RL Mechanical, Inc. v. The RC Company, Inc.

Superior Court of Pennsylvania·Decided July 8, 2019·No. 2934 EDA 2018·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

RL MECHANICAL, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA

Appellant :

:

:

v. :

:

:

RC COMPANY, INC. : No. 2934 EDA 2018

Appeal from the Judgment Entered, September 6, 2018, in the Court of Common Pleas of Chester County, Civil Division at No(s): 2015-11798-CT.

BEFORE: KUNSELMAN, J., MURRAY, J., and PELLEGRINI*, J. MEMORANDUM BY KUNSELMAN, J.: FILED JULY 08, 2019 RL Mechanical, Inc., Subcontractor, appeals from the judgment entered against it on its claims for breach of contract and violation of Pennsylvania’s Contractor and Subcontractor Payment Act and in favor of the RC Company, Inc., General Contractor, for breach of contract and related claims. Upon review, we affirm.

The trial court set forth detailed findings of fact in its decision. Briefly, we note that this case arises out of contractual dealings between the parties on two projects, the Vivarium Project and the Dental Office Project. RC served as the General Contractor; RL served as the Subcontractor to design and install HVAC systems. For each project, General Contractor and Subcontractor entered into a purchase order with general conditions and a subcontractor agreement. Disputes between the parties arose over each party’s compliance

* Retired Senior Judge assigned to the Superior Court.

with the contract documents. The Subcontractor filed suit; General Contractor then filed counterclaims. The claims are summarized below.

First, regarding the Vivarium Project, Subcontractor submitted Invoice 3 in the amount of $87,857.10 to General Contractor for payment. This invoice included a balance due for special order equipment in the amount of $65,264.58, which Subcontractor claimed was to be paid up front. However, General Contractor only paid $45,939.58 of the total amount requested.

According to Subcontractor, the payment process employed by General Contractor for Invoice 3 was not consistent with the process used for prior requests. For Invoices 1 and 2, the parties did not follow the payment process terms provided for in their contract. Instead, a representative of General Contractor reviewed the invoice, informed Subcontractor of the amount it disputed, if any, and noted an adjusted amount on the paperwork. General Contractor then issued payment consistent therewith.

However, with respect to Invoice 3, General Contractor did not inform Subcontractor that it disputed any portion of the payment request, and instead just unilaterally adjusted the amount to be paid. Moreover, the amount paid was not consistent with the amount General Contractor’s administrative assistant, Deborah McGreal, had noted on the paperwork. Additionally, General Contractor requested documentation supporting the request which it had not required before. Because General Contractor did not pay in accordance with the usual payment process, Subcontractor claims General Contractor breached the parties’ agreement. Consequently, Subcontractor

suspended performance, and filed suit seeking the balance of the contract due from General Contractor.

General Contractor countered, claiming that Subcontractor did not request payment under Invoice 3 in conformance with the agreement’s payment provisions. According to General Contractor, Subcontractor did not submit the required documentation. Additionally, the contract documents did not provide for prepayment of equipment as Subcontractor had demanded. Consequently, General Contractor only paid the amount it was required to pay pursuant to the terms of the contract documents. Then, because Subcontractor walked off the job, General Contractor claimed it had to hire another contractor, Sebastian and Sons, to complete the project. General Contractor sought damages incurred for having to use another contractor to complete the project at a higher price.

Second, regarding the Dental Office Project, Subcontractor claimed that General Contractor failed to pay the total amount due under the contract, $14,862, for several months. As a result, Subcontractor filed a mechanics’ lien claim. Sometime thereafter, General Contractor paid in full, subject to any claims.

General Contractor countered, claiming that the Subcontractor failed to provide General Contractor with documentation needed to close out the project with the tenant and building owner. Consequently, General Contractor withheld payment. Additionally, Subcontractor failed to install a certain exhaust fan required per the contract documents. General Contractor sought

damages in the amount of $1,600, for the fan that was not installed and the credit General Contractor gave the project owner for not installing it.

Both parties requested attorney’s fees for having to take legal action to recover amounts they claimed were owed under the contract documents.

