Rivera De Leon v. Maxon Engineering Services, Inc.

283 F. Supp. 2d 550, 2003 U.S. Dist. LEXIS 16795, 2003 WL 22175745
CourtDistrict Court, D. Puerto Rico
DecidedSeptember 19, 2003
DocketCIV. 00-2350(SEC)
StatusPublished
Cited by37 cases

This text of 283 F. Supp. 2d 550 (Rivera De Leon v. Maxon Engineering Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivera De Leon v. Maxon Engineering Services, Inc., 283 F. Supp. 2d 550, 2003 U.S. Dist. LEXIS 16795, 2003 WL 22175745 (prd 2003).

Opinion

OPINION AND ORDER

CASELLAS, District Judge.

The Court has before it Defendants’ motion to dismiss seeking dismissal of the Miller Act claim for lack of subject matter jurisdiction, and dismissal of the breach of contract cause of action for failure to state a claim. (Docket #57). Upon careful review of the matter before us, the parties’ arguments and the Magistrate Judge’s Report and Recommendation, the Court concludes that Defendants’ Motion to Dismiss must be GRANTED in part and DENIED in part.

Factual Background

Plaintiff filed the present action on October 19, 2000, seeking judgment ordering Defendants to fulfill their contractual obligations, and awarding him compensatory damages for alleged breach of contract, costs and reasonable attorney’s fees. On February 20, 2001, Plaintiff filed an amended complaint, under the Miller Act, 40 U.S.C. § 270a-270e, seeking recovery of a surety bond (payment bond) due to al *552 leged failure of payment and breach of contract. Pursuant to 28 U.S.C. § 1367(a), the supplemental jurisdiction statute, Plaintiff also brought claims under the Commonwealth’s tort and breach of contract statutes. Plaintiff alleges that he is a second-tier subcontractor to a construction services contract entered between the United States of America and, a joint venture, composed of Perini Jones, Inc. and Perini International (“Perini”). The contract at issue pertains to two construction projects at the U.S. Naval Station in Roosevelt Roads. The construction projects object of the contract involved demolition and underwater construction work at two sites on the Naval Base identified as (1) Bulkhead Charlie and (2) Pier Three. Defendants Perini (“the prime contractor”) proceeded to subcontract the services of Maxon Engineering Services, Inc. (“first tier subcontractor”), corporation which proceeded to subcontract the services of the Plaintiff (“second tier subcontractor”) to perform the construction.

Plaintiff states that during February of 2000, Maxon approached him and requested a bid proposal regarding the Bulkhead Charlie and Pier Three projects for consideration. Plaintiff states that he prepared and submitted said proposals for both projects including a detailed breakdown of payments for expenses incurred for mobilization, materials, labor, equipment, etc. In April of 2000, Maxon approved said proposal and the payment schedule submitted by Plaintiff, and the parties subsequently entered into an oral agreement through which plaintiff became obliged to perform the stipulated repairs and constructions on the two projects, and Maxon was bound to make the agreed payments. Under the terms of the agreement Plaintiff was responsible for furnishing the materials and equipment for the projects. Additionally, furnished Maxon with a photo analysis of the projects, and an invoice of the materials and equipment required in order to begin work. The parties allegedly agreed to estimate the construction costs and Plaintiffs service fee at $ 186,-000.00 for the Bulkhead Charlie project, and $ 240,000.00 for the Pier Three project.

Plaintiff alleges that once the service agreement was reached, Maxon required that Plaintiff have his employees on the project site within twenty four (24) hours. Plaintiff states that he requested Maxon provide a written contract of the agreement, and that Maxon allegedly “promised and represented” that it would provide said document along with an initial payment. On April 17, 2000, Plaintiff began pre-construction excavation and demolishing at the Bulkhead Charlie project site. After several weeks of working at the site, Plaintiff submitted a bill statement to Maxon for payment. Maxon failed to render payment.

In May of 2000, Perini Jones allegedly required that Plaintiff discontinue his original demolition plan at Bulkhead Charlie in order to excavate and locate tie rods. According to Plaintiff, said request entailed work not comprised in the service agreement. In response to the request, Plaintiff informed Maxon that the additional work represented a change order, and thus an adjustment of payment was necessary. Maxon allegedly agreed to pay the additional charges, proffering that payment would be made on May 9, 2000. Maxon failed to render payment.

On June 12, 2000, Maxon informed Plaintiff that his services were being terminated. Plaintiff alleges that he had complied with his obligations under the agreement entered with Maxon in April of 2000. Said termination prevented Plaintiff from completing construction at the Bulkhead Charlie project, and also prevented *553 him from commencing work on the Pier Three project. Neither Maxon nor Perini Jones have rendered any payment to Plaintiff for works performed. Plaintiff argues that he provided the Co-defendants with proper notice of failure to make payments.

