R.M. Taylor, Inc. v. H.M. White, Inc. (In Re R.M. Taylor, Inc.)

257 B.R. 289, 2000 Bankr. LEXIS 1633, 2000 WL 33115292
CourtUnited States Bankruptcy Court, W.D. Missouri
DecidedDecember 8, 2000
Docket19-30094
StatusPublished
Cited by9 cases

This text of 257 B.R. 289 (R.M. Taylor, Inc. v. H.M. White, Inc. (In Re R.M. Taylor, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.M. Taylor, Inc. v. H.M. White, Inc. (In Re R.M. Taylor, Inc.), 257 B.R. 289, 2000 Bankr. LEXIS 1633, 2000 WL 33115292 (Mo. 2000).

Opinion

MEMORANDUM OPINION

ARTHUR B. FEDERMAN, Chief Judge.

Debtor in possession R.M. Taylor, Inc. (RMT) filed this adversary proceeding to avoid alleged preferential transfers to defendant H.M. White, Inc. (White) totaling $334,170.00. On May 23, 2000, after RMT *291 filed the adversary, this Court converted the Chapter 11 case to Chapter 7. John L. Lewis, Jr., in his capacity as the Chapter 7 trustee (the Trustee), is now substituted as plaintiff. This is a core proceeding under 28 U.S.C. § 157(b)(2)(F) over which the Court has jurisdiction pursuant to 28 U.S.C. § 1334(b), 157(a), and 157(b)(1). The following constitutes my Findings of Fact and Conclusions of Law in accordance with Rule 52 of the Federal Rules of Civil Procedure as made applicable to this proceeding by Rule 7052 of the Federal Rules of Bankruptcy Procedure. For the reasons set forth below, I will find that the transfers in question here are not preferential.

FACTUAL BACKGROUND

RMT was a general contractor engaged in the business of design, manufacture, and installation of conveyor systems for the automotive industry. To that end, RMT hired subcontractors to complete all or part of various construction projects. In turn, RMT was sometimes hired as a subcontractor on other construction projects for the automotive industry. In one such instance RMT entered into a contract with General Motors (GM) to construct the Frame De-Ice Oven System (Invoice Number 477585) at the East Assembly Plant in Pontiac, Michigan (the Pontiac East Project). 1 RMT hired as a subcontractor on this job defendant White, a Michigan industrial sheet metal contractor that designs, builds, and installs air handling equipment in automotive plants. White’s subcontract agreement required RMT to pay it the sum of $477,868.00 for the work it was to perform. White began work on the Pontiac East Project in October of 1996, and completed the project on March 3,1997. RMT made three progress payments to White; the first on December 18, 1996, in the amount of $67,680.00; the second on January 20, 1997, in the amount of $143,820.00; and the third on March 6, 1997, in the amount of $190,350.00. The latter two payments, totaling $334,170.00, are the subject of this preference action. Either immediately before or after RMT made the above payments, it obtained partial lien releases from White. RMT required such lien releases because GM only paid RMT upon proof of payment by RMT to its subcontractors.

On June 6, 1996, White, acting as the general contractor, had hired RMT as a subcontractor on a different job, referred to as the Lake Orion Project. In essence this subcontract agreement required RMT to make field installations during the July 1996, Thanksgiving 1996, Christmas 1996, and July 1997 shutdown periods at a GM factory. RMT completed the July 1996, Thanksgiving 1996, and Christmas 1996 installations. White made two payments to RMT, but one invoice, submitted by RMT to White on March 11, 1997, remained unpaid on April 11, 1997, when RMT filed its Chapter 11 bankruptcy petition. According to the testimony of Scott Simkins, RMT’s controller at the time of the transfers at issue, and William White, White’s president at the time of the transfers at issue, the balance due to RMT from White on that invoice, plus retainage, was $233,276.43, as of April 11,1997. 2

On January 20, 1997, RMT executed a check to White in the amount of $143,820.00 for work it performed on the Pontiac East Project prior to November 25, 1996. 3 In exchange, White signed a partial unconditional waiver of its construction hen, dated January 17, 1997, in the amount of $143,820.00. 4 On March 6, 1997, RMT executed a check to White in the amount of $190,350.00 for work it performed on the Pontiac East Project prior *292 to December 31, 1996. 5 In exchange, White signed a partial lien release, dated March 17, 1997, waiving its construction lien in the amount of $190,350.00. 6 R.M. Taylor and Jill Richardson testified that RMT had to submit signed lien releases from the subcontractors to GM in order to receive further payment. According to RMT’s bankruptcy schedules, GM still owed RMT $511,257.98 on the Frame DeIce Oven System Project (Invoice Number 477585) on April 11,1997. 7

On April 9, 1999, RMT, as debtor in possession, filed this adversary proceeding. The Complaint alleges that RMT preferentially transferred the sum of $334,170.00 to White and seeks to avoid same. This Court held a trial on November 20 and 21, 2000. Both in its trial brief and at the hearing the Trustee argued that all of the elements of a preferential transfer are satisfied, and that none of the exceptions apply. White disagreed on several grounds. Since I find that White did not receive more than it would have received in a Chapter 7 liquidation, and that RMT and White intended the transfer to be a contemporaneous exchange for new value, I will deal substantively only with those arguments.

DISCUSSION

A. Preferential Transfer in General

Section 547(b) of the Bankruptcy Code (the Code) allows the bankruptcy trustee to avoid certain transfers that are deemed preferential. 8 As relevant here, a transfer of RMT’s property made to White within 90 days of the bankruptcy petition on account of an antecedent debt that benefitted White more than other creditors similarly situated would be preferential:

(B) Except as provided in subsection (c) of this section, the trustee may avoid any transfer of an interest of the debtor in property—
(1) to or for the benefit of a creditor;
(2) for or on account of an antecedent debt owed by the debtor before such transfer was made;
(3) made while the debtor was insolvent;
(4) made—
(A) on or within 90 days before the date of the filing of the petition;
(5) that enables such creditor to receive more than such creditor would receive if—
(A) the case were a case under chapter 7 of this title;
(B) the transfer had not been made; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Shields
586 B.R. 315 (W.D. Missouri, 2018)
Sarachek v. Luana Savings Bank
547 B.R. 292 (N.D. Iowa, 2016)
Schnittjer v. Pippert (Carney)
396 B.R. 22 (N.D. Iowa, 2008)
In Re Carney
396 B.R. 22 (N.D. Iowa, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
257 B.R. 289, 2000 Bankr. LEXIS 1633, 2000 WL 33115292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rm-taylor-inc-v-hm-white-inc-in-re-rm-taylor-inc-mowb-2000.