RIVERVIEW CONSTRUCTORS, LLC v. RCS LEARNING CENTER, INC., & Others (And a Consolidated Case).

Massachusetts Appeals Court·Decided March 18, 2025·No. 23-P-1386·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-1386

RIVERVIEW CONSTRUCTORS, LLC

vs.

RCS LEARNING CENTER, INC., & others1 (and a consolidated case2).

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This construction dispute originated in a failed real

estate deal by which defendants RCS Learning Center, Inc. and

RCS, Behavioral and Educational Consulting LLC (collectively,

RCS) planned to purchase adjacent parcels of land in Framingham

(the property) from defendants Northside LLC and Ann B. Pratt,

trustee of the Nobscot Realty Trust (collectively, Nobscot). Before RCS and Nobscot consummated that transaction, RCS contracted, with Nobscot's written consent, for plaintiff Riverview Constructors, LLC (Riverview), to build a school on the property. After Riverview and a subcontractor, Maine Drilling & Blasting, Inc. (Maine Drilling), performed work, the defendants' real estate deal fell apart, leading to this and other litigation.3 Riverview filed suit in Superior Court against RCS for breach of contract and related claims, and against Nobscot to enforce its mechanic's lien on the property.4 Maine Drilling filed suit against Riverview, RCS, and Nobscot to enforce its mechanic's lien on the property.5 The cases were consolidated for a jury trial.6 The jury returned a special verdict finding RCS in breach of a written

contract for $1.6 million and the corresponding covenant of good faith and fair dealing, causing Riverview damages of $530,190; and in breach of an implied contract for work pursuant to a change order, for which Riverview was entitled to recover $149,000 in quantum meruit. Judgment entered for Riverview.

RCS filed motions for a new trial and for judgment notwithstanding the verdict, arguing that Riverview did not prove the existence of a contract for $1.6 million or RCS's breach of that contract, Riverview failed to plead and prove damages, and the judge erred in instructing the jury on damages. Nobscot moved for discharge of the mechanic's liens of Riverview and Maine Drilling, arguing that neither had a written contract with Nobscot, and alternatively that any contract between Riverview and Nobscot was limited to a contract price of $84,500. The judge denied the postjudgment motions. RCS and Nobscot appeal, making those same contentions. We affirm.

Discussion. 1. Sufficiency of evidence of contract. RCS and Nobscot challenge the sufficiency of the evidence underlying Riverview's contract claims.

a. Scope of contract. RCS and Nobscot argue that any contract between RCS and Riverview permitted Riverview to perform only $84,500 worth of work and not the entire $1.6 million contract price.

In June 2016, Riverview sent RCS a site work proposal listing thirty-three categories of work it would perform to build the school on the property. The proposal specified that Riverview's "Total Base Bid" was in the amount of $1.6 million.

RCS's project manager Peter Cullinan drafted a "letter of intent to contract " (letter of intent) that incorporated by reference Riverview's proposal. Cullinan did not draft a formal contract because RCS did not have financing in place and, as the letter of intent stated, "final value engineering and construction details remain to be resolved." On August 17, 2016, principals for RCS, Nobscot, and Riverview signed the letter of intent. The letter of intent stated that, "with the consent of [Nobscot]," RCS was authorizing Riverview to start building the school by performing the first six items listed on Riverview's proposal, not to exceed a cost of $84,500. The letter of intent stated, "Work is to be initiated as soon as possible, and if the project is placed on hold for reasons not in [Riverview]'s control, [it] shall be compensated for the costs [it] has incurred to the point of stoppage."

Riverview began work in August 2016, and submitted monthly applications for payment to RCS. Each of Riverview's payment applications stated that the "ORIGINAL CONTRACT SUM" was $1.6 million. For several months, RCS paid Riverview promptly. By the end of October, the total amount that Riverview had billed

and RCS had paid was more than twice the $84,500 amount set forth in the letter of intent. Cullinan testified that the work continued beyond the scope of the first six items listed on the letter of intent because "RCS wanted to continue to proceed." RCS's president, Denise Rizzo-Ranieri, testified that RCS paid Riverview because RCS had agreed to the payments and wanted to "make good" on the work Riverview had done, with which she was content.

