Ritchie Paving, Inc. v. City of Deerfield

67 P.3d 843, 275 Kan. 157
CourtSupreme Court of Kansas
DecidedJanuary 24, 2003
Docket88,675
StatusPublished
Cited by10 cases

This text of 67 P.3d 843 (Ritchie Paving, Inc. v. City of Deerfield) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ritchie Paving, Inc. v. City of Deerfield, 67 P.3d 843, 275 Kan. 157 (kan 2003).

Opinion

*158 The opinion of the court was delivered by

Allegrucci, J.:

Ritchie Paving, Inc. sued the City of Deerfield, Kansas, seeking to recover its expenses in preparing the low, but unsuccessful, bid for a Deerfield street improvement project. The district court granted Deerfield’s motion to dismiss for failure to state a claim upon which relief may be granted. Ritchie Paving appealed. This court transferred the appeal from the Court of Appeals. K.S.A. 20-3018(c).

The following facts are taken from the district court’s decision granting Deerfield’s motion to dismiss and from Ritchie Paving’s petition, the allegations of which were accepted as true by the district court.

On April 17, 2000, Deerfield let bids for a street improvement project. The bid form required a bidder to supply commencement and completion dates within the calendar year 2000 for the project, with the commencement date no later than October 17. The project was to be completed within 75 days.

Ritchie Paving submitted a timely bid for $760,502.20 and specified a commencement date of October 1, 2000. Ritchie Paving’s bid was the lowest bid by more than $31,000. It was rejected.

Deerfield’s bid documents defined “the successful bidder as the lowest, qualified, responsible, and responsive bidder to whom owner makes an award.” The bid documents also stated: “If the contract is to be awarded, award will be to the lowest, responsible, responsive bidder whose evaluation by owner indicates to owner that the award will be in the best interests of the project.”

The following reasons were given on behalf of Deerfield for not accepting Ritchie Paving’s bid:

“1. A high probability that bad weather could delay the completion of the project;
“2. That the grant from the federal government would be lost if the project were not completed by April 1, 2001;
“3. That a dirt hauling agreement between Deerfield and Kearny County required that the project be completed before the end of the summer 2000;
“4. That Deerfield might have to pay a higher interest rate on their bonds because of a later completion date.”

Deerfield’s bid documents did not indicate that any of these factors were to be considered by bidders.

*159 Ritchie Paving sued Deerfield, framing its cause of action as promissory estoppel/detrimental reliance. Neither fraud nor other independent tort was alleged. Ritchie Paving alleged that it relied on the bid documents, that Deerfield knew it would rely on the bid documents, and that Deerfield’s rejection of its bid was based entirely on requirements not stated in the bid documents. Ritchie Paving alleged that it would not have incurred the expenses of preparing and submitting a bid if it had been informed of Deer-field’s requirements. Ritchie Paving sought to recover its expenses of $6,642.50. The question we must answer is whether an unsuccessful low bidder on a public works project has a cause of action for recovery of its bidding expenses absent allegations of fraud or other independent tort.

On a motion to dismiss for failure to state a claim upon which relief can be granted, the question is whether, in the light most favorable to plaintiff and with every doubt resolved in plaintiffs favor, the petition states any valid claim for relief. On appeal, as in the trial court, the questions are ones of law over which this court has unlimited review. Nichols v. Kansas Political Action Committee, 270 Kan. 37, 39, 11 P.3d 1134 (2000).

In granting Deerfield’s motion to dismiss, the district court found Sutter Bros. Constr. Co. v. City of Leavenworth, 238 Kan. 85, 708 P.2d 190 (1985), to be controlling. Comparing Sutter Bros. with the present case, the district court stated:

“There, as in this action, the Plaintiff does not seek to enjoin the award or issuance of the contract, to require new bids to be submitted, or to be awarded the contract. Rather, the Plaintiff seeks only damages sustained by it as a result of not receiving the contract. There is no allegation of fraud or other independent tort in this action. . . .
“Although the Plaintiff attempts to cloak its theory of recovery in promissory estoppels/detrimental reliance theories, the Sutter Brothers court has clearly stated that the bid is no more than an offer and that a contract does not exist until it is accepted.
“We must examine the statements made by the Defendant’s representatives. It is obvious that those factors mentioned by the Defendant’s representatives were concerns of the Defendant when considering the submitted bids. There is no indication in the bid documents that they were requirements for bidding or that *160 they were prerequisites to accepting any successful bid. Clearly, the Defendant’s representatives were mentioning intangibles that were of concern to them, and which were apparently answered by the next lowest bidder.
“. . . Kansas has long recognized that the lowest responsible bidder is not merely an objective term. In D. F. Williams v. City of Topeka, 85 Kan. 857, [861-62, 118 Pac. 864 (1911)], the Court adopted with approval the following language: ‘In determining who is the lowest responsible bidder, or the lowest and best bidder, the duty of the board or officer is not merely ministerial, but partakes of a judicial character requiring the exercise of discretion and judgment . . .’ Certainly, the Defendant had the right and the duty to consider those intangible factors which it perceived to be in the best interest of the project and the taxpayers whom it served. Obviously, there had to be a bid which alleviated those concerns and which the Defendant felt more than offset the difference in the bid price.
“The Plaintiff further attempts to cloak its request for expenses in preparation of the bid in terms other than for damages. However, Black’s Law Dictionary, 7th edition, clearly defines actual damages as an amount awarded to a complainant to compensate for proven injuries or loss; damages that repay actual losses. This is, clearly, an action for damages.
“The law does not protect one bidder against another bidder who may be more creative, innovative, or insightful with regard to the project at hand. The Court notes that this case was not filed until December 2000 when the Plaintiff realized in May of 2000 that its bid had been rejected. Certainly, the Plaintiff had the opportunity to follow the preferred method of contesting the award of the bid by seeking injunctive relief in a timely fashion.”

On appeal, Ritchie Paving distinguishes Sutter Bros. from the present case principally on the ground that in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashley Clinic v. Coates
545 P.3d 1020 (Court of Appeals of Kansas, 2024)
State v. McLinn
Supreme Court of Kansas, 2018
State v. Robinson
Supreme Court of Kansas, 2017
Bouton v. Byers
321 P.3d 780 (Court of Appeals of Kansas, 2014)
State v. Weber
304 P.3d 1262 (Supreme Court of Kansas, 2013)
Campbell v. Husky Hogs, L.L.C.
255 P.3d 1 (Supreme Court of Kansas, 2011)
State v. Horn
238 P.3d 238 (Supreme Court of Kansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
67 P.3d 843, 275 Kan. 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ritchie-paving-inc-v-city-of-deerfield-kan-2003.