RLB Contracting, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 3, 2014
DocketASBCA No. 57638
StatusPublished

This text of RLB Contracting, Inc. (RLB Contracting, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RLB Contracting, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) RLB Contracting, Inc. ) ASBCA No. 57638 ) Under Contract No. W912P8-07-C-0102 )

APPEARANCES FOR THE APPELLANT: Christopher B. Conley, Esq. Daniel J. Caruso, Esq. Simon, Peragine, Smith & Redfearn, L.L.P. New Orleans, LA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney William G. Meiners, Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE THRASHER

This appeal involves a Corps of Engineers (Corps) contract with RLB Contracting, Inc., (RLB) to enlarge a levee in southwest Louisiana using borrow material excavated from an adjacent ditch and the resulting claim arising from the realignment of the adjacent ditch. We have jurisdiction under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The government concedes entitlement and this decision only addresses quantum.

FINDINGS OF FACT

The Project Solicitation

1. The Corps issued Solicitation No. W912P9-07-B-0019 (solicitation) on 2 July 2007 to enlarge the Gordy Levee, part of the Atchafalaya Basin, Levees West of Berwick, West Bayou Sale (Bayou Sale project) located in southwest Louisiana 1 (supp. R4, tab 1). The location of the levee and the adjacent borrow ditch was in close proximity to the Gulf of Mexico and East Cote Blanche Bay (supp. R4, tab 43, Drawing No. 8) The solicited work consisted of clearing and grubbing, excavating the borrow ditch, trimming outfall drainage pipes in the existing ditch, constructing compacted fill levee embankment, removing and replacing culverts under ramps, placing surfacing

1 The solicitation was for a sealed bid 100% HUB Zone set-aside fixed-price constructi1 contract. material on the levee crown and ramps, fertilizing, seeding and mulching, installation of a new gas line, and other incidental work (supp. R4, tab 1). The largest single performance requirement of the solicitation, and the work at issue here, was the excavation and embankment work requiring the contractor to excavate soil from an adjacent ditch and use that soil to enlarge an existing levee (supp. R4, tab 1 at 02318-a, § 02332). As originally designed, the levee was required to be constructed to a grade of elevation + 12.5' (supp. R4, tab 43, Drawing No. 8).

2. The excavation and embankment work was addressed in the bid schedule as a work item for "Embankment, Compacted Fill" at contract line item number (CLIN) 0004 (embankment work), with an estimated quantity of 197,200 cubic yards (CYs) of material to be placed (supp. R4, tab 1 at 00010-3). The bid schedule contained no separate line item for the contractor's work in excavating the embankment material from the borrow source, nor for processing the material prior to placement. Instead, the cost and payment for this part of the job was included within the embankment work line item. In addition, Section 02332 provided that the contractor would only be paid for the embankment work for the amount of cubic yards of material measured and placed on the levee. (Supp. R4, tab 1 at 02318-1, 02332-3). The specifications did allow for payment of embankment placed that was the subject of settlement, but only if the contractor installed settlement gages in accordance with the terms of the contract. The contract provided that the contractor will forfeit payment for settlement if settlement gages (settlement plates) are not installed ''in strict accordance" with the specifications and drawings (supp. R4, tab 1 at 02332-4, ~ 1.4.3). RLB elected not to install settlement plates (tr. 1168-70).

3. The solicitation contained the standard contract plans and specifications found in most levee construction projects but additionally imposed special requirements on the project that increased the complexity of the scheduling on the contract (app. 2nd supp. R4, tab 23 at 2). Section No. 02332 of the contract, "Embankment", included the following requirements:

a. The specifications provided that the embankment and berms were to be constructed from the earth obtained from the borrow areas described in Section 02318, "EXCAVATION," and as shown on the drawings (supp. R4, tab 1 at 02332-8, ~ 1.7.1).

b. The "borrow area" of the contract was a drainage ditch located to the east of the levee. Although the distance varied, it was approximately forty (40) feet from the toe of the levee. The borrow area included a mandatory excavation area between Sta. 501 +00 and Sta. 738+00. (Supp. R4, tab 1 at 02318-1, ~ 1.1) However, levee construction was not required for the entire length of the borrow area. Levee construction was only required from Sta. 462+22 to Sta. 596+00. This meant the contractor would construct approximately 13,400 feet oflevee, but the adjacent ditch from which the mandatory borrow would be excavated was some 23,700 feet in length. (Supp. R4, tab 43, Drawing No.8) The levee reach from station 464+00 to station 474+00 (1,000 linear feet) did

2 have additional adjacent borrow, but excavation of that borrow was not mandatory. Also, as depicted in the contract drawings, there was no adjacent borrow along the levee from station 474+00 to station 501+00 (2,700 linear feet). (Supp. R4, tab 43, Drawing No.2)

c. The contract also mandated specific requirements to control the moisture content of the embankment material. The specifications required the contractor to perform the "necessary work in moisture control to bring the material" within the specified moisture content range providing that "[i]fthe material is too wet, it shall either be stockpiled and allowed to drain and/or the wet material shall be processed by disking and harrowing, if necessary, until the moisture content is reduced sufficiently." The contract only allowed placement of borrow material in the levee if it was within+/- 10% of the optimal moisture content, as established by testing. 2 The contract required that RLB perform testing to establish the optimal moisture content of the material to be placed in the levee. (Supp. R4, tab 1 at 02332-8, ~ 1.7.3, at 02332-5, ~ 1.5.1(10); tr. 1/160-61)

d. The contract drawings identified available processing and stockpiling areas along the levee reach, but also included certain prohibitions. Drawing 8, Note 1, states that processing of material on the protected side of the levee was allowed (except within identified ranges) but subject to certain restrictions. Processing of material could not exceed 2 feet in height and could be placed no closer than 10 feet from the natural bank line ofthe ditch. Drawing 8, Note 4, states "PROCESSED MATERIAL AND TEMPORARY STOCKPILES IN THIS AREA TO BE NO CLOSER THAN 10FT FROM TOP OF CUT AT ALL TIMES." Drawing 8, Note 5, states "TEMPORARY STOCKPILES AND PROCESSING MATERIAL SHALL NOT BE ALLOWED OR PERMITTED IN OR ON ANY CONSTRUCTED LEVEE FILL." (Supp. R4, tab 43, Drawing No.8)

e. There were also restrictions on the method used to place material. The contract required the embankment to be placed in layers and specification Section 02332, ~ 3.2.1, states in relevant part "Layers shall be started full out to the slope stakes and shall be carried substantially horizontal and parallel to the levee centerline with sufficient crown or slope to provide satisfactory drainage during construction." This latter provision

2 Mr. Boyd explained the concept of optimal moisture content during the hearing (tr. 1141-42). It is our understanding that the concept can be summarized as follows: Any sample of soil will retain water. For any sample there is a percentage of moisture, as a proportion of the weight of the solid material, at which it is at its maximum compactibility, as determined by a standard compaction test.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
RLB Contracting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rlb-contracting-inc-asbca-2014.