Following a bench trial, the court found in favor of Contractor and awarded it $8,350 total on its counterclaims for both projects, plus attorney’s fees to be determined. Subcontractor filed post-trial motions, which the trial court denied. The parties then stipulated to General Contractor’s attorney’s fees in the amount of $30,249.29. Judgment was entered in the amount $38,599.29.

Subcontractor timely appealed. Subcontractor and the trial court complied with Pa.R.A.P. 1925.

On appeal, Subcontractor raises the following issues:

1. Did the trial court err in making findings of fact unsupported by substantial evidence, abuse its discretion, and commit errors of law by failing to conclude that the written agreements of the parties were modified by the conduct and course of performance of the parties such that:

(a) [General Contractor’s] failure to make payment as required constituted a material breach of the contract between the parties;

(b) [Subcontractor] was entitled to suspend performance when not paid?

2. Did the trial court made [sic] findings of fact unsupported by substantial evidence, abuse its discretion, and commit errors of law by awarding attorney’s fees to [General Contractor]?

3. Did the trial court make findings of fact unsupported by substantial evidence, abuse its discretion, and commit errors

of law by awarding damages to [General Contractor] for the cost of “completing” the Vivarium Project?

Subcontractor’s Brief at 4. Subcontractor asks this Court to enter judgment in its favor and remand for determination of an award of attorneys’ fees.

Our review in a non-jury case is

limited to a determination of whether the findings of the trial court are supported by competent evidence and whether the trial court committed error in the application of law. Findings of the trial judge in a non-jury case must be given the same weight and effect on appeal as a verdict of a jury and will not be disturbed on appeal absent error of law or abuse of discretion. When this Court reviews the findings of the trial judge, the evidence is viewed in the light most favorable to the victorious party below and all evidence and proper inferences favorable to that party must be taken as true and all unfavorable inferences rejected.

Hart v. Arnold, 884 A.2d 316, 330–331 (Pa. Super. 2005), appeal denied, 897 A.2d 458 (2006) (citations omitted). “The [trial] court’s findings are especially binding on appeal, where they are based upon the credibility of the witnesses, unless it appears that the court abused its discretion or that the court’s findings lack evidentiary support or that the court capriciously disbelieved the evidence.” Id. (citations omitted). “Conclusions of law, however, are not binding on an appellate court, whose duty it is to determine whether there was a proper application of law to fact by the lower court.” Tagliati v. Nationwide Ins. Co., 720 A.2d 1051, 1053 (Pa. Super. 1998), appeal denied, 740 A.2d 234 (1999). “With regard to such matters, our scope of review is plenary as it is with any review of questions of law.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

RL Mechanical, Inc. v. The RC Company, Inc., (Pa. Ct. App. 2019).

RL Mechanical, Inc. v. The RC Company, Inc. (RL Mechanical, Inc. v. The RC Company, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eichman v. McKeon
824 A.2d 305 (Superior Court of Pennsylvania, 2003)
Hart v. Arnold
897 A.2d 458 (Supreme Court of Pennsylvania, 2006)
Widmer Engineering, Inc. v. Dufalla
837 A.2d 459 (Superior Court of Pennsylvania, 2003)
McMullen v. Kutz
985 A.2d 769 (Supreme Court of Pennsylvania, 2009)
Levicoff v. Richard I. Rubin & Co.
196 A.2d 359 (Supreme Court of Pennsylvania, 1964)
Tagliati v. Nationwide Insurance
720 A.2d 1051 (Superior Court of Pennsylvania, 1998)
Magar v. Lifetime, Inc.
144 A.2d 747 (Superior Court of Pennsylvania, 1958)
Rohm & Haas Co. v. Continental Casualty Co.
732 A.2d 1236 (Superior Court of Pennsylvania, 1999)
Reott v. Asia Trend, Inc.
7 A.3d 830 (Superior Court of Pennsylvania, 2010)
Foster v. Maritrans, Inc.
790 A.2d 328 (Superior Court of Pennsylvania, 2002)
In re Estate of Bowman
797 A.2d 973 (Superior Court of Pennsylvania, 2002)
Hart v. Arnold
884 A.2d 316 (Superior Court of Pennsylvania, 2005)
Reott v. Asia Trend, Inc.
55 A.3d 1088 (Supreme Court of Pennsylvania, 2012)