RMS Technology, Inc. v. TDY Industries, Inc.

64 F. App'x 853
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 6, 2003
Docket02-1299
StatusUnpublished
Cited by18 cases

This text of 64 F. App'x 853 (RMS Technology, Inc. v. TDY Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RMS Technology, Inc. v. TDY Industries, Inc., 64 F. App'x 853 (4th Cir. 2003).

Opinion

*854 OPINION

PER CURIAM.

Plaintiff RMS Technology brings this appeal alleging that the district court improperly dismissed its complaint against defendants Teledyne Industries, Inc., Teledyne Technologies Inc., and Teledyne Brown Engineering, Inc. (collectively “Teledyne”) on summary judgment. The district court properly applied both the Uniform Commercial Code and Virginia procedural law to these claims to find that the suit was filed outside of the applicable limitations period. We thus affirm the dismissal of RMS’s case.

I.

Lockheed Martin, which is not a party to this suit, contracted with Teledyne on May 2, 1995, to fabricate, test, and deliver armor moving target carrier (“AMTC”) systems. The AMTC systems were part of a Remote Target System (“RETS”) requested by the U.S. government to provide realistic combat training for the armed services. On July 7, 1995, Teledyne executed a contract (“Purchase Order 456258”) with RMS Technology under which RMS agreed to manufacture three first article and thirty-seven subsequent AMTC systems in its facilities in Newport News, Virginia. This assembly was to be completed between December 30, 1995, and July 30,1996.

Contract negotiations between Teledyne and RMS consisted of an exchange of letters regarding price estimates and each company’s responsibility under the purchase order. In its initial response to Teledyne’s request for quotes, RMS advised Teledyne that the price would vary based on what portion of the materials Teledyne supplied for the project. RMS also informed Teledyne that RMS was currently producing AMTC systems for the U.S. military, that RMS would continue production until December 1995, and that RMS thought any remaining first article tests on the AMTC systems might be waived because of its experience manufacturing such systems. Ultimately, the parties agreed that Teledyne would supply most of the raw materials for the first'two years of production and that RMS would supply primer, paint, cleaning chemicals, consumables and hydraulic fluid.

The contract provided that all work was to be completed in “accordance with the total technical and delivery requirements and terms and conditions as specified in the reference purchase order.” It also required RMS to represent and warrant “that the goods and services furnished” under the contract “be merchantable and fit for the particular purpose intended [and] free of defects in design workmanship and materials.” The contract further provided that “[t]itle and risk of loss to goods shall pass to Buyer upon receipt at Buyer’s designated destination.” Lastly, the contract contained a choice of law provision, stating that “[t]he rights and obligations of the parties hereto shall be governed by the law of the State of Alabama.”

On February 22, 1996, RMS advised Teledyne that it was “compelled to stop work on contract number 456258 due to a lack of funds.” RMS also informed Teledyne that it had laid off all of its employees. Following receipt of RMS’s correspondence, Teledyne sent a letter to RMS on February 29, 1996, alleging default by RMS and terminating the contract.

On April 26, 1996, RMS submitted a claim for $176,435.56 to Teledyne for out of scope work done in connection with the contract. Teledyne responded by letter, informing RMS that it would submit all valid and substantiated claims to Lockheed Martin as part of its settlement proposal. In November, 1996, Teledyne sent this *855 proposal to Lockheed Martin, including only the amounts that Teledyne had actually paid to RMS. Teledyne also informed Lockheed that RMS had claimed additional costs, but that such costs were not included in the proposal because they were not yet substantiated. On December 20, 1996, Teledyne entered into a settlement agreement with Lockheed Martin which did not include any sums for the allegedly out of scope work.

On February 23, 2001, RMS filed a five count complaint against Teledyne in the United States District Court for the Eastern District of Virginia for $282,788.78, plus pre-judgment interest and costs. RMS alleged breach of contract (Count I), quantum meruit (Count II), impossibility and commercial impracticality of performance of the contract (Count III), unjust enrichment (Count IV), and constructive trust (Count V). Teledyne filed a motion for summary judgment on April 26, 2001, arguing that each count of RMS’s complaint had been filed outside the applicable statute of limitations period.

Specifically, Teledyne contended that the contract was for the sale of goods and was therefore governed by the Uniform Commercial Code (UCC). Teledyne also argued that the equitable counts of the complaint were barred by Virginia’s three year statute of limitations for unwritten contracts. The district court agreed and granted Teledyne’s motion for summary judgment on October 22, 2001. RMS appeals this ruling.

II.

Summary judgment is appropriate when “the record taken as a whole could not lead a rational trier of fact to find for the non-moving party.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). The district court found that there was no genuine issue of fact in this case as to which statutes of limitations applied. We agree.

A.

RMS first contends that the district court erred by applying the UCC’s four year statute of limitations to Counts I and III of its complaint. Whether a particular transaction is governed by the UCC depends on the predominant purpose of the transaction, however. Princess Cruises, Inc. v. Gen. Elec. Co., 143 F.3d 828, 832-33 (4th Cir.1998). Where, as here, a transaction is primarily for the sale of goods, the terms of the UCC govern claims arising from that transaction. Id. RMS argues that its duty under the contract was only to provide the necessary labor, processes and facilities to fabricate the AMTC systems with materials provided by Teledyne. The contract price, then, was based solely on the cost of the man-hours needed to complete the contract and not on the cost of the AMTC systems themselves. Therefore, RMS contends that the district court erred in finding that RMS did not create a genuine issue of fact as to whether the contract was for the rendering of services or for the sale of goods.

Three factors are helpful in determining the primary purpose of a contract: (1) the language of the contract; (2) the nature of the business of the supplier; and (3) the intrinsic worth of the materials involved. Coakley and Williams, Inc. v. Shatterproof Glass Corp., 778 F.2d 196, 197 (4th Cir.1985). Each of these factors weighs in favor of a finding that this contract was for the sale of goods.

Under the first factor, the district court correctly found that a number of indicia in the contract language signal that the contract was for the sale of goods. The UCC defines goods as “all things (including spe *856

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
M.D. North Carolina, 2026
CM-Focus LLC v. Conviso LLC
W.D. Virginia, 2025
LLT Management LLC v. Emory
E.D. Virginia, 2025
FREDEKING v. TRIAD AVIATION, INC.
M.D. North Carolina, 2022
Herren Farms, LLC v. Martin
W.D. Virginia, 2022
In re Lewis
517 B.R. 615 (E.D. Virginia, 2014)
East West, LLC v. Rahman
873 F. Supp. 2d 721 (E.D. Virginia, 2012)
Rms Technology, Inc. v. Teledyne Industries, Inc.
540 U.S. 814 (Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
64 F. App'x 853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rms-technology-inc-v-tdy-industries-inc-ca4-2003.