Riverdale Mills Corp. v. United States

345 F. Supp. 2d 50, 59 ERC (BNA) 1655, 2004 U.S. Dist. LEXIS 23915, 2004 WL 2711300
District Court, D. Massachusetts·Decided November 1, 2004·No. CIV.A. 00-40137-NMG·Published·Cited by 1 cases

Opinion

MEMORANDUM OF DECISION

GORTON, District Judge.

On August 8, 2000 Plaintiffs filed the instant action under the Federal Tort *52 Claims Act, 28 U.S.C. § 2671 et seq. (“the FTCA”), alleging that the United States of America, through its agents, maliciously prosecuted them by bringing criminal charges against Plaintiffs for alleged violations of the Clean Water Act, 33 U.S.C. § 1251 et seq. The parties appeared for trial before this Court, sitting without a jury, on July 22, 2004, and three subsequent trial days. The Court now announces its findings of fact and conclusions of law.

I. Findings of Fact

1) Riverdale Mills Corporation (“RMC” or “Riverdale Mills”) and its principal owner, James M. Knott, Sr. (“Knott”) operate a plant in Northbridge, Massachusetts which manufactures zinc galvanized, plastic-coated, welded steel wire mesh. The production involves two processes, one that produces acidic wastewater (“the galvanizing line”) and the other that produces caustic, or alkaline, wastewater (“the coating line”). RMC ultimately discharges that industrial wastewater into the public sewer owned by the Town of Northbridge.

2) Knott owns the land and building where the facility is located, including the private roadway between the building and the millpond across the roadway, and RMC leases the building from Knott.

3) In 1997, Riverdale Mills constructed a system to insure that the wastewater from its operations was treated before being discharged from the building. The system was designed to combine the two streams of wastewater inside the plant and add a caustic soda to them so that metals would be precipitated out of the wastewa-ter and so that when the acidic water was released it would be within the pH limits set by law and by RMC’s permit. That process is known as “pretreatment”.

4) Following pretreatment, described above, according to the design of the pretreatment system, the now-combined wastewaters would flow intermittently through a pipe to a manhole just outside the building on Riverdale Street (“Manhole # 1”), where it joins a sewer pipe. The discharge would then flow through that pipe for approximately 300 feet to a second manhole (“Manhole #2”) where the pipe joins a public trunk sewer line which ultimately discharges at the Town of North-bridge’s treatment plant.

5) In late summer of 1997, the Environmental Protection Agency (“EPA”), Region 1 received an anonymous letter purporting to be from an RMC employee, “WWT operator/lst shift”. The letter asserted that the company had allowed its treatment facility to fall into disrepair and reported that the plant’s wastewater pretreatment system was not functioning, that no one at the plant was assigned to operate or maintain the system and that the writer was concerned that the company was violating wastewater pretreatment standards for zinc, iron and pH because it was discharging wastewater without pretreatment. The letter was routed inside the EPA to both the Criminal Investigation Division (“CID”) and, through the Office of Environmental Stewardship, to the Office of Environmental Measurement and Engineering (“OEME”) in Lexington, Massachusetts.

6) OEME is composed of environmental engineers who conduct inspections of, among others, industrial users identified by the Office of Environmental Stewardship and also provide technical assistance to the Agents of the CID. Lacking powers of arrest and search, OEME employees are not law enforcement officers as that term is defined in the FTCA. CID is staffed by Special Agents who are such law enforcement officers, i.e. they are authorized by law to conduct searches and to make arrests in the course of investiga *53 tions of violations of federal environmental statutes which Congress has determined should carry criminal as well as civil sanctions.

7) When OEME received its copy of the anonymous letter with the request that it conduct a compliance inspection of RMC, Team Leader Elizabeth Deabay (“Dea-bay”) assigned Inspectors Karen Baker (“Baker”) and Justin Pimpare (“Pimpare”) to conduct an inspection. The inspection was scheduled for October 21, 1997. At CID, Special Agent Stephen Creavin (“SA Creavin”) was given a copy of the anonymous letter by his supervisor and was assigned to look into the matter. SA Creavin recorded the letter as a “lead”, the term used inside CID to refer to information which warranted further inquiry in order to determine whether an investigation should be undertaken.

8) On October 21, 1997, Inspectors Baker and Pimpare traveled from the Lexington lab to Riverdale Mills in Northbridge, Massachusetts. At some time that morning, prior to the beginning of the inspection, Deabay received word of a medical emergency in Baker’s family and, as a result, she assigned Inspector Daniel Granz (“Granz”) to go to Riverdale Mills instead of Baker.

9) Granz had not heard of Riverdale Mills or Knott prior to being assigned replace Baker on the inspection. He did not talk to SA Greavin before he went to Riverdale Mills on October 21, 1997 nor did he see the anonymous letter before 12:00, Noon of that day. When Granz arrived at Riverdale Mills, an “initial conference” involving Inspector Pimpare, Knott and two Riverdale Mills employees, Brian Benoit (“Benoit”) and Dennis Veader (“Veader”), was in progress and was nearing conclusion.

10) On October 21, 1997, Knott consented to an inspection of the RMC plant on the express condition that the inspectors be accompanied at all times by designated representatives of RMC so that they could personally witness whatever the EPA agents observed or sampled.

11) Prior to Granz’s arrival, Knott explained to Pimpare that the Riverdale Mills wastewater treatment system included mixing two separate streams of process wastewater in a tank so that the pH would be raised, the metals would drop out and the precipitated metals would be put through a filter press and taken to a landfill.

12) The inspection that day confirmed, however, that, as alleged in the anonymous letter, the wastewater pretreatment system was not operational and apparently had not been so for some time. There were no operating manuals, monitoring or maintenance records or logs of any kind available in the area. Many parts were either disconnected or in disrepair. River-dale Mills Executive Vice President Paul McGuann (“McGuann”) was present with the inspectors when they looked at the wastewater pretreatment systems and he later compiled a list of several repairs and replacement parts that were needed to bring the system into compliance and proposed a schedule for completion of the project by mid-December 1997. The scheduled tasks included plans to “connect coating line to mix tank # 1” and to “determine current piping scheme to get coating to mix tank # 1”. Another task was to “create a documented WWT piping schematic for the current input sources”.

13) During the morning of October 21, 1997, the Inspectors informed Knott that, as part of the inspection, they wanted to take samples of RMC’s wastewater discharge. After their initial morning conference, Knott led them to Manhole # 1 and

Free access — add to your briefcase to read the full text and ask questions with AI

Riverdale Mills Corp. v. United States, 345 F. Supp. 2d 50, 59 ERC (BNA) 1655, 2004 U.S. Dist. LEXIS 23915, 2004 WL 2711300 (D. Mass. 2004).

345 F. Supp. 2d 50 (Riverdale Mills Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Riverdale Mills Corp. v. Pimpare
392 F.3d 55 (First Circuit, 2004)