The scope of the parties' agreement was a question of fact for the jury. See Situation Mgt. Sys., Inc. v. Malouf, Inc., 430 Mass. 875, 879 (2000). The letter of intent signed by principals for RCS, Nobscot, and Riverview sufficed to establish a meeting of the minds on the material terms of the contract. The letter of intent stated that Riverview was authorized "to initiate the development of the Project," a term defined earlier in the letter to mean the building of the entire school. See Sea Breeze Estates, LLC v. Jarema, 94 Mass. App. Ct. 210, 215 (2018) (mutual assent occurs where there is offer by one party and acceptance by other "in the terms in which [the offer] is made" [citation omitted]). The jury was not required to believe that RCS and Nobscot only agreed to six items of work at a cost of $84,500, especially because RCS paid Riverview far more than that amount, on invoices referencing $1.6 million as the "ORIGINAL CONTRACT SUM." The jury could find that, by their

course of conduct, the parties excused the failure to execute a formal contract as contemplated by the letter of intent. See Situation Mgt. Sys., Inc., supra at 878-879; Prism Group, Inc. v. Slingshot Tech. Corp., 104 Mass. App. Ct. 785, 796 n.7 (2024).

b. Maine Drilling's blasting work. Riverview's proposal, which was incorporated by reference into the letter of intent, listed an alternate task, "Drill Blast & Remove Ledge Boulders," for the amount of $343,062 that was included within the $1.6 million contract price. [In late September 2016, RCS authorized that blasting work. Riverview subcontracted the blasting to Maine Drilling, which performed that work between December 2016 and early March 2017. The parties stipulated that Riverview and Maine Drilling's subcontract was worth $285,973.14, of which Riverview had paid $28,000, leaving a balance of $257,973.14.

RCS's president testified that RCS "agreed to do the blasting" and that she knew that Maine Drilling was performing that work. The letter of intent signed by principals for both RCS and Nobscot incorporated by reference Riverview's proposal describing the drilling and blasting work. Nobscot never questioned why blasting work was being done on its property.

Based on the evidence, the jury could have found that RCS authorized Riverview to subcontract Maine Drilling's work. To prove that Nobscot consented to Maine Drilling's work,

Free access — add to your briefcase to read the full text and ask questions with AI

RIVERVIEW CONSTRUCTORS, LLC v. RCS LEARNING CENTER, INC., & Others (And a Consolidated Case)., (Mass. Ct. App. 2025).

RIVERVIEW CONSTRUCTORS, LLC v. RCS LEARNING CENTER, INC., & Others (And a Consolidated Case). (RIVERVIEW CONSTRUCTORS, LLC v. RCS LEARNING CENTER, INC., & Others (And a Consolidated Case).) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Blake v. Commissioner of Correction
532 N.E.2d 671 (Massachusetts Supreme Judicial Court, 1989)
City of Lawrence v. Falzarano
402 N.E.2d 1017 (Massachusetts Supreme Judicial Court, 1980)
Laurin v. DeCarolis Construction Co., Inc.
363 N.E.2d 675 (Massachusetts Supreme Judicial Court, 1977)
Anthony's Pier Four, Inc. v. HBC ASSOCIATES
583 N.E.2d 806 (Massachusetts Supreme Judicial Court, 1991)
Trace Construction, Inc. v. Dana Barros Sports Complex, LLC
945 N.E.2d 833 (Massachusetts Supreme Judicial Court, 2011)
Lightlab Imaging, Inc. v. Axsun Technologies, Inc.
13 N.E.3d 604 (Massachusetts Supreme Judicial Court, 2014)
Situation Management Systems, Inc. v. Malouf, Inc.
724 N.E.2d 699 (Massachusetts Supreme Judicial Court, 2000)
Ayash v. Dana-Farber Cancer Institute
822 N.E.2d 667 (Massachusetts Supreme Judicial Court, 2005)
Baudanza v. Comcast of Massachusetts I, Inc.
912 N.E.2d 458 (Massachusetts Supreme Judicial Court, 2009)
Friedman v. Globe Newspaper Co.
646 N.E.2d 159 (Massachusetts Appeals Court, 1995)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Globe Newspaper Co. v. Ayash
546 U.S. 927 (Supreme Court, 2005)