servicing-llc-v-spirit-construction-services-inc-ilnd-2020.