Plaintiff also argues that both the unjustified termination and Co-defendants’ failure to remunerate him for work previously performed constitute a breach of contract. Plaintiff asserts that both Co-defendants, Perini and Maxon, jointly and intentionally, made misrepresentations aimed at leading him to agree to provide his services at the two projects. Plaintiff adds that Maxon’s sole intention in contracting his services was to protect its interests in the subcontract with Perini, not to contract a reliable party to complete the repairs and constructions at the two projects, as was represented. Additionally, Plaintiff states that, once Maxon felt that its subcontract with Perini was stable, it terminated Plaintiff’s contract. Thus, Plaintiff argues that both Maxon and Peri-ni Jones are responsible for the breach of contract.

On February 20, 2001, Defendants Peri-ni Jones, Inc. and Perini International filed a Motion to Dismiss under Rules 12(b)(1) and 12(b)(6) of the Federal Rules of Civil Procedure (Docket # 16). On March 12, 2001, Defendants filed a memorandum of law in support of their motion to dismiss (Docket # 18). On April 16, 2001, Plaintiff filed an opposition to Defendants’ motion to dismiss (Docket #23). On May 21, 2001, Defendants filed a reply to Plaintiffs’ opposition (Docket #27). On June 22, 2001 and July 6, 2001, respectively, Plaintiff filed a sur reply and a supplemental sur reply to the Defendants’ reply to Plaintiffs opposition to Defendants’ motion to dismiss (Docket ##39 and 44). On August 22, 2001, the Court entered an Order denying without prejudice Defendants’ motion to dismiss (Docket # 16), and granted Plaintiff thirty (30) days to conduct limited discovery regarding the issue of waiver of the surety bond required under the Miller Act (Docket ##47 and 48).

On March 26, 2002, Defendants Perini Jones, Inc. and Perini International filed a renewed motion to dismiss under Rules 12(b)(1) and 12(b)(6) of the Federal Rules of Civil Procedure, accompanied by a memorandum of law in support of said motion (Docket # 57). On April 24, 2002, Plaintiff filed a memorandum in support of the application of the federal enclave jurisdiction doctrine (Docket #62).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Solis v. Lorraine Enterprises
907 F. Supp. 2d 186 (D. Puerto Rico, 2012)
United States v. Lopez-Diaz
872 F. Supp. 2d 120 (D. Puerto Rico, 2012)
Rosado-Gonzalez v. Alejandro Otero Lopez Hospital
836 F. Supp. 2d 48 (D. Puerto Rico, 2011)
Brauchitsch-Monedero v. Puerto Rico Electric Power Authority
786 F. Supp. 2d 470 (D. Puerto Rico, 2011)
Melendez-Ortiz v. Wyeth Pharmaceutical Co.
775 F. Supp. 2d 349 (D. Puerto Rico, 2011)
AGOSTO-RAMOS v. Puerto Rico Telephone Co.
743 F. Supp. 2d 30 (D. Puerto Rico, 2010)
Maldonado v. Municipality of Barceloneta
682 F. Supp. 2d 109 (D. Puerto Rico, 2010)
Caracas International Banking Corp. v. United States
670 F. Supp. 2d 142 (D. Puerto Rico, 2009)
Milliman, Inc. v. Health Medicare Ultra, Inc.
641 F. Supp. 2d 113 (D. Puerto Rico, 2009)
United States v. Crespo-Rios
623 F. Supp. 2d 198 (D. Puerto Rico, 2009)
Torres v. Bella Vista Hospital, Inc.
639 F. Supp. 2d 188 (D. Puerto Rico, 2009)
United States v. Armstrong
626 F. Supp. 2d 229 (D. Puerto Rico, 2009)
Vega Colon v. Wyeth Pharmaceutical
611 F. Supp. 2d 110 (D. Puerto Rico, 2009)
Cortes-Rivera v. Department of Correction & Rehabilitation
617 F. Supp. 2d 7 (D. Puerto Rico, 2009)
Matías-Cardona v. VERIZON WIRELESS PUERTO RICO, INC.
610 F. Supp. 2d 157 (D. Puerto Rico, 2009)
Vargas-Colon v. Hospital Damas, Inc.
597 F. Supp. 2d 290 (D. Puerto Rico, 2009)
Amador v. McDonald's Corp.
601 F. Supp. 2d 403 (D. Puerto Rico, 2009)
Rivera-Santiago v. ABBOTT PHARMACEUTICAL PR, LTD.
608 F. Supp. 2d 216 (D. Puerto Rico, 2008)
United States v. Andujar-Ortiz
575 F. Supp. 2d 373 (D. Puerto Rico, 2008)
Ortiz-Feliciano v. United States
566 F. Supp. 2d 71 (D. Puerto Rico, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
283 F. Supp. 2d 550, 2003 U.S. Dist. LEXIS 16795, 2003 WL 22175745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivera-de-leon-v-maxon-engineering-services-inc-prd-2003.