RJ Ducote Contractor, Inc. v. LH Bossier, Inc.
This text of 192 So. 2d 179 (RJ Ducote Contractor, Inc. v. LH Bossier, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
R. J. DUCOTE CONTRACTOR, INC.
v.
L. H. BOSSIER, INC., et al.
Court of Appeal of Louisiana, First Circuit.
*180 Richard B. Sadler, Jr., of Provosty, Sadler & Scott, McSween & McSween, Alexandria, for appellant.
Charles Wm. Roberts, of Burton, Roberts & Ward, Baton Rouge, for appellees.
Before LANDRY, ELLIS and BAILES, JJ.
LANDRY, Judge.
Defendant L. H. Bossier, Inc. (Bossier) and its surety, National Surety Corporation (National), have taken this appeal from the judgment of the trial court awarding plaintiff R. J. Ducote Contractor, Inc. (Ducote) judgment in the sum of $9,060.01 (less a credit hereinafter indicated) for alleged breach of a contract wherein Ducote subcontracted to perform all dirt work required in the construction of a state highway project on which Bossier was prime contractor. The trial court also awarded appellee legal interest on the amount of the judgment from March 21, 1961, until paid, together with 10% additional as attorney's fees pursuant to LSA-R.S. 38:2246, appellee having duly filed a lien against the project in question.
We find the judgment of the trial court must be amended to allow appellants credit in the further sum of $2,500.00 as will hereinafter appear.
The agreement between Bossier and Ducote was verbal which circumstance was the primary cause of this litigation. The precise issue before the court is the difference of opinion between the parties regarding the manner in which Ducote was to be paid for work performed under the subcontract.
All parties concerned agree that payments to Bossier under the prime contract, which was to build a by-pass on U. S. Highway 165 pursuant to agreement with the Department of Highways of the State of Louisiana (Department), were to be based and made upon monthly estimates of items completed. It is also conceded that the estimates were to be made by the project engineer employed by the State, in this case, Walter Reese Overton (Overton). Both appellants and appellee likewise acknowledge that the estimates, according to custom in the trade, were made on or about the 20th or 21st of each month and reflected all project items completed since the last preceding estimate.
*181 Appellee contends the terms of the subcontract provided that Ducote would be paid the agreed subcontract unit prices on all work performed based upon the monthly estimates of the project engineer, irrespective of whether the work was in fact satisfactorily completed and formally accepted by the Department at the time of each such estimate. Appellants contend, however, that appellee was to be paid only upon satisfactory completion and acceptance by the Department of each contract item regardless of the monthly estimates approved by the project engineer and the sums paid thereunder to the prime contractor. Additionally, appellants aver the work performed by appellee pursuant to item four (hereinafter discussed in some detail) was incomplete and improperly executed. On this ground appellants filed a reconventional demand seeking judgment against appellee in the sum of $6,865.59. Said reconventional demand is founded on the premise that Bossier finished the work at a cost of $13,454.16 and has a further claim against Ducote in the admitted sum of $2,471.44, which total claim is entitled to a credit of $9,060.01, said latter sum being the amount to which Ducote was entitled had he finished the work according to the agreement.
The contract between Bossier and the Department is dated March 30, 1960. Subsequently, on July 31, 1960, the verbal subcontract was confected between Bossier and Ducote. It is conceded that as the work progressed Bossier received four stage payments from the Department predicated upon monthly estimates submitted by Overton. As each of the four payments were received by Bossier, said appellant in turn paid Ducote the unit subcontract price of such estimates in stage payments in similar fashion. It is acknowledged that the fourth and last payment made to Ducote by Bossier was on December 14, 1960, for work performed by Ducote as per the estimate of the project engineer made November 25, 1960. Thereafter a statement was presented to Bossier by Ducote under date of December 16, 1960, covering work performed subsequent to November 25, 1960, in the sum of $9,060.01. For all practical purposes the aforesaid statement may be considered a request by Ducote for payment of item 5 under the subcontract. Although Bossier received payment of item number 5 from the Department in January, 1961, Bossier nevertheless declined to pay Ducote the amount due under said item contending that certain work done by Ducote and previously paid for under item 4 had been rejected by the project engineer as unsatisfactory. On this basis Bossier contended it was justified in withholding further payments to Ducote until item 4 was satisfactorily completed. Appellee took the position that Bossier's refusal to pay constituted an active breach of the contract which required payment to appellee pursuant to the estimates of the project engineer and on this ground refused further performance.
Appellants' primary contention is that the trial court erred in concluding the terms of the verbal subcontract provided that Ducote be paid on the basis of the monthly estimates of the project engineer rather than on the basis of completed and accepted items of work.
The contract in question being verbal in nature, its terms can only be established by parol evidence. As is to be expected, the testimony of appellant and appellee on this vital issues is in conflict. In substance Ducote and his witnesses testified that in accordance with custom in the industry, it is usual for the subcontractor on such a project to be paid his bid unit price based on the monthly estimates of the project engineer, which arrangement was in fact agreed to by the parties in the present case. The witnesses summoned by appellant Bossier, however, denied the arrangement contended for by appellee and averred the parties agreed that appellee would be paid only upon completion and acceptance by the Department of each item for which the *182 subcontractor submitted a statement for payment.
The only disinterested witness to testify concerning this crucial issue was Overton. While his testimony does not expressly confirm or corroborate that of appellee, nevertheless we discern therefrom the clear impression that, as contended by appellee, it is customary in the industry that a subcontractor be paid on the basis of monthly estimates submitted by the project engineer on work of this nature. We conclude, therefore, as did our colleague below, the evidence preponderates in favor of the contention of appellee regarding the terms of the verbal subcontract insofar as they relate to the method of payment to Ducote.
Counsel for appellants contends that permitting the decision of the lower court to stand in favor of appellee will have an undesirable and unwholesome effect upon the road construction industry in this state inasmuch as it gives a subcontractor the same legal relationship with the owner of the project as is enjoyed by the prime contractor. In this connection, counsel also argues that the effect of the decision of the trial court is to require payment to the subcontractor without consideration and against such eventuality the prime contractor has no protection because customarily subcontractors are not required to furnish performance bonds.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
192 So. 2d 179, 1966 La. App. LEXIS 4586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rj-ducote-contractor-inc-v-lh-bossier-inc-lactapp-1966.