Davis v. Kice Indus., Inc. (In re WB Servs., LLC)

587 B.R. 548
CourtUnited States Bankruptcy Court, D. Kansas
DecidedJune 25, 2018
DocketCASE NO. 16–10759; ADV. NO. 17–5074
StatusPublished
Cited by2 cases

This text of 587 B.R. 548 (Davis v. Kice Indus., Inc. (In re WB Servs., LLC)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Kice Indus., Inc. (In re WB Servs., LLC), 587 B.R. 548 (Kan. 2018).

Opinion

Dale L. Somers, United States Chief Bankruptcy Judge

Defendant Kice Industries, Inc. (Kice), moves for summary judgment on the Chapter 7 Trustee's preference claim under 11 U.S.C. § 547.1 Kice was a subcontractor *552of Debtor WB Services, LLC (Debtor), which was the prime contractor for the construction of a project on property owned by East Kansas Agri-Energy, LLC (EKAE or Owner). Within 90 days before Debtor filed for relief under Chapter 7, EKAE paid Kice on a past due account by a check payable jointly to Debtor and Kice. The Trustee seeks to recover the payment as a preferential transfer. Kice asserts it is entitled to summary judgment because the transfer it received was not "an interest of the debtor in property" as required to make the payment a preference under § 547(b), or because even if the transfer was preferential, the new value defense of § 547(c)(1) bars the Trustee's recovery.2

For the reasons examined below, the Court rejects Kice's arguments that the transfer was not preferential. The Court also finds that the new value defense may defeat the Trustee's claim, but the uncontroverted facts are insufficient for the Court to rule on this issue, necessitating a trial.

UNCONTROVERTED FACTS .

EKAE as Owner and Debtor WB as Contractor entered into a Design-Build Agreement Between Owner and Contractor dated July 15, 2014 (the Contract), for the construction of a renewable diesel facility on real property owned by EKAE (the Project). Section 9.2.4.2 on the contract provides:

9.2.4.2 RESPONSIBILITY FOR LIENS. If Owner has made all payments in the time required by this article, Contractor shall, within a reasonable time after filing, cause the removal of any liens filed against the premises or public improvement fund by any party or parties performing labor or services or supplying materials in connection with the Work. If Contractor fails to take such action on a lien, Owner may cause the lien to be removed at Contractor's expense, including bond costs and reasonable attorneys' fees.3

Section 10.1.1.1 provides:

10.1.1.1 Provided Contractor has been paid in accordance with this Agreement, Contractor shall keep the Worksite free from all liens, charges, claims and judgments, security interests or encumbrances ("Liens") arising out of the performance of the Work and shall defend, indemnify and hold harmless Owner, lenders, and the Worksite from and against all costs, charges, expenses, including reasonable attorneys' fees related to any Liens, that Owner may incur resulting from or arising out of such Liens. Contractor shall take prompt steps to discharge or bond off any such Lien filed against the Worksite by any Subcontractor, sub-subcontractor, or Material Supplier.4

Debtor WB as Contractor and Kice as Subcontractor entered into a contract dated November 11, 2014, under which Kice agreed to supply labor and material for the Project. The subcontract provided for Kice to submit applications for partial payment as work progressed, and for approved applications *553to be paid within 30 days of receipt.

In late 2015 and early 2016, representatives of EKAE and Debtor expressed concerns in ongoing conversations about whether the subcontractors and suppliers for the Project were being paid in a timely manner. In January 2016, Debtor was behind on making payments to Kice, and on January 20, 2016, Kice stopped work on the Project due to Debtor's failure to pay.

In February and March 2016, representatives of Debtor and EKAE discussed how to pay Debtor for work on the Project while assuring subcontractors and suppliers were paid. EKAE recommended issuing joint checks, payable to Debtor and subcontractors or suppliers, and Debtor did not oppose that proposal. Under the agreed procedure, EKAE would issue checks jointly payable to Debtor and subcontractors or suppliers, a representative of Debtor would come to EKAE's offices and endorse the checks, and EKAE would mail the checks to the subcontractors and suppliers. Using this procedure, EKAE intended to control the application of the funds it would pay.

Debtor prepared two conditional lien waivers for Kice to complete as a condition for receiving the past due funds it was owed. One is for $79,581.35 and the other is for $3,080.00. Both waivers state that they cover a progress payment for labor, services, equipment, or material furnished to Debtor through February 23, 2016. Kice executed both waivers on February 24, 2016, and returned them to Debtor. Before it received the check on March 7, 2016, Kice had a right to file a subcontractor's lien against the Project property.

Debtor submitted applications for payment to EKAE for work on the Project on February 9, 2016, February 23, 2016, and March 4, 2016. On March 4, 2016, EKAE issued six checks jointly payable to Debtor and six different subcontractors, including a check jointly payable to Debtor and Kice for $118,191.35. The amount of this check was for the outstanding amount owed for Kice's work on the Project, although the lien waivers Kice had signed covered only $82,661.35 of that balance. A representative of Debtor came to the EKAE facility and endorsed the check, and EKAE then mailed it to Kice. Kice received the check and deposited it on March 7, 2016, which was within 90 days of January 20, 2016, the date Kice last performed work on the Project. On its financial records, Debtor entered $118,191.35 as a payment received from EKAE.

Debtor filed for relief under Chapter 7 on April 28, 2016. The Chapter 7 Trustee filed his complaint in this action on June 19, 2017. He alleges that Kice's receipt of the joint payee check for $118,191.35 was a preferential transfer that should be avoided, and prays for judgment in the amount of $118,191.35, plus interest and costs.

ANALYSIS.

The resolution of preference litigation involving a bankrupt general contractor in the construction industry presents unusual concerns because of the customs and practices of the industry. As one court has observed:

Like the law merchant of an earlier day, the building trades have gradually created a set of commercial expectations as the result of the customs and practices of the industry. The nature of the industry is such that the commercial expectations of the parties are defeated when a building contractor or subcontractor does not use accounts paid to him on a job to pay subcontractors or materialmen. Unless the parties see that construction funds are properly applied down the line, the liabilities of the parties up the line are affected. The unpaid *554workers [and subcontractors and suppliers] must undertake the lengthy and wasteful process of filing, perfecting and foreclosing on their mechanics liens. The owner's property and the construction lender's security are encumbered.5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
587 B.R. 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-kice-indus-inc-in-re-wb-servs-llc-ksb-2018.