Herren Farms, LLC v. Martin

CourtDistrict Court, W.D. Virginia
DecidedJuly 18, 2022
Docket3:21-cv-00025
StatusUnknown

This text of Herren Farms, LLC v. Martin (Herren Farms, LLC v. Martin) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herren Farms, LLC v. Martin, (W.D. Va. 2022).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF VIRGINIA CHARLOTTESVILLE DIVISION

HERREN FARMS, LLC, Plaintiff, CASE NO. 3:21-cv-00025

v. MEMORANDUM OPINION

LAWRENCE E. MARTIN, t/a LnR Feed & Grain Handling Systems JUDGE NORMAN K. MOON

Defendant.

Plaintiff’s 115-foot grain elevator collapsed on a windy day in April of 2017, causing over half a million dollars of property damage. Plaintiff now seeks to recover those losses in this breach of contract suit against Defendant, who sold and assembled the elevator just six months prior to its failure. According to Plaintiff, Defendant breached his implied duty of care by improperly installing the elevator’s guy wires and support brackets—two stabilizing systems that would have prevented the elevator from falling. Currently before the Court is Defendant’s motion for summary judgment, which turns solely on Defendant’s contention that the statute of limitations has run on Plaintiff’s claim. The question comes down to which of Virginia’s statutory periods applies: (1) that relating to the sale of goods, (2) that relating to unsigned contracts for services, or (3) that relating to signed contracts for services. Plaintiff’s claim is time-barred if governed by the first two provisions. But it is timely under the third. Defendant’s motion will be denied because a rational factfinder could conclude that the parties’ contract is signed and is for services. I. Background Plaintiff owns and operates a small farm outside of Culpeper, Virginia. Complaint ¶ 1.1 In the summer of 2016, Plaintiff decided to expand its grain handling and storage facilities by having Defendant, a “Feed and Grain Systems Design and Build Contractor,” see Dkt. 31-1, erect three large grain silos and a 115-foot grain elevator on his property. See Dkt. 31-8 p. 12 (engineer’s drawing of elevator and grain bins). This final design was the culmination of several days of back-and-forth negotiations with Defendant, whereby Defendant submitted drawings and

quotes for Plaintiff’s review. The first piece of correspondence in the record is an email dated June 28, 2016, in which Defendant previewed three designs for Plaintiff in illustration of “the general idea of what you can do.” See Dkt. 31-2 p. 1. Following some discussion, Defendant returned to Plaintiff a few days later (again by email) with detailed specs for a facility utilizing a 75-foot grain elevator, as well as a conveyor system to transport grain to the largest of three silos. See Dkt. 31-3. In addition to the itemized “Estimate/Contract” documents that came as attachments to this email, the body of the email included a summary of costs and instructed Plaintiff to “return with your written approval and a 10% deposit to order.” Id. p. 1. Negotiations continued. Defendant sent Plaintiff a subsequent email later that same day promoting an alternative design, this time

featuring a 115-foot elevator that would save money by obviating the need for a conveyor system. See Dkt. 31-4. The signature line in the body of each of Defendant’s emails bore Defendant’s name in cursive font. Defendant eventually emailed detailed proposals for the construction of a grain handling and storage system utilizing the 115-foot elevator design. See Dkt. 31-5. The

1 Plaintiff’s Complaint can be found at Dkt. 1-1 pp. 7–9. “Estimate/Contract” documents once more came in the form of email attachments, with the body of each email carrying Defendant’s electronic signature and the opening email repeating Defendant’s instruction to Plaintiff to “return with your written approval and a 10% deposit to order.” See id. p. 7. The total estimate for the final version of the project was $285,752.00. Id. p. 4. This included $26,839.00 in labor for Plaintiff to “[a]ssemble and erect” the elevator. Dkt. 29- 2 p. 6. If that last number seems high, consider that the 75-page assembly manual provided by

the elevator’s manufacturer instructs that “[q]ualified civil engineers and contractors should be relied upon for site design, layout and construction. This manual is to be used as a guideline only.” Dkt. 31-7 p. 3. And in the section relating to guy wire brackets, the manual specifically provides that “Customer (or its retained engineer or construction supervisor) is responsible [to determine suitable guying and/or bracing methods and materials] and should give consideration to . . . wind loads.” Id. p. 44. The role of the installer becomes especially critical where, as with Plaintiff’s project, accessory equipment is involved. On page 18, under the heading “Pre- Installation Information,” the manual states: Bucket Elevators are designed to be vertically self-supporting when erected, but must be supported or guyed against wind loads. This elevator has not been designed to support other equipment such as cleaners, distributors, spouting, etc. Separate structures must be provided to support any accessory equipment. . . . It is the responsibility of user and/or installer to consult a civil or structural engineer regarding installation, including but not limited to construction, supervision, foundation, guying or bracing for specific site.

NOTE: The MOST IMPORTANT preparations are retaining a licensed engineer to plan installation and a qualified millwright or contractor to erect elevator and accompanying equipment and structures. Plaintiff’s grain elevator incorporated both a distributor and downspouting system. See Dkt. 29-2 p. 1. In addition to professional engineers, Plaintiff’s affidavit reflects that “proper construction” of the elevator required “a crane, a forklift, field welding, the fabrication and installation of guy wire and bracing systems, as well as concrete footings and anchoring for the more than ten story tall structure.” Dkt. 31 ¶ 18 (emphasis added). Defendant confirmed in his deposition testimony that the assembly and erection of the elevator required “on-site welding and

brackets for the guy wires,” which were his responsibility. Dkt. 32-1 (Martin Deposition) 46:20– 47:4. Defendant in fact did not retain or consult any civil or structural engineers when erecting Plaintiff’s elevator. See id. 43:2–17. He also installed the guy wire brackets at greater intervals, used two fewer guy wires, and used fewer concrete anchors than instructed by the manufacturer. See id. 43:18–46:19. As previewed above, Plaintiff’s elevator collapsed in high winds only a few months after its construction. An engineering report prepared by Plaintiff’s insurer concluded that the collapse resulted from Defendant’s failure to adequately design and manufacture the elevator’s wind- loading restraints. See Dkt. 31-8 p. 8. Defendant does not dispute that conclusion. See Martin

Deposition 47:6–18.

II. Legal Standard Summary judgment is appropriate where “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). In considering whether the record rationally supports the facts necessary to the nonmovant’s case, the Court must take “the evidence and all reasonable inferences drawn therefrom in the light most favorable to the nonmoving party.” Henry v. Purnell, 652 F.3d 524, 531 (4th Cir. 2011) (en banc). Nevertheless, a party opposing summary judgment “may not rest upon the mere allegations or denials of his pleading but must set forth specific facts showing that there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986) (cleaned up).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Henry v. Purnell
652 F.3d 524 (Fourth Circuit, 2011)
RMS Technology, Inc. v. TDY Industries, Inc.
64 F. App'x 853 (Fourth Circuit, 2003)
Bray v. Brown
521 S.E.2d 526 (Supreme Court of Virginia, 1999)
Williamson v. Bank of New York Mellon
947 F. Supp. 2d 704 (N.D. Texas, 2013)
Coakley & Williams, Inc. v. Shatterproof Glass Corp.
706 F.2d 456 (Fourth Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Herren Farms, LLC v. Martin, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herren-farms-llc-v-martin-vawd-2022.